Providence Transit Concrete Corp. v. New England Concrete Corp.

14 A.2d 807, 65 R.I. 430, 1940 R.I. LEXIS 128
CourtSupreme Court of Rhode Island
DecidedJuly 25, 1940
StatusPublished
Cited by3 cases

This text of 14 A.2d 807 (Providence Transit Concrete Corp. v. New England Concrete Corp.) is published on Counsel Stack Legal Research, covering Supreme Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Providence Transit Concrete Corp. v. New England Concrete Corp., 14 A.2d 807, 65 R.I. 430, 1940 R.I. LEXIS 128 (R.I. 1940).

Opinion

*431 Moss, J.

This is an action in assumpsit to recover an alleged balance of $4007.89 due and payable for certain materials delivered by the plaintiff to the defendant over a period from September 11, 1934 to March 20, 1937. The defendant relies upon certain matters of recoupment and denies that there is any unpaid balance.

The case was tried before a justice of the superior court, without a jury, and after the conclusion of the trial he filed a decision, in which the final conclusion was that there was a balance of $2770.85 due from the defendant to the plaintiff. Both of the parties duly filed bills of exceptions setting forth numerous exceptions taken by them.

The case is now before us on these bills of exceptions; but all of the exceptions have been waived by the respective parties except two for the plaintiff and one for the defendant. One of those not waived by the plaintiff is to the refusal of *432 the trial justice to permit it to introduce evidence that, before the making of the written agreement between the parties upon which the later and principal claim of the plaintiff is based, it was agreed between the parties that the defendant would not require the plaintiff to furnish any “ground-edge” tiles.

We have serious doubt of the admissibility of such evidence; but because of the ruling which we state infra as to an alleged later agreement to the same effect, this exception becomes immaterial and will not be discussed herein. The other exceptions now insisted upon are one taken by each of the parties to the final decision of the trial justice so far as it was against that party.

The principal part of the plaintiff’s claim upon which its declaration is based is for a balance of $3450 alleged to be due to it from the defendant under a written contract entered into by them and dated April 9, 1936, by the terms of which the plaintiff agreed to furnish and deliver to the defendant, at the site of a building in this state which the defendant was constructing under a contract with the state of Rhode Island, as a P. W. A. project, “All the necessary ceramic-glazed units required for the above mentioned job as per plans and specifications for the sum of Seven Thousand Four Hundred Fifty Dollars ($7450.00).”

The parties agree that the defendant paid to the plaintiff under this contract the sum of $4000, leaving, according to the plaintiff’s contention, the above-mentioned sum of $3450 still due. The defendant, however, contends that the plaintiff violated certain parts of the contract, and that as a consequence the defendant had to make extra expenditures in carrying out its contract with the state which much exceeded $3450, and therefore owes the plaintiff nothing.

The plans and specifications referred to in the above contract between the plaintiff and the defendant are those *433 contained in the aforesaid contract between the defendant and the state of Rhode Island. What those specifications were was shown by a copy of the construction agreement above referred to, which was filed as an exhibit-in the case; and there seems to be no dispute as to what they were.

Among other things they called for certain partitions in the building to be glazed on both sides and built with 6 inch thick terra cotta blocks, each unit to be ground to size and squared, assuring perfect jointing. A part of the specifications reads as follows: “Partitions glazed on both sides shall be built of 6" terra cotta blocks, glazed on both sides.” Ceramic units, as referred to above, are the same things as terra cotta tiles.

A large part of the defendant’s claim in recoupment was based on the admitted fact that although the plaintiff furnished all the tiles that were used in the complete construction of the building, those furnished for the partitions above described were not 6 inch blocks glazed on both sides, but were 4 inch and 2 inch blocks, each of which was glazed on only one side. Evidently, two of these small tiles, one of 4" and one of 2", each glazed on only one side could be put together in one of these partition walls in such a way as to be practically equivalent to a single 6" tile glazed on both sides.

The defendant contends that it is entitled to a large deduction from .the contract price, by way of recoupment, on the ground that the substitution was a breach of contract by the plaintiff, which resulted in heavy damages to the defendant, because it made necessary the use of more than double the original number of tiles in laying these partitions and much greater labor cost to the defendant was required for laying these tiles than would have been required for laying the 6 inch tiles called for by the contract. The defendant also relies on the contention that the plaintiff failed to comply with the requirement, in the contract specifications, that each glazed terra cotta tile should be ground to size and *434 squared, assuring perfect fitting; and that this failure also greatly increased the defendant’s costs of construction.

The trial justice, in his decision, made certain findings that in our opinion were not clearly unsupported by the evidence or against the preponderance of the evidence. Among these were findings that after the original contract between these parties was made they entered into a supplemental agreement by which 4 inch and 2 inch tiles were to be substituted for the 6 inch tiles, required by the original contract, and the requirement as to glazed tiles being ground to size and squared was eliminated.

The trial justice also made a finding that there was no evidence — and we have found none — that the defendant, as a part of the modifying agreement, “insisted on reimbursement for any additional cost” of construction to the defendant made necessary by the changes in the original contract requirements as to the tiles to be furnished. And there is no evidence that the plaintiff, in the modifying agreement, consented to any such reimbursement.

In our opinion it necessarily follows, from these findings, that the defendant was not entitled to any deduction from the contract price by reason of these modifications, which were agreed upon between the parties, even though they resulted in increasing the construction costs of the defendant.-

The trial justice so decided as to the defendant’s claim of recoupment for added costs of construction alleged to have resulted from the fact that the tiles furnished by the plaintiff were not ground in accordance with the original requirements. Yet, after discussing the evidence as to the increase of costs, which the defendant contended had resulted from the substitution of 4 inch and 2 inch tiles for 6 inch tiles, the trial justice said, in his decision, that he thought that a fair sum to be allowed to the defendant for such increased cost was $274.44. He therefore deducted that amount from the *435 unpaid balance of the contract price fixed in the original contract between the' parties. In our opinion he committed an error in so doing.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cardoso v. Mendes, 94-6214 (1999)
Superior Court of Rhode Island, 1999
Corning Glass Works v. SEABOARD SURETY COMPANY
308 A.2d 813 (Supreme Court of Rhode Island, 1973)
David Chernack v. Gilbert Radlo
331 F.2d 170 (First Circuit, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
14 A.2d 807, 65 R.I. 430, 1940 R.I. LEXIS 128, Counsel Stack Legal Research, https://law.counselstack.com/opinion/providence-transit-concrete-corp-v-new-england-concrete-corp-ri-1940.