PUBLIC SERVICE ELECTRIC & GAS COMPANY v. NEWPORT ASSOCIATES DEVELOPMENT COMPANY

CourtDistrict Court, D. New Jersey
DecidedJune 9, 2021
Docket2:16-cv-08445
StatusUnknown

This text of PUBLIC SERVICE ELECTRIC & GAS COMPANY v. NEWPORT ASSOCIATES DEVELOPMENT COMPANY (PUBLIC SERVICE ELECTRIC & GAS COMPANY v. NEWPORT ASSOCIATES DEVELOPMENT COMPANY) is published on Counsel Stack Legal Research, covering District Court, D. New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
PUBLIC SERVICE ELECTRIC & GAS COMPANY v. NEWPORT ASSOCIATES DEVELOPMENT COMPANY, (D.N.J. 2021).

Opinion

UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEW JERSEY

PUBLIC SERVICE ELECTRIC & GAS COMPANY, Plaintiff, v. Civ. No. 16-8445 NEWPORT ASSOCIATES OPINION DEVELOPMENT COMPANY; NEWPORT ASSOCIATES PHASE I DEVELOPERS LIMITED PARTNERSHIP, Defendants.

This matter comes before the Court on three motions: a motion (DE 231) to strike filed by Consolidated Edison Company of New York (“Con Edison”); a motion (DE 235) to strike filed by Public Service Electric & Gas Company (PSE&G); and a cross motion (DE 240) filed by Newport Associates Development Company and Newport Associates Phase I Developers Limited Partnership (“Newport”) for leave to amend its pleading. Having considered the parties’ submissions and having heard oral argument, the motions (DE 231, 235) to strike are GRANTED, and the cross motion (DE 240) for leave to amend is DENIED. I. Background The original complaint was filed in November of 2016. (DE 1.) On December 24, 2020, with consent of all parties, PSE&G filed an amended complaint which reasserted its previously unripe Section 113 CERCLA contribution claim and asserted a breach of contract claim against Con Edison. In response, Newport filed a new answer, counterclaims, and third-party complaint (referred to here as “Newport’s Pleading”), which added new allegations about leaks on lines other than the one directly at issue in this case. (DE 226.) PSE&G and Con Edison (“the Utilities”) each moved to strike Newport’s pleading, arguing that it was filed in violation of Rule 15 and that it circumvents prior limitations on discovery ordered by the Court. Newport opposed these motions and cross moved to amend its answer, third-party complaint, and counterclaims. (DE 240.) A timeline of the relevant procedural history is as follows: • Feb. 2, 2018: Newport filed its initial third-party complaint against Con Edison and counterclaims against PSE&G (DE 72)

• May 21, 2018: Newport filed an amended answer, third-party complaint, and counterclaims (DE 98)

• Jan. 28, 2019: The Court granted Con Edison’s motion to dismiss Counts IV and V (DE 148)

• Aug. 26, 2019: Judge Clark issued a protective order preventing Newport from seeking discovery related to “leaks of dielectric fluid in Con Edison’s facilities,” instead limiting discovery to leaks involving welded couplers on HPFF submarine or terrestrial cables (DE 169) o May 1, 2020: The Court upheld Judge Clark’s decision (DE 191) o Jan. 27, 2021: Judge Clark denied Newport’s motion for reconsideration (DE 221)

• December 24, 2020: PSE&G filed its second amended complaint and amended crossclaims (DE 219)

• Feb. 5, 2021: Newport filed an answer, counterclaims, and third- party complaint (DE 226)

In short, this is not the first time the parties have disputed the relevance of cables beyond the specific cable at issue in this case. During discovery, Newport requested from Con Edison “documents and information detailing every leak of dielectric fluid from any Con Edison facility, with the exception of leaks originating from self-contained fluid-filled cables, without any geographic or temporal limitations.” (DE 169 at 10.) Newport argued that such discovery would shed light on the leak-prone nature of the Cables, the circumstances in which this type of cable leaks, the Utilities’ awareness of the risks of leaks, and the likely resultant harm. (DE 157 at 14). Judge Clark limited discovery to leaks involving high-pressure, fluid-filled (“HPFF”) cables and welded couplers (whether submarine or terrestrial). (DE 169 at 11-12.) Newport also requested documents concerning the B and C Line without limitation, arguing that other leaks or failures anywhere on the Cables could have caused the leak at issue. (DE 157 at 25.) Emphasizing that this action arises out of a discrete leak of dielectric fluid from the particular Hudson River Section of the Cables, Judge Clark found as follows: Documents relating to the “components” of sections of the Cables and surrounding infrastructure beyond the Hudson River Section, such as the East River Section of the Cables, which are installed in a utility tunnel, are not encased in cement jackets or coated in coal tar wrap, and are not joined by welded couplers, would be wholly irrelevant to Newport’s allegations regarding the cause of the leak at issue. (DE 169 at 13.) Judge Clark therefore held that Con Edison was only required to produce the requested information as to the Hudson River Section of the Cables. (DE 169 at 14.) The Utilities now cite to Judge Clark’s ruling to show that allegations regarding leaks on lines outside of the Newport Marina or of leaks not involving HPFF cables and welded couplers are immaterial to the issues surrounding the leak at issue in this litigation. (PSE&G Reply at 11.) II. Discussion a. Rule 15 Newport argues that because its pleading was filed in response to PSE&G’s amended pleading, it did not require leave of the court or consent of the parties under Rule 15. The Utilities argue against the as-of-right approach, and advocate what has been deemed the “moderate approach,” discussed below. Rule 15 governs amended and supplemental pleadings. In relevant part, the Rule provides: (a) Amendments Before Trial. (1) Amending as a Matter of Course. A party may amend its pleading once as a matter of course within: (A) 21 days after serving it, or (B) if the pleading is one to which a responsive pleading is required, 21 days after service of a responsive pleading or 21 days after service of a motion under Rule 12(b), (e), or (f), whichever is earlier. (2) Other Amendments. In all other cases, a party may amend its pleading only with the opposing party's written consent or the court's leave. The court should freely give leave when justice so requires. (3) Time to Respond. Unless the court orders otherwise, any required response to an amended pleading must be made within the time remaining to respond to the original pleading or within 14 days after service of the amended pleading, whichever is later. Fed. R. Civ. P. 15. Rule 15 was amended in 2007 and 2009. Rule 15(a) previously contained the phrasing “in response to,” which the amendments eliminated.1 The amendments also abrogated old Rule 13(f), “leaving Rule 15 as the sole rule governing amendments to pleadings.” Berrada v. Cohen, No. 16574-SDW-LDW, 2017 WL 6513954, at *3 (D.N.J. Dec. 20, 2017), aff'd, No. 16574-SDW-LDW, 2018 WL 1837916 (D.N.J. Apr. 17, 2018). Prior to the 2007 and 2009 amendments, courts had adopted different approaches to the permissibility of a response to an amended pleading: Courts adopting the “narrow” approach held that an amended counterclaim must respond only to the changes made by the amended complaint. The “moderate” approach provides that an amended counterclaim may be filed without Court leave only if the amended complaint to which it [responds] changed the theory or scope of the case, and, accordingly, the amendments to the

1 Prior to its amendment, Rule 15(a) provided that “[a] party shall plead in response to an amended pleading within the time remaining for response to the original pleading or within 10 days after service of the amended pleading.” Fed. R. Civ. P. 15(a) (2006) (repealed 2007) (emphasis added); Berrada v. Cohen, 2017 WL 6513954, at *2. counterclaims must be similar in scope to the amendments made to the complaint. Finally, the permissive approach provides that the defendant always has the right to add new counterclaims when the plaintiff amends the complaint, no matter the scope of those counterclaims. Id. (citations omitted). In Slim CD, decided prior to the 2009 amendment, Judge Wolfson adopted the moderate approach. Slim CD, Inc. v. Heartland Payment Systems, Inc., No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Foman v. Davis
371 U.S. 178 (Supreme Court, 1962)
Alnoraindus Burton v. Partha Ghosh
961 F.3d 960 (Seventh Circuit, 2020)

Cite This Page — Counsel Stack

Bluebook (online)
PUBLIC SERVICE ELECTRIC & GAS COMPANY v. NEWPORT ASSOCIATES DEVELOPMENT COMPANY, Counsel Stack Legal Research, https://law.counselstack.com/opinion/public-service-electric-gas-company-v-newport-associates-development-njd-2021.