prospect venture v. engelberth

CourtVermont Superior Court
DecidedMarch 27, 2024
StatusPublished

This text of prospect venture v. engelberth (prospect venture v. engelberth) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
prospect venture v. engelberth, (Vt. Ct. App. 2024).

Opinion

STATE OF VERMONT

CHITTENDEN COUNTY, SS. PROSPECT VENTURE. L.P., ) Plaintiff, ) ) v. ) ) ENGELBERTH CONSTRUCTION, INC., ) Chittenden Superior Court Defendant, ) Docket No. $1273-00 CnC ) Vv. ) be CHITTENDEN SoUNT —— ) se FILED IN CLERKS OFFI | FRENCH & BULEY CONSTRUCTION, INC, 9) fs} Ses BOB SCHUMACHER, NORMAN HAYES, ) fst gy ep oe CHRIS KITTELL, d/b/a/ KITTELL BUILDERS) ~2am |. AND CARL FRITZ, d/b/a EAGLE BUILDERS, ) i wh a Pe Third-Party Defendants. ) be MA MLE a

MEMORANDUM OF DECISION Motions for Summary Judgment

This case is before the court on numerous motions for summary judgment filed by the defendant and third-party defendants. The first was filed by Third-party Defendant Chris Kittell on January 14, 2002. The second was filed by Third-party Defendant Carl Fritz on January 28, 2002. The third was filed by Third-party Defendant Bob Schumacher on February 5, 2002. On February 5, 2002, Defendant Engelberth Construction filed a Motion for Summary Judgment against the plaintiff and filed a partial opposition to the third-party defendants’ motions for summary judgment. On March 6, 2002, plaintiff replied in opposition to all of the summary judgment motions. On March 22, 2002, Engelberth filed a reply to plaintiff's opposition and on March 25, 2002, Kittell filed a reply to both plaintiff and defendant’s opposition. Third-party defendant Chris Kittell is represented by Michael H. Lipson, Esq. Third-party defendant Carl Fritz is represented by Richard Wadhams, Jr., Esq. Third-party defendant Bob Schumacher is - represented by E. William Leckerling, Esq. Defendant, Engelberth Construction, is répresented by Daniel L. Burchard, Esq. Plaintiff, Prospect Venture, is represented by Michael J. Harris, Esq.

The facts in this case are undisputed as set forth in the third-party defendants’, defendant’s, and plaintiff's statements of undisputed facts, supporting affidavits and other documents. In 1992, plaintiff, Prospect Venture, and defendant, Engelberth, entered into a contract for the construction of a student apartment complex (known as the “Redstone Apartments”) on the University of Vermont campus. Between 1992 and 1993, Engelberth hired a number of subcontractors, including Third-party Defendants Kittell, Fritz and Schumacher, to

-1- help complete the proj ect. Written contracts for the subcontracting work were executed between Engelberth and the individual subcontractors. None of the subcontractors executed contracts with Prospect Venture directly.

By the end of August 1993, Prospect Venture took possession of the Redstone Apartments and began to lease the apartments to UVM students for the fall 1993 semester. In September 2000, plaintiff filed a Complaint against Engelberth claiming Engelberth had negligently constructed the Apartments and that it had breached its contract and implied warranties with the plaintiff. On July 17, 2001, Engelberth filed an indemnity claim joining the third-party defendants. According to Engelberth, if Prospect Venture is entitled to recover, then the third-party defendants, pursuant to the express terms of their subcontracts, are required to indemnify Engelberth for any damages which it may be liable.

In the motions now before the court, Engelberth and the third-party defendants all claim that summary judgment should be granted because the statute of limitations has expired based on an accrual provision in the contract between Prospect Venture and Engelberth, and because plaintiff failed to abide by certain conditions precedent in the contract prior to filing suit. Plaintiff responds that the accrual provision of the contract is ambiguous and that Vermont’s “discovery rule” should apply, rather than the accrual provision, which would extend the expiration of the statute of limitations.

ANALYSIS

Defendants’ argument that the statute of limitations has expired is based on an accrual provision in the contract between Prospect Venture and Engelberth that defines the commencement of the statutory limitation period. According to the contract, the statute of limitations period commences at one of three times depending on the nature of the acts or failures to act: 1) Before Substantial Completion of the project pursuant to provision 13.7.1; 2) Between Substantial Completion and Final Certificate for Payment pursuant to provision 13.7.2; and 3) After Final Certificate for Payment pursuant to provision 13.7.3. Determining the commencement of the statute of limitations depends on when the act complained of occurred. In this case, because the alleged negligent construction occurred before the date of Substantial Completion, the only relevant period for the purposes of this motion is the period before Substantial Completion of the project.’

| Because the court’s decision rests on other grounds, the claim that the plaintiff failed to abide by conditions precedent in the contract will not be addressed.

2 In its opposition to the motions, plaintiff argues that if under 13.7.1 its claims are barred as acts occurring before Substantial Completion, then it still retains a claim under 13.7.2 for acts occurring between the date of Substantial Completion and the issuance of a Final Certificate for Payment. This claim is without merit. While Prospect Venture may have “required [Engelberth] to return to the project well into 1994 to work on and correct problems

-2- All parties acknowledge that the date of Substantial Completion was no later than September 1993, when the students moved in. The contract itself indicates that the date of Substantial Completion was August 19", 1993. Contract, at 2. Plaintiff specifically asserts that the meaning of the phrase “relevant date” [of Substantial Completion] in the pertinent clause in the contract is not defined and is therefore ambiguous as it is capable of multiple meanings, and that the defendants “fail to consider the modifying effect of the ‘relevant date’ clause.” (PI.’s - Mot. in Opp’n. to Summ. J. at 4.) Plaintiff contends that under the frame of “relevant date,” the court should apply the “discovery rule, and treat the statute of limitations period as starting when defects in the work were discovered.

The court does not find the Substantial Completion provision ambiguous. The provision clearly states:

13.7.1 As between the Owner and Contractor:

.1 Before Substantial Completion. As to acts or failures to act occurring prior to the relevant date of Substantial Completion, any applicable statute of limitations shall commence to run and any alleged cause of action shall be deemed to have accrued in any and all events not later than such date of Substantial Completion.

Contract Provision 13.7.1. The provision indicates that the applicable statute of limitations will commence to run no later than the date of Substantial Completion. In this case, that means the statute of limitations started no later than September 1993 and expired six years from that date

regarding such issues as patio deck door latches, heating deficiencies and roof shingle problems” (Pl.’s Mot. In Opp’n. to Summ. J. at 6), these acts are not connected to the claims in this case. Plaintiff does not assert, as a basis for the Complaint, that the defendants were negligent in their work with the door latches, heating systems or shingles. Plaintiff cannot bootstrap its action on this corrective work on individual items into a delay of the commencement of the statute of limitations on the siding work completed in a timely manner under the contract . 13.7.2 does not apply because the alleged defective construction occurred before the date of Substantial Completion and not after.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

University of Vermont v. W.R. Grace & Co.
565 A.2d 1354 (Supreme Court of Vermont, 1989)
Isbrandtsen v. North Branch Corp.
556 A.2d 81 (Supreme Court of Vermont, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
prospect venture v. engelberth, Counsel Stack Legal Research, https://law.counselstack.com/opinion/prospect-venture-v-engelberth-vtsuperct-2024.