Protek v. Lake Erie Screw, Unpublished Decision (11-7-2005)

2005 Ohio 5958
CourtOhio Court of Appeals
DecidedNovember 7, 2005
DocketNo. 2005CA00018.
StatusUnpublished
Cited by1 cases

This text of 2005 Ohio 5958 (Protek v. Lake Erie Screw, Unpublished Decision (11-7-2005)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Protek v. Lake Erie Screw, Unpublished Decision (11-7-2005), 2005 Ohio 5958 (Ohio Ct. App. 2005).

Opinion

OPINION
{¶ 1} Plaintiff-appellant Protek, Ltd. (hereinafter "Protek") appeals that portion of the December 14, 2004 Judgment Entry of the Stark County Court of Common Pleas declining to award all of Protek's claimed damages and granting defendant-appellee Lake Erie Screw Corporation's (hereinafter "LES") counterclaim for unpaid invoices, after finding defendant-appellee Lake Erie Screw Corporation breached the parties' agreement. LES cross-appeals that portion of the judgment entry finding it materially breached the terms of the parties' agreement, awarding Protek costs due to customer charge-back and expedited shipping, and failing to award LES prejudgment interest.

STATEMENT OF THE FACTS AND CASE
{¶ 2} This case arises out of an agreement between the parties whereby Lake Erie Screw agreed to manufacture and deliver specialty bolts to Protek. Protek alleges LES breached the agreement by failing to meet delivery due dates and by delivering defective product.

{¶ 3} Both parties are registered QS 9000/ISO 9002 facilities, certifying the implementation of certain processes emphasizing defect prevention and reduction of variation and waste in the supply chain. A QS 9000 supplier is required to establish systems to support 100% on-time shipments to meet customer production and service requirements. Whenever non-conforming product is produced or supplied, QS 9000 certification requires the completion of corrective action reports to address and correct the problem and eliminate the cause of nonconformities.

{¶ 4} In the Fall of 2001, an outside sales representative for LES called upon Protek's predecessor, Alliance Steel Products, Inc. At the time, LES was aware Protek was experiencing problems with its then supplier. The representative indicated LES was an ISO9002/QS9000 registered manufacturer. Later, Alliance Steel Products, Inc. contacted LES asking them to quote the production of certain specialty bolts for use in Protek's tank pad production. LES responded quoting quantities to be produced, delivery dates and price. The quotes bore the legend "Registered ISO9002/QS9000." Alliance Steel Products did not accept the quote.

{¶ 5} LES submitted a second quote to Protek on December 17, 2001. The second quote modified the terms of pricing and delivery dates. Protek accepted the second quote and began issuing purchase orders on January 4, 2002. The purchases were ordered for inclusion in tank pad assemblies to be shipped to Goodyear for inclusion in a military project for tanks and fighting vehicles.

{¶ 6} On March 13, 2002, LES submitted a quotation for a seventh type of bolt. On March 25, 2002, a re-quotation was submitted. A second re-quotation was submitted on June 19, 2002.

{¶ 7} Protek did not specify or agree to pay only for a defect free product. The terms and conditions of the purchase orders did not contract for "defect free" bolts. The LES quotes contained an express warranty limiting its liability and Protek's remedies.

{¶ 8} Approximately 90% of the bolts supplied by LES to Protek were to be used by Protek to assemble the tank pads to be used by Goodyear in the production of the tanks for the U.S. military. Approximately 10% of the bolts supplied by LES to Protek were used to service customers other than Goodyear.

{¶ 9} At the time of the initial requested quotation from LES regarding bolts, Protek faxed copies of the different bolts to LES. Some of the prints were legible, some were "fuzzy", and some were illegible. LES requested Protek provide clearer prints, but the mailed prints were no more legible and the faxed prints did not provide any clarification. Protek indicated to LES it did not have clearer prints. As a result, LES was required to draft its own set of prints. Protek approved prints for six different types of bolts in February 2002, and sent approval of the prints to LES on February 14, 2002. Prior to the approval, however, Protek placed a purchase order for quantities of five of the six types of bolts. The purchase order was dated January 4, 2002, and required delivery of the bolts by March 29, 2002. A second purchase order was placed on January 11, 2002, requiring delivery by April 1, 2002.

{¶ 10} On February 21, 2002, LES contacted Protek and asked Protek to prioritize the delivery dates for the initial purchase orders, since "currently [LES has] all parts slated for 4/1/02" and in talking with LES' "tooling engineers this is unrealistic" and LES needs "to spread them out somewhat." In response, Protek prioritized the bolt orders.

{¶ 11} On March 8, 2002, LES proposed a modification to the delivery dates set forth in the initial purchase orders. Protek did not object. The first delivery of bolts did not occur until April 16, 2002.

{¶ 12} Despite the late delivery, Protek issued additional purchase orders from March 27, 2002, to April 24, 2002. The problems relating to delivery were ongoing throughout the parties' relationship.

{¶ 13} Some of the bolts LES shipped to Protek were nonconforming. The problem lead to LES implementing a corrective action plan in which LES agreed to "100% containment" visually inspecting all parts shipped to Protek. In the end, LES continued to ship some nonconforming product.

{¶ 14} Protek filed a complaint in the Stark County Court of Common Pleas on January 14, 2003, alleging breach of contract. LES filed a counterclaim alleging money owed on account. On February 2, 2004, the matter proceeded to a bench trial. The trial court requested the parties file proposed findings of fact and conclusions of law. On December 14, 2004, the trial court, via Judgment Entry, issued its findings of fact and conclusions of law. The trial court concluded LES had not delivered the bolts in a timely manner and had breached a material term of the parties' agreement. The court awarded Protek $155,941.18 for its costs arising from a customer charge-back and expedited shipping. The trial court offset the award to Protek by the amount of LES' counterclaim for unpaid invoices in the amount of $112,670.23. Accordingly, the trial court awarded Protek a net judgment in the amount of $43,270.93.

{¶ 15} It is from the December 14, 2004, Judgment Entry both parties now appeal.

{¶ 16} On appeal, Protek assigns as error:

{¶ 17} "I. THE TRIAL COURT ERRED, AS A MATTER OF LAW AND AGAINST THE MANIFEST WEIGHT OF THE EVIDENCE, IN FAILING TO AWARD PLAINTIFF ALL OF ITS DAMAGES TO WHICH THE TRIAL COURT HAD RULED PLAINTIFF WAS ENTITLED AS A RESULT OF DEFENDANTS BREACHES.

{¶ 18} "II. THE TRIAL COURT ERRED, AS A MATTER OF LAW AND AGAINST THE MAINFEST WEIGHT OF THE EVIDNENCE, IN CONCLUDING THAT DEFENDANT-APPELLANT DID NOT WARRANT 100% DEFECT FREE PARTS, THUS FAILING TO AWARD PLAINTIFF INCIDENTAL DAMAGES RESULTING FROM DEFENDANT'S BREACH OF THIS WARRANTY.

{¶ 19} "III. THE TRIAL COURT ERRED, AS A MATTER OF LAW, IN AWARDING DEFENDANT CONTRACT DAMAGES ON ITS COUNTERCLAIM AFTER THE TRIAL COURT HAD ALREADY RULED THAT DEFENDANT HAD BREACHED, BY VIRTUE OF ITS FAILURES TO PERFORM, THE VERY CONTRACT UPON WHICH THIS COUNTERCLAIM AWARD WAS PREDICATED."

I
{¶ 20} In the first assignment of error, Protek argues the trial court erred in failing to award all of its damages as a result of LES' breach of contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wildcat Drilling, L.L.C. v. Discovery Oil & Gas, L.L.C.
2018 Ohio 4015 (Ohio Court of Appeals, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
2005 Ohio 5958, Counsel Stack Legal Research, https://law.counselstack.com/opinion/protek-v-lake-erie-screw-unpublished-decision-11-7-2005-ohioctapp-2005.