Program and Construction Management Group, Inc. v. Thurman J. Davis, Sr., Acting Administrator, General Services Administration

246 F.3d 1363, 2001 U.S. App. LEXIS 7164, 2001 WL 392057
CourtCourt of Appeals for the Federal Circuit
DecidedApril 19, 2001
Docket00-1312
StatusPublished

This text of 246 F.3d 1363 (Program and Construction Management Group, Inc. v. Thurman J. Davis, Sr., Acting Administrator, General Services Administration) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Program and Construction Management Group, Inc. v. Thurman J. Davis, Sr., Acting Administrator, General Services Administration, 246 F.3d 1363, 2001 U.S. App. LEXIS 7164, 2001 WL 392057 (Fed. Cir. 2001).

Opinion

FRIEDMAN, Senior Circuit Judge.

The principal question is whether the General Services Administration Board of Contract Appeals (Board) correctly interpreted a contract to upgrade the heating, ventilation and air conditioning of the cafeteria and kitchen in a government building as contemplating that the cafeteria would remain open during the performance of the contract. We affirm that ruling and also the Board’s rejection of the other grounds on which the contractor sought additional compensation, ie., that the government was responsible for various delays in the performance of the contract.

I

The basic facts are undisputed. The General Services Administration contracted with the appellant Program and Construction Management Group, Inc. (Contractor) to upgrade the heating, ventilation and air conditioning of the cafeteria, kitchen and other facilities in a government building, for a fixed-price of $747,267. The contract had been set aside for a small business under 48 C.F.R. Subpart 19.5 and resulted from negotiations. The government instituted the procurement by issuing a solicitation which, after various amendments, became the contract.

The solicitation stated at least three times that the building would remain open and occupied during the work. It pointed out that “[t]he Government will occupy the site and the existing building during the entire period of construction” (Section 01010, clause 1.4), that “[t]he premises will be occupied during performance of work under the contract” (Section 1040, clause 1.5), and that “[t]he building shall remain in operation during the work of this contract” (Note to architectural drawing 3-1A). The last note also stated: “[t]he hours of operation allowed for the contractor’s work in occupied areas is indicated in the specifications.”

Section 1040, clause 1.5, captioned “LIMITATIONS FOR USE OF SITE,” stated:

H. Unless noted otherwise, all work in Mechanical Equipment Rooms may be done during standard business hours. In Kitchen, serving line areas and dining area, all work shall be done between 2:00 pm and 5:00 am on week nights and from 2:00 pm Friday to 5:00 am Monday.
I. Standard building hours are 6:30 a.m. to 6:30 p.m., Monday through Friday. ...
M. Existing Equipment on Site: Cover equipment that is to remain in place within the area of contract operations and protect it against damage or loss.... In addition, dining tables, chairs and service equipment shall be wiped clean of debris after the conclusion of every work day before 5:00 am.

Note 8 to architectural drawing 9-M-l initially stated:

The cafeteria, dining area, kitchen and serving line shall remain in operation during the work of this contract. Be *1365 fore work begins the contractor shall submit a plan to provide temporary ventilation, cooling or heating, as required to maintain indoor temperatures of 80 degrees F in the cooling season and 65 degrees F in the heating season. The kitchen cooling season indoor temperature shall be maintained at 85 degrees Fahrenheit maximum.

During discussions with the Contractor, the government decided to eliminate the requirement for temporary heating or cooling until the contract was awarded and it could be determined whether that action would be necessary. The government issued Amendment 01 to the solicitation, effective February 16, 1994, which included the statement:

Delete in its entirety General Note 8, on drawing 9-M-l.

The contract required the Contractor to “commence work under the contract within [a] calendar day after the contractor receives the notice to proceed and to complete the work within 180 days after receipt of the notice to proceed.” Section 00800-1. The Contractor received the notice to proceed on December 8, 1995, and the government deemed the work substantially completed on October 17, 1996, more than 300 days later.

The Contractor submitted to the contracting officer a claim of $405,468 for a variety of costs attributed to delay or work changes that the government caused. The Contractor also sought damages based on its additional costs allegedly incurred because the cafeteria and kitchen were kept open during construction.

After the contracting officer denied the claims, the Contractor appealed to the Board, which also rejected them all. After an evidentiary hearing, the Board interpreted the contract as contemplating that the cafeteria would remain open during the performance of the contract. It stated:

Reading this contract as a whole, it is clear that the building, including the work areas, would be occupied and the hours when the contractor could work in occupied areas would be restricted.... Construing the contract, including amendment 1, as a whole, we conclude that GSA did not intend to close the cafeteria for the duration of this project, and the contract did not do so.... The contract did not state or imply that the cafeteria would be closed.

Program and Constr. Mgmt. Group, Inc. v. Gen. Servs. Admin., No. GSBCA 14178, 14557, slip op. at 27-28 (G.S.B.C.A. Dec. 30, 1999) (Board decision).

The Board concluded that the Contractor was “not entitled to any further compensation from GSA for added costs associated with changed work or delays encountered in the performance of this contract. Most of the delays claimed by [the Contractor] were attributable to its faulty understanding of the contract terms.... To the extent that GSA changed work, or caused delays that did not run concurrently with [the Contractor]-caused delay, it has fully compensated [the Contractor] under change orders to the contract.” Board decision, slip op. at 33.

II

The Contractor contends that because Note 8 to the drawing was the only provision of the contract that explicitly stated that the cafeteria would remain open during performance of the contract, the deletion of that provision meant that *1366 the contract no longer so provided. We agree with the Board, however, that viewing the contract as a whole, it contemplated that the cafeteria would remain open during the work. “[I]n view of the Board’s considerable experience and expertise in interpreting government contracts, its interpretation is given careful consideration.” Interstate Gen. Gov’t Contractors v. Stone, 980 F.2d 1433, 1434 (Fed.Cir. 1992) (quoting Triax-Pacific, A Joint Venture v. Stone, 958 F.2d 351, 353 (Fed.Cir.1992)).

In three different places, the contract stated that the government would continue to occupy and operate the building during contract performance. The contract also sharply distinguished between the hours when the work could be done in the building generally and the more limited periods it could be done in the cafeteria area. It provided that work in mechanical equipment rooms could be done “during standard business hours,” which it defined as “6:30 a.m.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
246 F.3d 1363, 2001 U.S. App. LEXIS 7164, 2001 WL 392057, Counsel Stack Legal Research, https://law.counselstack.com/opinion/program-and-construction-management-group-inc-v-thurman-j-davis-sr-cafc-2001.