Public Service Electric and Gas Company v. Town of Westfield

New Jersey Superior Court Appellate Division·Decided April 14, 2025·No. A-3602-22·Unpublished

Opinion

NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION This opinion shall not "constitute precedent or be binding upon any court ." Although it is posted on the internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.

SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION

DOCKET NO. A-3602-22

PUBLIC SERVICE ELECTRIC AND GAS COMPANY,

Plaintiff-Respondent,

v. TOWN OF WESTFIELD,

Defendant-Appellant.

Argued November 4, 2024 – Decided April 14, 2025 Before Berdote Byrne and Jacobs.

On appeal from the Superior Court of New Jersey, Law Division, Union County, Docket No. L-1092-22.

Scott D. Salmon argued the cause for appellant (Jardim, Meisner, Salmon, Sprague & Susser, PC, attorneys;

Thomas C. Jardim, of counsel; Kenneth L. Winters, on the briefs).

Natalie F. Dallavalle argued the cause for respondent (PSE&G Services Corporation, attorneys; Natalie F.

Dallavalle and Paige Nestel, on the brief).

PER CURIAM The Town of Westfield appeals from the trial court's order awarding summary judgment to Public Service Electric and Gas Company ("PSE&G") and finding Westfield's ordinance, number 2022-04, (the "Ordinance") is partially preempted by state law, specifically Chapter 48 of the New Jersey statutes. On appeal, Westfield contends, for the first time, that the trial court applied the wrong legal test to invalidate its ordinance by using an as-applied rather than facial-challenge analysis. Westfield also argues summary judgment was improper because the trial court impermissibly ruled on a genuine issue of material fact: whether the route chosen for PSE&G's Union County Project (the "Supplemental Project") was essential.

We affirm the trial court as we agree. In re PSE&G1 is directly on point, and requires the partial preemption of Westfield's Ordinance to the extent it conflicts with state and federal law. PSE&G did not seek relief from the trial court on the basis of the unconstitutionality of the Ordinance on either an as- applied or facial basis. Rather, it requested the court find the Ordinance was preempted by relevant sections of Chapter 48 of the New Jersey statutes. Therefore, Westfield's argument regarding whether an as-applied or facial

1 In re Public Service Electric & Gas Co., 35 N.J. 358, (1961).

A-3602-22

analysis should have been applied is irrelevant to the issue of preemption. Westfield's second argument is also improperly before us. Whether the route chosen for the supplemental project was essential was not raised before the trial court. Regardless, the route chosen by PSE&G has no relation to the Ordinance's attempt to control the height of transmission line poles.

I.

PSE&G is New Jersey's largest electric utility provider, serving approximately 2.3 million customers in New Jersey. It is subject to both state regulation by the Board of Public Utilities ("BPU"), and federal regulation by the Federal Energy Regulatory Commission ("FERC") through its delegated authority to PJM Interconnection, LLC ("PJM"). See N.J.A.C. 14:5-1.1; N.J.A.C. 14:5-2.1. As a public utility operating pursuant to Chapter 48 of the New Jersey statutes, one of PSE&G's primary obligations is to "furnish safe, adequate and proper service" across New Jersey. N.J.S.A. 48:2-23; N.J.A.C. 14:3-3.1. To meet this statutory obligation, in 2007, PSE&G initiated an upgrade of existing 26kV power lines—first installed in the 1920s—with 69kV power lines (the "2007 Project"). These higher-voltage lines are intended to address New Jersey's dramatic increase in population and electricity reliance over the preceding one hundred years, as well as meet projected increases in

A-3602-22

demand for the foreseeable future. It is undisputed PSE&G has installed more than 575 miles of 69kV power lines in almost one hundred municipalities since 2007, including nine municipalities in Union County serving approximately 25,000 customers. The only unfinished portion at the time of this appeal was a five-mile stretch in Westfield.

PSE&G's statewide initiative is, in turn, part of a broader multistate effort governed by federal law and regulations that seeks to prevent the loss of electric power exceeding twenty-four hours to utility customers nationwide. In 2017, PJM, on behalf of FERC, determined PSE&G's existing transmission lines supplying electricity to two Union County substations were in violation of several federal reliability criteria. PSE&G responded by creating a plan to enhance and strengthen its existing statewide initiative (the "2017 Project"), which PJM approved on behalf of FERC. The 2017 Project requires PSE&G to replace existing thirty-five-feet-tall utility poles with poles ranging from between sixty-five and seventy-five feet in height. The National Electrical Safety Code mandates poles carrying 69kV power be between sixty-five and seventy-five feet in length to meet certain minimum spacing requirements separating the lines.

A-3602-22

While implementing the 2017 Project, PSE&G identified additional local reliability concerns in and around Westfield, specifically at the nearby Clark substation. Because a failure at the Clark substation would negatively affect service to the surrounding area, including service to Westfield, PSE&G initiated the Supplemental Project to ensure overall reliability to its customers. PSE&G determined five possible routes to effectuate the Supplemental Project. The original route went through a residential area and was opposed by Westfield. PSE&G accommodated Westfield's concerns by amending the Supplemental Project to bypass the original residential area and proceed along South Avenue before turning onto Central Avenue. PSE&G determined this route would entail the shortest amount of permitting time, require significantly fewer easements than other possible routes, and was the most cost-effective alternative route, despite adding an additional seven million dollars in costs from the original route.

Westfield adopted the Ordinance at issue on February 22, 2022. See Westfield, N.J., Ordinance 2022-04 (Feb. 22, 2022). Although the Ordinance states its primary purpose is directed at "Small Wireless Facilities within the public right-of-way," its "secondary purpose . . . is to better manage access and use of its rights-of-way by traditional utilities." Ibid. The Ordinance requires a

A-3602-22

utility company obtain a right-of-way permit and agreement prior to the placement of any utility pole within the public right-of-way. Ibid. No permit or agreement is required, however, if the utility company replaces an existing pole with a replacement that is "substantially identical to, or smaller" in both height and diameter. Ibid. The Ordinance also provides that "[n]o proposed [p]ole shall be taller than thirty-five (35) feet or one[-]hundred[-]ten (110%) percent of the height of [p]oles in the [s]urrounding [s]treetscape, whichever is higher." Ibid.

The Ordinance does, however, have exceptions:

[E]xceptions from findings that would otherwise justify denial[] may be granted by the Administrative Review Team if the Administrative Review Team makes the finding that:

(1) Denial of the facility as proposed would violate federal law, state law, or both; or

(2) A provision of this Chapter, as applied to an applicant, would deprive the applicant of its rights under federal law, state law, or both.

[Ibid.]

On April 8, 2022, PSE&G filed a complaint in lieu of prerogative writs against Westfield, seeking to invalidate various sections of the Ordinance on preemption grounds, specifically by operation of several provisions in Title 48

A-3602-22

of the New Jersey statutes and its accompanying regulations. The complaint also sought invalidation of the Ordinance on the basis that it is arbitrary, capricious, and unreasonable.

Free access — add to your briefcase to read the full text and ask questions with AI

Public Service Electric and Gas Company v. Town of Westfield, (N.J. Ct. App. 2025).

Public Service Electric and Gas Company v. Town of Westfield (Public Service Electric and Gas Company v. Town of Westfield) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Borough of Roselle v. Public Service Electric & Gas Co.
173 A.2d 233 (Supreme Court of New Jersey, 1961)
Matter of Alleged Violations of Law by Valley Road Sewerage Co.
712 A.2d 653 (Supreme Court of New Jersey, 1998)
Overlook Terrace Management Corp. v. Rent Control Board of West New York
366 A.2d 321 (Supreme Court of New Jersey, 1976)
Nieder v. Royal Indemnity Insurance
300 A.2d 142 (Supreme Court of New Jersey, 2004)
Abbott Ex Rel. Abbott v. Burke
971 A.2d 989 (Supreme Court of New Jersey, 2009)
Matter of Valley Road Sewerage Co.
685 A.2d 11 (New Jersey Superior Court App Division, 1996)
Brill v. Guardian Life Insurance Co. of America
666 A.2d 146 (Supreme Court of New Jersey, 1995)
Hon. Dana L. Redd v. Vance Bowman(073567)
121 A.3d 341 (Supreme Court of New Jersey, 2015)
Taylor v. Public Service Corp.
73 A. 118 (New Jersey Court of Chancery, 1909)
Public Service Corp. v. Town of Westfield
84 A. 718 (New Jersey Court of Chancery, 1912)
Taylor v. Public Service Corp.
81 A. 1134 (Supreme Court of New Jersey, 1911)
Public Service Corp. v. Town of Westfield
91 A. 740 (Supreme Court of New Jersey, 1914)