Progressive Rail Inc. v. CSX Transportation, Inc.

CourtDistrict Court, E.D. Kentucky
DecidedMarch 17, 2021
Docket3:15-cv-00018
StatusUnknown

This text of Progressive Rail Inc. v. CSX Transportation, Inc. (Progressive Rail Inc. v. CSX Transportation, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Progressive Rail Inc. v. CSX Transportation, Inc., (E.D. Ky. 2021).

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF KENTUCKY CENTRAL DIVISION FRANKFORT

SIEMENS ENERGY, INC. and ) PROGRESSIVE RAIL, INC., ) ) Civil No. 3:15-cv-00018-GFVT Plaintiffs, ) ) V. ) MEMORANDUM ) OPINION CSX TRANSPORTATION, INC., ) & ) ORDER Defendant. )

*** *** *** *** This matter is before the Court on Defendant CSX Transportation, Inc.’s Motion for Entitlement to Attorneys’ Fees and Bill of Costs. [R. 112; R. 113.] Plaintiff Siemens Energy, Inc. opposes the Motion, arguing that the language of the Blue Anchor Bill’s Himalaya and Indemnity Clauses preclude CSXT from attorneys’ fees. For the reasons that follow, both of Defendant CSXT’s Motions will be granted. I The factual background of this shipping and transportation case is long and detailed. Consequently, the Court’s previous outline of the facts leading to Siemens’ action for damages [R. 110] is incorporated by reference. On March 10, 2020, this Court ruled on the parties’ cross- motions for summary judgment, granting Defendant CSXT’s Motion and denying Siemens’. [R. 110.] In the Order granting summary judgment, this Court found that (1) The Blue Anchor Bill, to which both CSXT and Siemens were a party, was a through bill, via the Himalaya Clause;1 (2)

1 A common means of shielding downstream carriers from liability. [See R. 110 at 16–17.] as such, the Bill’s provisions were applicable to sub-contractors, such as CSXT; (3) one such provision was the unambiguously-drafted Covenant Not to Sue;2 and (4) CSXT was therefore entitled to summary judgment as Siemens’ claims were barred pursuant to the Covenant Not to Sue. [R. 110.] Siemens appealed the decision to the Sixth Circuit, maintaining that the Blue

Anchor Bill was not a through bill and on other grounds. [See R. 118.] The Sixth Circuit affirmed this Court’s decision and rejected Siemens’ arguments. [Id.] Now, CSXT seeks an order recognizing its entitlement to attorneys’ fees and costs based upon the Indemnity Clause found within the Blue Anchor Bill, as well as its prevailing party status. [R. 112; R. 113.] Siemens opposes the Motion for entitlement to attorneys’ fees,3 arguing for a narrow interpretation of the Bill, which would exclude CSXT from collecting attorneys’ fees. [R. 122.]

II A The principle that each party bear the costs of his or her own litigation expenses, including attorney’s fees, is so entrenched in the justice system of this country that it has become known as the “American Rule.” Fox v. Vice, 131 S. Ct. 2205, 2213, 180 L. Ed. 2d 45 (2011) (citing Alyeska Pipeline Service Co. v. Wilderness Society, 421 U.S. 240, 247, 95 S.Ct. 1612, 44 L.Ed.2d 141 (1975)). A court may award attorneys’ fees and costs, however, “where … the bill of lading provides for the award of attorney fees.” Maersk Inc. v. Alan Marketing, Inc., 1998 WL 167323 at *3 (S.D.N.Y. April 10, 1998); see also Cross Equipment, Ltd. v. Hyundai Merchant Marine (America) Inc., 1999 WL 169433 at *1 (E.D. La. March 25, 1999). In the

2 Section 5.2(a) states that “[t]he Merchant [Siemens] undertakes: (a) that no claim or allegation shall be made against any Sub-Contractor [CSXT] whatsoever … which imposes or attempts to impose upon any Sub-Contractor any liability whatsoever in connection with the Goods or the Carriage of Goods ….” [R. 112-2 at 2.] 3 Siemens has failed to respond to CSXT’s Bill of Costs. present case, CSX asks this Court to recognize an entitlement to attorneys’ fees based upon the Indemnity Clause found within the Blue Anchor Bill that CSXT and Siemens are parties to as a sub-contractor and a merchant, respectively.

B Here, the parties dispute the proper scope and interpretation of the Himalaya and Indemnity Clauses. Specifically, Siemens argues that a narrow interpretation of the Bill, which would exclude CSXT from collecting attorneys’ fees, is proper. [R. 122.] Siemens, however, misconstrues the unambiguous terms of the contract.

This Court previously ruled that the Covenant Not to Sue within the Blue Anchor Bill extended to CSXT, as a sub-contractor, by way of the Himalaya Clause. [R. 110.] The Himalaya Clause, Section 5.3 of the Blue Anchor Bill, states that:

[E]very Sub-Contractor [like CSXT] shall have the benefit of all provisions herein benefitting the Carrier … as if this sea waybill ... were expressly for its benefit and in entering into this contract the Carrier, to the extent of these provisions, does so not only on his own behalf but also as agent or trustee for such Sub-Contractor and such Sub-Contractor shall to this extent be or be deemed to be parties to this contract.” (emphasis added). In the previous Order, this Court found that the limited liability provisions within the contract were applicable to sub-contractors, such as CSXT. [R. 110 at 16.] Consequently, Siemens, as a merchant, was found to have improperly brought a claim against a subcontractor, CSXT, in violation of Section 5.2(a). [Id. at 17.] Here, the exact same section of the Bill, Section 5, is again put into question by Siemens. The Indemnity Clause, Section 5.2(b) of the Blue Anchor Bill, states that “[t]he Merchant [Siemens] undertakes: … (b) if any claim or allegation should nevertheless be made against a Sub-Contractor [CSX], to Indemnify the Carrier against all consequences thereof.” [R. 112-2 at 6.] In the Bill, “Indemnify” is defined as to “defend, indemnify and hold harmless, including in respect of legal fees and costs …” [Id.] As CSXT notes, the exact same reasoning and contractual terms that this Court has previously discussed, as applied to the liability provisions, apply here. The Supreme Court, in Norfolk S. Ry. Co. v. Kirby, instructed that maritime

contracts “must be construed like any other contracts: by their terms and consistent with the intent of the parties.” 543 U.S. 14, 16 (2004). Thus, where the bill’s terms are clear and unambiguous, those terms are to be given their plain and usual meaning. Royal Ins. Co. of Am. v. Orient Overseas Container Line Ltd., 525 F.3d 409, 421 (6th Cir. 2008). The Court will apply these well-established principles in interpreting the language of the relevant provisions concerning attorneys’ fees. Siemens argues that Sections 5.2(b) and 5.3, read in pari materiae, create a narrow set of

circumstances in which CSXT would be able to recover attorneys’ fees. [R. 122.] Specifically, Siemens asserts that indemnity would only be triggered where “(1) the Merchant (Siemens) [breaches] the covenant not to sue in Subsection 5.2(b); and (2) that breach [necessarily] inflict[s] one or more adverse consequences to the Carrier (BAL).” [Id. at 5.] Because BAL suffered no adverse consequences, Siemens explains, CSXT’s claim for attorneys’ fees falls outside the scope of the Indemnity Clause. [Id.] Siemens further argues that an award of attorneys’ fees in the present case would improperly allow CSXT, a sub-contractor, to receive a greater benefit than the Carrier would receive if it had likewise been sued for a cargo damage claim. [Id. at 8.]

Siemens, however, misconstrues the Himalaya Clause in its argument. The Himalaya Clause clearly states that “every Sub-Contractor shall have the benefit of all provisions herein benefitting the Carrier …, as if this sea waybill … were expressly for its benefit.” [R. 112-2 at 6] (emphasis added). Based on the plain language, the Clause extends to CSXT (a sub- contractor) all of the provisions benefitting the carrier, not the actual benefits that the carrier receives.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alyeska Pipeline Service Co. v. Wilderness Society
421 U.S. 240 (Supreme Court, 1975)
Crawford Fitting Co. v. J. T. Gibbons, Inc.
482 U.S. 437 (Supreme Court, 1987)
Fox v. Vice
131 S. Ct. 2205 (Supreme Court, 2011)
James Miles v. State of California
320 F.3d 986 (Ninth Circuit, 2003)
George R. Hall, Inc. v. Superior Trucking Co.
532 F. Supp. 985 (N.D. Georgia, 1982)
King v. Gowdy
268 F. App'x 389 (Sixth Circuit, 2008)
Progressive Rail Inc. v. CSX Trans., Inc.
981 F.3d 529 (Sixth Circuit, 2020)
Contreras v. City of Chicago
119 F.3d 1286 (Seventh Circuit, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
Progressive Rail Inc. v. CSX Transportation, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/progressive-rail-inc-v-csx-transportation-inc-kyed-2021.