Progressive Architects/engineers/planners, Inc. v. Security Insurance Company of Hartford

103 F.3d 130, 1996 U.S. App. LEXIS 35675
Court of Appeals for the Sixth Circuit·Decided December 16, 1996·No. 95-1935·Unpublished

Opinion

103 F.3d 130

NOTICE: Sixth Circuit Rule 24(c) states that citation of unpublished dispositions is disfavored except for establishing res judicata, estoppel, or the law of the case and requires service of copies of cited unpublished dispositions of the Sixth Circuit.
PROGRESSIVE ARCHITECTS/ENGINEERS/PLANNERS, INC., Plaintiff-Appellant,
v.
SECURITY INSURANCE COMPANY OF HARTFORD, Defendant-Appellee.

Nos. 95-1935, 95-1981.

United States Court of Appeals, Sixth Circuit.

Dec. 16, 1996.

Before: MARTIN, Chief Judge; WELLFORD and MOORE, Circuit Judges.

PER CURIAM.

Progressive Architects/Engineers/Planners, Inc. appeals and Security Insurance Company of Hartford cross-appeals the district court's final judgment in this diversity action involving a dispute about coverage under an architects and engineers professional liability policy and application of a pollution exclusion contained therein.

I.

This suit arises from the construction of a retail outlet in the city of Woodhaven, Michigan. The retailer, Meijer, hired Progressive to perform certain preliminary site engineering services at the proposed outlet location. A berm, created from natural soils, was built for the purpose of storing contaminated soils found at the site. Progressive was instructed that no debris larger than six inches in diameter was to be placed in the berm.

Ultimately, Meijer sued Progressive and several other parties for the costs of remediation of the Woodhaven site. Meijer pled five causes of action against Progressive: breach of contract, professional malpractice, negligence, breach of warranty, and express and common law indemnification, alleging that Progressive had allowed debris and barrels larger than the six inch limit to be placed in the berm. Meijer sought damages from Progressive for the cost of opening the berm and removing these improper contents. Progressive admitted that its representative tacitly allowed other contractors to place some larger debris in the berm, but maintained that it knew nothing of any barrels or pollutants being placed there.

Progressive sought coverage from Security, its insurer, which initially denied coverage based on the policy's pollution exclusion. However, when Progressive's counsel asked Security to reconsider, Security reviewed its position, and with assistance of counsel agreed by letter dated August 2, 1991 that it owed a duty of defense and a duty of indemnity for the cost of removing certain specified inert and nonpollutant debris from the berm.

After exhaustion of the policy's deductible, Security paid the cost of Progressive's defense. Meijer and Progressive reached a settlement in which Progressive paid Meijer $350,000.00. Security approved the settlement and contributed $75,000.00, reserving the issue of coverage on the full settlement amount.

Progressive then sued Security in United States District Court for the Western District of Michigan for breach of the insurance contract and for a declaratory judgment as to Security's liability to Progressive. Security counterclaimed for a return of a portion of the $75,000.00 it had advanced. Following discovery, both sides moved for summary judgment.

In a July 18, 1994 Opinion and Order, the district court denied Progressive's motion for summary judgment and granted Security's motion in part, finding that Security had no duty under the language of the policy to indemnify Progressive because the entire claim fell within the pollution exclusion. The court also denied without prejudice Security's motion for summary judgment on the issue of damages for its counterclaim, finding that a genuine factual issue existed as to the proper measure of damages for the counterclaim.

After further briefing, the district court on August 19 issued a second Opinion and Order on counterclaim damages. The court rejected Progressive's argument that the cost of removing the inert debris exceeded Progressive's $350,000.00 settlement with Meijer, and rejected Security's proposed measure of damages as not including expense for opening the berm.

Following the final pretrial conference, Security filed a motion in limine seeking a definitive ruling as to the issues to be litigated at trial. On December 13, the district court entered a third Opinion and Order which clarified and revised its previous rulings. Security's motion in limine was denied, and the district court's order concerning Progressive's motion for summary judgment was changed; the motion was denied to the extent that it sought liability under the policy, but granted as to liability under the August 2, 1991 letter. Summary judgment was denied as to the issue of damages, and Security's motion for summary judgment was denied in its entirety.

The sole issue at trial was the "cost of removal" of the inert debris as set forth in the August 2, 1991 letter. On July 21, 1995, the court entered its Findings and Conclusions of Law, holding that Progressive was entitled to damages of $72,020.00 and that Security was therefore entitled to have $2,980.00 of the amount previously paid returned to it. The court found that Security's agreement in the August 2, 1991 letter was based on an erroneous assumption that the cost of removing the nonpollutant debris "could be segregated from the cost of removing" other materials and pollutants, and that this erroneous assumption was apparent from the face of the agreement. The court rejected Progressive's evidence as to Meijer's cost of removing the debris from the berm and the body of law cited by Progressive dealing with the allocation of known costs between covered and noncovered claims. On July 31, judgment was entered. Progressive appeals and Security cross-appeals the decision and judgment.

Three issues are before us on appeal: whether Security's August 2, 1991 letter admitted an independent and separate duty or a duty of indemnity under the policy; whether the pollution exclusion contained in Progressive's policy bars coverage; and whether the district court properly determined damages.

II.

Free access — add to your briefcase to read the full text and ask questions with AI

Progressive Architects/engineers/planners, Inc. v. Security Insurance Company of Hartford, 103 F.3d 130, 1996 U.S. App. LEXIS 35675 (6th Cir. 1996).

103 F.3d 130 (Progressive Architects/engineers/planners, Inc. v. Security Insurance Company of Hartford) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Wilson v. International Brotherhood Of Teamsters
83 F.3d 747 (Sixth Circuit, 1996)
Continental Casualty Co. v. Board of Education
489 A.2d 536 (Court of Appeals of Maryland, 1985)