PT Kaltim Prima Coal v. AES Barbers Point, Inc.

180 F. Supp. 2d 475, 46 U.C.C. Rep. Serv. 2d (West) 676, 2001 U.S. Dist. LEXIS 20908, 2001 WL 1622259
CourtDistrict Court, S.D. New York
DecidedDecember 18, 2001
Docket00 Civ. 7196 AKH
StatusPublished
Cited by2 cases

This text of 180 F. Supp. 2d 475 (PT Kaltim Prima Coal v. AES Barbers Point, Inc.) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
PT Kaltim Prima Coal v. AES Barbers Point, Inc., 180 F. Supp. 2d 475, 46 U.C.C. Rep. Serv. 2d (West) 676, 2001 U.S. Dist. LEXIS 20908, 2001 WL 1622259 (S.D.N.Y. 2001).

Opinion

OPINION AND ORDER

HELLERSTEIN, District Judge.

This case arises from a twenty-year requirements contract for coal, in effect since January 1990. The plaintiff-supplier, PT Kaltim Prima Coal (“KPC”), claims that the defendant-purchaser breached the contract by refusing to accept delivery of September and October 2000 shipments. The defendant-purchaser, AES Barbers Point, Inc. (“AES”), claims that its refusal was excused by the supplier’s invocation of the force majeure clause of the contract, and its need to obtain replacement supplies promptly. After full discovery, both sides moved for summary judgment and, having presented all available evidence and in response to my request, converted their motions to motions for judgment after trial, without a jury, pursuant to Fed.R.Civ.P. 52. 1

For the reasons discussed below, I find that AES acted reasonably and pursuant to the contract in refusing to accept delivery of the September 2000 shipment, and that it breached the contract in refusing to accept delivery of the October 2000 shipment. Accordingly, I grant judgment to AES as to the September 2000 shipment, and to KPC as to the October 2000 shipment.

Factual Background

KPC owns and operates a coal mining facility in East Kalimantan, Indonesia. AES operates a coal-fired cogeneration facility at Barbers Point in Oahu, Hawaii, producing electricity for sale to its primary customer, Hawaiian Electric Company. The electricity produced by AES supplies 20 per cent of the electricity requirements of the island of Oahu.

Pursuant to an Amended and Restated Fuel Supply Agreement executed January 12, 1990 (the “Fuel Supply Agreement” or the “Agreement”), KPC is the sole supplier of coal to AES for a twenty-year period. 2 The coal supplied is to be priced according to a formula set out in the Agreement. At the time the contract was made, the formula price was approximately 10 per cent below market. At the time of the events leading to this dispute, however, the formula price was approximately double the market price.

*477 The Fuel Supply Agreement contemplates monthly deliveries of coal from KPC in Indonesia to the AES facility in Hawaii. According to the custom of the parties, AES provides a proposed shipping schedule to KPC once a year, and updates the schedule regularly based on AES’ needs. Also according to the parties’ custom, KPC nominates a ship to AES during the final week of the month preceding shipment, to set sail for AES in the first week of the shipment month and arrive to 15 to 20 days later.

Over the course of approximately ten years, KPC delivered, and AES received, 88 shipments of coal, totaling 4.6 million tons, without incident. Using telefax and electronic mail, officials of KPC and AES maintained frequent and continuous communications concerning AES’ requirements and KPC’s fulfillments.

Beginning in mid-June 2000, labor strife at KPC’s Indonesian facilities interfered with KPC’s ability to process and move coal to its loading port. On July 4, 2000, KPC declared force majeure on all of its sales contracts, including its agreement with AES, effective “4 July, 2000 until full operations recommence.” KPC did not express an anticipated “recommence[ment]” date:

We regret to formally advise that since June 14, 2000 PT Kaltim Prima Coal’s (KPC) coal processing facility has been illegally blockaded by some employees who are members of SBSI (Serikat Bu-ruh Sejahtera Indonesia), one of the three labour associations at KPC. As a result of that actions [sic], KPC has been unable to crush coal or convey coal to the Tanjung Bara Coal Terminal (TBCT). Shipments of coal from June 16, 2000 to today have fully depleted the coal stocks at TBCT.
This illegal action prevents KPC from fulfilling certain of its contractual obligations and accordingly PT. Kaltim Pri-ma Coal declares the above action to be an event of Force Majeure. Force Maj-eure is therefore in effect from 4 July, 2000 until full operations recommence.

Despite its declaration of force majeure, KPC’s July shipment to AES, having already been loaded without incident, was delivered on time. On July 9, 2000, KPC lifted its declaration of force majeure.

KPC’s labor problems continued. In mid-July 2000, the striking labor union again blockaded KPC’s coal processing facility and conveyer. On July 21, 2000, AES’ President and General Manager, Kevin Pierce, having learned that obtaining coal from an alternate supplier would require 40 to 50 days lead time, sought assurance from KPC that it would continue to supply coal to AES as required. On July 24, 2000, KPC responded by giving assurance that it would have sufficient coal for the August shipment, and that it had been developing other supply options should the need have arisen:

During this time your coal requirements have definitely been at the forefront in our considerations to ensure you had sufficient coal. We had progressed [sic] a couple of options available to us where KPC could, with your prior approval, deliver coal from other sources within the specification limits. Fortunately however, this is no longer necessary as KPC has returned to full operations.... We are currently working with [the shipping agent] to find the appropriate vessel within the 3 August to 13 August laycan loading window and can assure you that there will be coal available for your next shipment.

On August 2, 2000, KPC advised AES that KPC had enough coal at the port ready to be loaded and shipped for the August 2000 requirement. The next day, however, on August 3, 2000, KPC issued a *478 “Notice of Potential Force Majeure,” stating that its coal conveyor had again been disrupted by labor strife and that “[i]t remains unclear as to how long this action will continue.” On August 5, 2000, KPC issued yet another “Notice of Potential Force Majeure,” stating that, “[wjithout action by the government authorities the removal of the blockade is unlikely within the foreseeable future.”

Notwithstanding its Notice of Potential Force Majeure, and at the same date of August 5, 2000, KPC loaded the vessel it had nominated for the August delivery to AES, thereby exhausting the coal already at the port. The ship set sail August 8 and arrived at Barbers Point on August 27, 2000.

On August 7, 2000, KPC declared Force Majeure on all of its sales contracts, effective midnight that day. KPC’s notice to its customers stated:

The operations at KPC minesite remain blockaded with no being [sic] coal conveyed to the port since Wednesday, 2nd August. KPC no longer has sufficient coal available to fully load any awaiting ship.
Effective 24.00, 7th August, 2000, KPC declares Force Majeure under its sales contracts.

KPC’s “Notice of Force Majeure” made no mention of the expected duration of the force majeure event. According to KPC’s August 5 potential force majeure notice, the condition was expected to last for “the foreseeable future,” until government authorities caused the blockade to be removed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Medinol Ltd. v. Boston Scientific Corp.
346 F. Supp. 2d 575 (S.D. New York, 2004)
Sutton Associates v. LexisNexis
196 Misc. 2d 30 (New York Supreme Court, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
180 F. Supp. 2d 475, 46 U.C.C. Rep. Serv. 2d (West) 676, 2001 U.S. Dist. LEXIS 20908, 2001 WL 1622259, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pt-kaltim-prima-coal-v-aes-barbers-point-inc-nysd-2001.