Public Service Co. v. Federal Energy Regulatory Commission

851 F.2d 1548
CourtCourt of Appeals for the Fifth Circuit
DecidedAugust 17, 1988
DocketNo. 87-4577
StatusPublished
Cited by4 cases

This text of 851 F.2d 1548 (Public Service Co. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Public Service Co. v. Federal Energy Regulatory Commission, 851 F.2d 1548 (5th Cir. 1988).

Opinion

PATRICK E. HIGGINBOTHAM, Circuit Judge:

The Federal Energy Regulatory Commission found zone rates on a major gas pipeline to be unjust, unreasonable, and discriminatory, and, pursuant to the Natural Gas Act, the Commission ordered a change in transmission cost allocation. Pipeline customers challenge the FERC’s directive as well as the Commission’s determination of the date on which the change is to be effective. We reject the challenges and affirm.

I

Transco operates a major unidirectional natural gas pipeline that starts from its supply sources in Texas and Louisiana and ends almost 2,000 miles away near New York City. The pipeline’s service territory is divided into three zones. Zone 1 extends [1551]*1551about 522 miles and includes Mississippi, Alabama, and Georgia. Zone 2 extends 455 miles and includes the Carolinas, Virginia, and the District of Columbia. Finally, Zone 3 extends 227 miles and includes Maryland, Delaware, Pennsylvania, New Jersey, and New York.

Transco and its customers reached an agreement in 1962 that provided that Zone 2 customers would pay 2.8 cents more per thousand cubic feet of gas than would Zone 1 customers, while Zone 3 customers would pay 3.6 cents more per thousand cubic feet than Zone 2 customers. The Federal Power Commission, the FERC’s predecessor, approved the plan, and subsequent rate settlements and schedules have incorporated these zone differentials.

Transco filed an application for higher rates in 1976. Transco had not proposed any change in the 1962 zone differentials, but the parties in settlement negotiations were unable to agree on a cost allocation method. The FERC ordered a hearing on the issue, and an administrative law judge approved the 1962 differentials.1 The Commission, however, rejected the ALJ’s determination and ordered costs to be allocated by the Mcf-mile method.2 Zone rates thus would be “based upon fully allocated costs without regard to the settlement based differentials previously in effect.”3

The D.C. Circuit set aside the Commission’s cost allocation order in Public Service Commission of the State of New York v. FERC.4 The appellate court first rejected the move to Mcf because the FERC had not found that the 1962 differentials were, in the language of § 5(a) of the Natural Gas Act, “unjust, unreasonable, unduly discriminatory, or preferential.”5 The Commission bore the burden of making such proof by substantial evidence.6 “It is not enough that the petitioners failed to prove that the zone differentials are just and reasonable. It is the Commission which must adduce substantial evidence tending to show that the existing zone rates are unjust and unreasonable.”7 The D.C. Circuit also found that the FERC had not supported the allocation change with substantial evidence.8

Transco filed an application for a general rate increase on March 31, 1982. The parties reached a settlement, which reserved the issue of the zone differentials.9 In reviewing the settlement, the AU found the current differentials to be unjust and discriminatory and, after finding distance to be the primary cost factor on the transmission system, ordered partial implementation of an Mcf-mile cost allocation method.10 Transmission costs incurred in transporting gas from off-shore gathering points to compressor Station 65 were excluded from Mcf allocation.11 The Commission affirmed in part and modified in part the AU’s decision in Opinion No. 260.12 The Commission denied in part and granted [1552]*1552in part rehearing in Opinion No. 260-A.13

The pipeline customers raise multiple challenges on appeal. The Zone 3 customers contend that the AU unlawfully placed the burden of proof on them. Zone 3 also argues that neither the unlawfulness of the 1962 differentials nor the appropriateness of Mcf-mile allocation were supported by substantial evidence. The Zone 2 customers attack the exclusion of upstream production costs from Mcf-mile allocation. Both zones, as well as the North Carolina Utilities Commission, contest the date the Commission set for the new differentials to take effect.

II

A

Zone 3 first contends that the AU unlawfully shifted the burden of proof to it, despite PSCNY’s statement that the party advocating the change bears the burden to show the existing rates are unjust and discriminatory. Zone 3 of course recognizes that the AU appreciated the importance of PSCNY:

Since Public Service has not been explicitly overruled, that decision must be regarded as precedent and its dictates complied with in the present proceeding. Advocates of a change in the present zone differentials must show by substantial evidence both that the existing rate differentials are unlawful and that the proposed zone differentials based on the Mcf-mile method are lawful and in compliance with the strictures of the Act.14

However, after then looking at Commission precedent, which determined that distance was the primary factor in selecting a proper cost allocation method, the AU stated, “As framed by these Commission decisions, the question to be answered is whether any of the factors identified by the Zone 3 Group present such 'extreme variations’ as to outweigh distance as the primary cost factor on Transco’s transmission system.” 15 It is this framing of the question that Zone 3 contends erroneously shifted the burden of proof.

We disagree. First, it is clear that both the AU and the Commission were well aware of the proper allocation of the burden of proof.16 Second, the precedent cited by the AU recognizes a general economic argument that Zone 3 does not dispute. “It is a simple economic fact that the delivery cost of natural gas increases in close proportion to the length of the transmission line of any given size.”17 Third, the AU clearly believed this “simple economic fact” was true on this particular pipeline, and his reference to the testimony of Mr. Clay, one of Zone 2’s witnesses,18 demonstrates his awareness that substantial evidence existed to support the finding that distance was the primary cost factor on Transco. We thus reject Zone 3’s contention that the AU improperly relied on “general [FERC] principles” to shift the burden of proof.

B

After finding distance to be the primary cost factor on the Transco system, the AU directly addressed the legality of the 1962 differentials:

Assuming arguendo that the historic differentials perfectly allocated transmission costs at the time at which they were agreed upon, the contention that they still do so today, some twenty years later is contrary to the record as well as to common sense. A pipeline’s transmission costs are composed of a number of components, including compression costs, and costs related to the pipeline [1553]*1553facilities themselves such as upkeep and taxes. As recounted above, according to the testimony of Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Transwestern Pipeline Company v. Federal Energy Regulatory Commission, the Public Utilities Commission of the State of California, Process Gas Consumers Group, Southern California Gas Company, El Paso Natural Gas Company, Pacific Gas and Electric Company, Texas Eastern Transmission Corporation, the Kansas Power and Light Company, Southwest Gas Corporation, Williams Natural Gas Company, Intervenors. Transwestern Pipeline Company v. Federal Energy Regulatory Commission, Southern California Gas Company, Southwest Gas Corporation, Pacific Gas and Electric Company, Williams Natural Gas Company, Public Utilities Commission of the State of California, El Paso Natural Gas Company, Citizens Energy Corporation, Intervenors. Transwestern Pipeline Company v. Federal Energy Regulatory Commission, Williams Natural Gas Company, Southern California Gas Company, Public Utilities Commission of the State of California, Intervenors. Transwestern Pipeline Company v. Federal Energy Regulatory Commission, Kansas Power & Light Company, Natural Gas Clearinghouse, Inc., Williams Natural Gas Company, Southern California Gas Company, Public Utilities Commission of the State of California, Pacific Gas & Electric Company, Psi, Inc., Texas Eastern Transmission Corp., Southwest Gas Corp., Intervenors. Public Utilities Commission of the State of California v. Federal Energy Regulatory Commission, Kansas Power & Light Company, Natural Gas Clearinghouse, Inc., Williams Natural Gas Company, Southern California Gas Company, Pacific Gas & Electric Company, Psi, Inc., Southwest Gas Corp., Transwestern Pipeline Company, Intervenors. Kansas Power & Light Company v. Federal Energy Regulatory Commission, Natural Gas Clearinghouse, Inc., Williams Natural Gas Company, Pacific Gas & Electric Company, Public Utilities Commission of the State of California, Southern California Gas Company, Psi, Inc., Transwestern Pipeline Company, Intervenors
897 F.2d 570 (D.C. Circuit, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
851 F.2d 1548, Counsel Stack Legal Research, https://law.counselstack.com/opinion/public-service-co-v-federal-energy-regulatory-commission-ca5-1988.