PROFESSIONAL STONE, STUCCO & SIDING APPLICATORS, INC. VS. JMOC BUILDERS, INC. (L-2989-15, PASSAIC COUNTY AND STATEWIDE)
Opinion
NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION This opinion shall not "constitute precedent or be binding upon any court." Although it is posted on the internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.
SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION
DOCKET NO. A-0015-17T2
PROFESSIONAL STONE, STUCCO & SIDING APPLICATORS, INC.,
Plaintiff-Respondent,
v. JMOC BUILDERS, INC.,
Defendant-Appellant.
Argued October 23, 2018 – Decided January 28, 2019 Before Judges Yannotti and Rothstadt.
On appeal from Superior Court of New Jersey, Law Division, Passaic County, Docket No. L-2989-15.
Brian D. Schwartz argued the cause for appellant (Craner, Satkin, Scheer, Schwartz & Hanna, PC, attorneys; Brian D. Schwartz, on the briefs).
Riley E. Horton, Jr., argued the cause for respondent.
PER CURIAM
Defendant JMOC Builders, Inc. appeals from the Law Division's July 21, 2017 judgment in the amount of $50,832.17 it entered in favor of defendant's subcontractor, plaintiff, Professional Stone, Stucco & Siding Applicators, Inc. Following a bench trial, the trial court concluded that defendant breached its agreement with plaintiff. The court awarded damages based solely upon the unpaid balance due under the parties' agreement, and added prejudgment interest and attorney's fees.
On appeal, defendant contends that it was error for the court to simply rely upon the balance of the contract amount that was not paid without any calculation of plaintiff's lost profits. Because plaintiff did not prove its lost profits, defendant argues the court should not have entered judgment and instead it should have dismissed the complaint. We agree. We reverse the trial court's judgment because we conclude there was no evidence in the record for the trial court to rely upon to award damages to plaintiff.
The facts as found by the trial court are summarized as follows. Plaintiff is a company that performs stone, stucco, brick, and siding work on new construction for contractors and builders. Defendant provides maintenance and construction services and was the construction manager on a project at an apartment building in Morristown owned by defendant's principal. The parties
A-0015-17T2
entered into two contracts in May 2014 that called for plaintiff to first install a weather-resistant membrane to the exterior of defendant's building for a price of $13,975.00, and then, under the second contract, to provide materials and labor for the application of exterior stucco to the building for a price of $78,525.00. Defendant was to pay for the stucco work by making two $30,000 payments when thirty percent and sixty percent of the work was completed, with the remaining $18,525.00 to be paid at completion.
The stucco agreement addressed plaintiff's damages in the event that defendant did not allow plaintiff to commence or "continue performance" under the agreement. If defendant interfered with plaintiff's performance, plaintiff would be entitled to recover "as a measure of damages . . . an appropriate portion of the profit [plaintiff] would have earned under th[e] agreement, plus the reasonable [value] of the labor and materials that were furnished." 1 Just prior to plaintiff commencing performance of the contract, the parties also entered into a subcontractor agreement on August 25, 2014. The subcontractor agreement stated that it could be terminated by defendant's written
1 It also stated that if defendant defaulted, plaintiff would be immediately entitled to payment of the "outstanding unpaid balance," a late charge of "1 1/2% per month," and the "owner [would be] responsible for all costs and fees including attorney's fees incurred in [the] collection of [the] outstanding balance."
A-0015-17T2
notice in the event of an uncured breach, or upon thirty days' written notice by plaintiff in the event of untimely payment. Additionally, either party could terminate the agreement if the other materially breached any other provision and failed to cure the breach within thirty days of receiving notice from the non- breaching party.
Plaintiff fully performed the contract for the installation of the weather membrane in May 2014 and was paid in full in June 2014. Plaintiff then subcontracted the labor portion of the stucco contract to a sub-subcontractor, Duo Construction, LLM (Duo) for $55,580.00. Duo began work on the stucco sub-subcontract in August 2014 and ceased work in November 2014. According to Duo's principal, when Duo had completed approximately eighty percent of the stucco project, it was forced to stop because the remainder of the building was not complete, and thus not ready for stucco application. Defendant's principal confirmed that when Duo stopped working, excavation work prevented stucco from being applied to parts of the building. Although Duo still had twenty percent of the work to complete, plaintiff had paid Duo all but approximately $3,500 of its contract price.
Prior to Duo not being able to complete its work, defendant had already paid plaintiff the first $30,000 installment as well as $20,000 towards the second
A-0015-17T2
payment due under the contract. It also issued another payment of $10,000 but, in December 2014, defendant stopped payment on that check because it found leaks in the building that it previously directed plaintiff to cure, and which prevented the building from being "water tight."
Defendant initially raised issues about the leaks in an August 12, 2014 email to plaintiff asking it to "do something about getting the upper portion water tight." On December 2, 2014, plaintiff emailed defendant informing it that the work was complete and requesting a final payment of $28,525.00. Defendant disagreed with that assessment and in a responding email described the work as "far from complete." Shortly after that email exchange, defendant stopped payment on the $10,000 check because the building was "taking in water" and experiencing other issues, and defendant was dissatisfied with plaintiff's "overall lack of attention" to the project, which was causing leaks to occur throughout the building. Defendant emailed plaintiff on December 10, 2014, demanding that plaintiff "remedy th[e] situation immediately."
After discussions between the parties, it was determined that it was necessary for the building to be caulked in order for it to be waterproof. However, according to plaintiff, the leaks were not its fault, but due to the roof
A-0015-17T2
being unfinished. Nevertheless, plaintiff immediately installed a "caulking membrane" to remedy the issue.
Despite plaintiff's actions, in mid- to late December 2014, defendant decided to hire a different company to complete the remaining stucco work. In June 2015, it hired Darco Construction Corp. (Darco) to complete the unfinished work for a total cost of $25,400.00. According to plaintiff, after December 2014, it did not receive any communication from defendant regarding returning to the site to finish the work, or any written communication that plaintiff was terminated or that its services were no longer required. It was plaintiff's understanding that defendant would contact it when it was ready for plaintiff to complete the stucco work. According to defendant, it believed that stopping payment on the $10,000 check in December 2014 and the parties' subsequent communications were "a form of [notice of] termination."
Based on its belief that it would be completing the work on the project, on August 21, 2015, plaintiff sent an email to defendant, stating that it was "looking forward to completing [its] scope and collecting [its] final payment." In response to that email, on August 27, 2015, defendant informed plaintiff that it had hired Darco to caulk due to plaintiff's "history of delays and poor workmanship" as well as Duo's "inferior work." Plaintiff replied that it "had no
A-0015-17T2
Free access — add to your briefcase to read the full text and ask questions with AI
PROFESSIONAL STONE, STUCCO & SIDING APPLICATORS, INC. VS. JMOC BUILDERS, INC. (L-2989-15, PASSAIC COUNTY AND STATEWIDE) (PROFESSIONAL STONE, STUCCO & SIDING APPLICATORS, INC. VS. JMOC BUILDERS, INC. (L-2989-15, PASSAIC COUNTY AND STATEWIDE)) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.