PROFESSIONAL STONE, STUCCO & SIDING APPLICATORS, INC. VS. JMOC BUILDERS, INC. (L-2989-15, PASSAIC COUNTY AND STATEWIDE)

CourtNew Jersey Superior Court Appellate Division
DecidedJanuary 28, 2019
DocketA-0015-17T2
StatusUnpublished

This text of PROFESSIONAL STONE, STUCCO & SIDING APPLICATORS, INC. VS. JMOC BUILDERS, INC. (L-2989-15, PASSAIC COUNTY AND STATEWIDE) (PROFESSIONAL STONE, STUCCO & SIDING APPLICATORS, INC. VS. JMOC BUILDERS, INC. (L-2989-15, PASSAIC COUNTY AND STATEWIDE)) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
PROFESSIONAL STONE, STUCCO & SIDING APPLICATORS, INC. VS. JMOC BUILDERS, INC. (L-2989-15, PASSAIC COUNTY AND STATEWIDE), (N.J. Ct. App. 2019).

Opinion

NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION This opinion shall not "constitute precedent or be binding upon any court." Although it is posted on the internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.

SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION DOCKET NO. A-0015-17T2

PROFESSIONAL STONE, STUCCO & SIDING APPLICATORS, INC.,

Plaintiff-Respondent,

v.

JMOC BUILDERS, INC.,

Defendant-Appellant. _________________________

Argued October 23, 2018 – Decided January 28, 2019

Before Judges Yannotti and Rothstadt.

On appeal from Superior Court of New Jersey, Law Division, Passaic County, Docket No. L-2989-15.

Brian D. Schwartz argued the cause for appellant (Craner, Satkin, Scheer, Schwartz & Hanna, PC, attorneys; Brian D. Schwartz, on the briefs).

Riley E. Horton, Jr., argued the cause for respondent.

PER CURIAM Defendant JMOC Builders, Inc. appeals from the Law Division's July 21,

2017 judgment in the amount of $50,832.17 it entered in favor of defendant's

subcontractor, plaintiff, Professional Stone, Stucco & Siding Applicators, Inc.

Following a bench trial, the trial court concluded that defendant breached its

agreement with plaintiff. The court awarded damages based solely upon the

unpaid balance due under the parties' agreement, and added prejudgment interest

and attorney's fees.

On appeal, defendant contends that it was error for the court to simply rely

upon the balance of the contract amount that was not paid without any

calculation of plaintiff's lost profits. Because plaintiff did not prove its lost

profits, defendant argues the court should not have entered judgment and instead

it should have dismissed the complaint. We agree. We reverse the trial court's

judgment because we conclude there was no evidence in the record for the trial

court to rely upon to award damages to plaintiff.

The facts as found by the trial court are summarized as follows. Plaintiff

is a company that performs stone, stucco, brick, and siding work on new

construction for contractors and builders. Defendant provides maintenance and

construction services and was the construction manager on a project at an

apartment building in Morristown owned by defendant's principal. The parties

A-0015-17T2 2 entered into two contracts in May 2014 that called for plaintiff to first install a

weather-resistant membrane to the exterior of defendant's building for a price of

$13,975.00, and then, under the second contract, to provide materials and labor

for the application of exterior stucco to the building for a price of $78,525.00.

Defendant was to pay for the stucco work by making two $30,000 payments

when thirty percent and sixty percent of the work was completed, with the

remaining $18,525.00 to be paid at completion.

The stucco agreement addressed plaintiff's damages in the event that

defendant did not allow plaintiff to commence or "continue performance" under

the agreement. If defendant interfered with plaintiff's performance, plaintiff

would be entitled to recover "as a measure of damages . . . an appropriate portion

of the profit [plaintiff] would have earned under th[e] agreement, plus the

reasonable [value] of the labor and materials that were furnished." 1

Just prior to plaintiff commencing performance of the contract, the parties

also entered into a subcontractor agreement on August 25, 2014. The

subcontractor agreement stated that it could be terminated by defendant's written

1 It also stated that if defendant defaulted, plaintiff would be immediately entitled to payment of the "outstanding unpaid balance," a late charge of "1 1/2% per month," and the "owner [would be] responsible for all costs and fees including attorney's fees incurred in [the] collection of [the] outstanding balance." A-0015-17T2 3 notice in the event of an uncured breach, or upon thirty days' written notice by

plaintiff in the event of untimely payment. Additionally, either party could

terminate the agreement if the other materially breached any other provision and

failed to cure the breach within thirty days of receiving notice from the non-

breaching party.

Plaintiff fully performed the contract for the installation of the weather

membrane in May 2014 and was paid in full in June 2014. Plaintiff then

subcontracted the labor portion of the stucco contract to a sub-subcontractor,

Duo Construction, LLM (Duo) for $55,580.00. Duo began work on the stucco

sub-subcontract in August 2014 and ceased work in November 2014. According

to Duo's principal, when Duo had completed approximately eighty percent of

the stucco project, it was forced to stop because the remainder of the building

was not complete, and thus not ready for stucco application. Defendant's

principal confirmed that when Duo stopped working, excavation work prevented

stucco from being applied to parts of the building. Although Duo still had

twenty percent of the work to complete, plaintiff had paid Duo all but

approximately $3,500 of its contract price.

Prior to Duo not being able to complete its work, defendant had already

paid plaintiff the first $30,000 installment as well as $20,000 towards the second

A-0015-17T2 4 payment due under the contract. It also issued another payment of $10,000 but,

in December 2014, defendant stopped payment on that check because it found

leaks in the building that it previously directed plaintiff to cure, and which

prevented the building from being "water tight."

Defendant initially raised issues about the leaks in an August 12, 2014

email to plaintiff asking it to "do something about getting the upper portion

water tight." On December 2, 2014, plaintiff emailed defendant informing it

that the work was complete and requesting a final payment of $28,525.00.

Defendant disagreed with that assessment and in a responding email described

the work as "far from complete." Shortly after that email exchange, defendant

stopped payment on the $10,000 check because the building was "taking in

water" and experiencing other issues, and defendant was dissatisfied with

plaintiff's "overall lack of attention" to the project, which was causing leaks to

occur throughout the building. Defendant emailed plaintiff on December 10,

2014, demanding that plaintiff "remedy th[e] situation immediately."

After discussions between the parties, it was determined that it was

necessary for the building to be caulked in order for it to be waterproof.

However, according to plaintiff, the leaks were not its fault, but due to the roof

A-0015-17T2 5 being unfinished. Nevertheless, plaintiff immediately installed a "caulking

membrane" to remedy the issue.

Despite plaintiff's actions, in mid- to late December 2014, defendant

decided to hire a different company to complete the remaining stucco work. In

June 2015, it hired Darco Construction Corp. (Darco) to complete the unfinished

work for a total cost of $25,400.00. According to plaintiff, after December 2014,

it did not receive any communication from defendant regarding returning to the

site to finish the work, or any written communication that plaintiff was

terminated or that its services were no longer required. It was plaintiff's

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stanley Co. of America v. Hercules Powder Co.
108 A.2d 616 (Supreme Court of New Jersey, 1954)
Desai v. BOARD OF ADJ. OF PHILLIPSBURG
824 A.2d 166 (New Jersey Superior Court App Division, 2003)
Cesare v. Cesare
713 A.2d 390 (Supreme Court of New Jersey, 1998)
VAL Floors, Inc. v. Westminster Communities, Inc.
810 A.2d 625 (New Jersey Superior Court App Division, 2002)
JL Davis & Associates v. Heidler
622 A.2d 923 (New Jersey Superior Court App Division, 1993)
Cromartie v. Carteret Sav. & Loan
649 A.2d 76 (New Jersey Superior Court App Division, 1994)
Seidman v. Clifton Savings Bank
14 A.3d 36 (Supreme Court of New Jersey, 2011)
Globe Motor Company v. Ilya Igdalev(074996)
139 A.3d 57 (Supreme Court of New Jersey, 2016)
Feldman v. Jacob Branfman & Son, Inc.
166 A. 126 (Supreme Court of New Jersey, 1933)
Motorworld, Inc. v. William Benkendorf077009)
156 A.3d 1061 (Supreme Court of New Jersey, 2017)
RSI Bank v. Providence Mut. Fire Ins. Co.
191 A.3d 629 (Supreme Court of New Jersey, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
PROFESSIONAL STONE, STUCCO & SIDING APPLICATORS, INC. VS. JMOC BUILDERS, INC. (L-2989-15, PASSAIC COUNTY AND STATEWIDE), Counsel Stack Legal Research, https://law.counselstack.com/opinion/professional-stone-stucco-siding-applicators-inc-vs-jmoc-builders-njsuperctappdiv-2019.