Professional Services Group, Inc. v. CH2M Hill Central, Inc.

620 F. Supp. 194, 1985 U.S. Dist. LEXIS 17207
CourtDistrict Court, E.D. Wisconsin
DecidedAugust 2, 1985
DocketNo. 83-C-934
StatusPublished

This text of 620 F. Supp. 194 (Professional Services Group, Inc. v. CH2M Hill Central, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Professional Services Group, Inc. v. CH2M Hill Central, Inc., 620 F. Supp. 194, 1985 U.S. Dist. LEXIS 17207 (E.D. Wis. 1985).

Opinion

DECISION AND ORDER

CURRAN, District Judge.

The present action was commenced on July 26,1983, invoking the court’s diversity jurisdiction. The three count complaint alleges that the defendant breached its contract with the plaintiff, damaging it in the amount of $60,968.00; that' such breach caused the plaintiff to under-utilize its capacity, resulting in lost profits of $242,-602.50 and that the defendant’s conduct constituted a breach of its covenant of good faith, resulting in damages of $303,-570.50. Presently before the court are the defendant’s motion for summary judgment on all counts and the plaintiff’s motion for partial summary judgment on count 1.

BACKGROUND

On August 3, 1977, the defendant, CH2M Hill, Inc. contracted with the Metropolitan Sewerage District of the County of Milwaukee to provide management and engineering services on a pollution abatement project. This project is an on-going one which may not be completed until the next decade.

An early phase of the project involved a sewer system evaluation survey which was intended to provide CH2M Hill and the Sewerage District with an analysis of the specific deficiencies of the Milwaukee area sewer system. According to the Master Agreement between CH2M Hill and the District, CH2M Hill was authorized to contract with consultants, including Professional Services Group, Inc. (PSG), among others. This $16,000,000 program began in 1978 and was completed in 1981 and utilized up to 250 trained technical personnel provided by the consulting firms.

[195]*195The contractual relationship between the plaintiff and the defendant is embodied primarily in two documents. The master sub-consultant agreement provided the general framework for the legal relationship between the two and Task Order 4-37 specifies the services which the plaintiff was to provide to the defendant on the sewer system evaluation survey. Task Order No. 4-37 provided that the plaintiff was to perform the following services as part of the team effort for the following tasks: organization and coordination, physical survey — manhole inspection and ground water monitoring, physical survey — flow monitoring, physical survey — building inspection, smoke testing, dye water flooding, internal inspection of sewer system and sewer system evaluation survey summary. The Task Order further provided that the workdays of labor to be provided by PSG were 7,078 work days at an estimated direct labor cost of $393,980.00.

In August of 1980, the Program Management Office, which was, according to the contract, responsible for the day-to-day supervision and management of the program, announced that it would begin down staffing by returning 17 people on August 22, 1980 and 18 people on August 29, 1980 to their respective companies. Four PSG personnel were part of this initial reduction. Further reductions were announced in late August and in September. At the time of the initial reductions, PSG had accumulated approximately two-thirds of the 7,078 workdays contemplated by the contract. The court has been unable to ascertain exactly how many workdays were performed by PSG; however, it does appear to be uncon-troverted that the actual direct labor performed by PSG totaled $296,645.38 or 75.2% of the $393,980 direct labor cost ceiling.

As the project wound down, it appeared that there were differences between the level of effort reflected in the estimated cost ceilings and the actual work performed by the various consultants. Frank Jenes of CH2M Hill developed a formula for recalculating the fixed dollar profits due under the various associate contracts. The following table represents the contractual fixed fee with its proposed revision under the Jenes formula:

Associate Zimmerman Madison CRS Howard, Needles DKI Linton & Company Donohue & Associates Polytech, Inc. Graef, Anhalt Globetrotters, Inc. PSG Proposed CH2M Hill's Revision as Total Proposed % of Total Fixed Fee Revision Fixed Fee $261,573.00 135,012.00 64,686.00 196,803.00 90,168.00 1,355.00 518,392.00 144,463.00 302,701.00 88,092.00 222,977.00 $251,097.00 128,790.00 58,669.00 186,478.00 88,071.00 1,331.00 486,969.00 145,339.00 299,746.00 77,284.00 161,849.00 95.99% 95.39% 90.69% 94.75% 97.67% 98.23% 93.94% 100.61% 99.02% 87.73% 72.58%

All of the Associate firms, with the exception of PSG, accepted the revised fee. Although CH2M Hill maintains that PSG refused to negotiate the reduction in the fixed fee, it does appear froga the record before the court that negotiations were ongoing from July 1981 until this action was filed on July 27, 1983. These negotiations included a request from PSG that the parties submit to binding arbitration pursuant to Article 7 of the Master Agreement between PSG and CH2M Hill. On its cross motion for summary judgment as to claim 1, PSG argues that it is entitled to the entire fixed dollar profit specified in the contract, whereas CH2M Hill maintains that the proposed revised, fixed dollar profit figure is equitable and that PSG breached the contract by failing to negotiate the figure.

DISCUSSION

The court finds the following contractual provisions relevant in resolving this controversy.

AGREEMENT BETWEEN CH2M HILL CENTRAL, INC. AND PROFESSIONAL SERVICES GROUP

ARTICLE 1. PROGRAM MANAGEMENT

A. That, the day-to-day supervision and management of the work called for by the CONTRACT and any and all matters relating thereto shall be the responsibility of the CH2M Program Director, or his delegate.

[196]*196ARTICLE 3. SCOPE

A. That, specific material and services to be provided by the ASSOCIATE under this AGREEMENT will be detailed in Associate Task Orders to be issued from time to time. Such Associate Task Orders will describe the work to be performed, basis of payment, and time for completion. Assignments will include work to be accomplished in the ASSOCIATE’S office(s) and/or personnel to be assigned to CH2M’s PROGRAM office.

B. That, the ASSOCIATE will not begin work on any of the services of an Associate Task Order until CH2M directs him in writing to proceed.

C. The ASSOCIATE shall, upon mutual agreement, accept assignments of Associate Task Orders that are within the capability of the ASSOCIATE’S staff. These assignments will provide that time allotments and fee arrangements will be consistent with values for this type of work negotiated by CH2M with other ASSOCIATES and the DISTRICT.

ARTICLE 4. COMPENSATION

A. As consideration for providing the services enumerated in the individual Associate Task Orders, CH2M shall pay the ASSOCIATE the amount of the ASSOCIATE’S Direct Salary expended for each service, plus a percentage of Direct Salary for total Overhead (Salary and General), plus Direct Expenses in connection therewith, plus a Fixed Dollar Profit for each service.

Said payment for each service shall be negotiated by the parties at the time each service is authorized and authorization to proceed shall be in the form of an Associate Task Order specifying the work to be performed, basis of payment and time for completion or the period of time for 'Which the service is to be provided. Each Associate Task Order shall become a supplement to and part of this AGREEMENT. On cost plus fixed dollar profit types of fees, the Cost Ceiling represented by Direct Salary, plus Total Overheads (Salary and General) and Direct Expenses shall not be exceeded without a formal amendment of this AGREEMENT.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

American Motorists Insurance v. Trane Co.
544 F. Supp. 669 (W.D. Wisconsin, 1982)
Nelsen v. Farmers Mutual Automobile Insurance
90 N.W.2d 123 (Wisconsin Supreme Court, 1958)
Barden v. Junior College District No. 520
406 U.S. 920 (Supreme Court, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
620 F. Supp. 194, 1985 U.S. Dist. LEXIS 17207, Counsel Stack Legal Research, https://law.counselstack.com/opinion/professional-services-group-inc-v-ch2m-hill-central-inc-wied-1985.