Probuild Co., L.L.C. v. DPR Construction

90 Va. Cir. 383
CourtCharlottesville County Circuit Court
DecidedJuly 3, 2015
DocketCase No. CL 15-203; Case No. CL 15-124
StatusPublished

This text of 90 Va. Cir. 383 (Probuild Co., L.L.C. v. DPR Construction) is published on Counsel Stack Legal Research, covering Charlottesville County Circuit Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Probuild Co., L.L.C. v. DPR Construction, 90 Va. Cir. 383 (Va. Super. Ct. 2015).

Opinion

By Judge Richard E. Moore

In this Motion To Stay Proceedings for Arbitration, I have now had time to read (or in some cases re-read) all of the pleadings and memoranda, as well as review the file, some of the cases cited, and my notes.

Factual Background

In this case ProBuild, a subcontractor to DPR, the general contractor, made a claim on DPR, on or about January 8, 2015, for certain payments allegedly due under the subcontract. On this same date, and prior to filing suit, ProBuild sent a formal Notice of Dispute, pursuant to § 17.2.1 of the subcontract (Exhibit 3 to the Complaint) for wrongly refusing to pay what it claimed was due under the subcontract. The parties then (on February 12, and again on March 20) engaged in informal discussions and negotiation, as anticipated by § 17.2.2, in an effort to resolve their differences. They did not, however, reach a mutually acceptable resolution.

ProBuild asserts that, as the “disputing party” under 17.2.1 and 17.2.2, it could have, under 17.2.3, requested mediation, but did not. DPR did not file a formal Notice of Dispute, and, as the non-disputing party under the [384]*384contract and respondent to ProBuild’s Dispute Notice, also did not, at that time, request mediation.

ProBuild then elected to file suit (on March 20,2014) against Continental Casualty and two other companies, the sureties on the payment bond, and (on May 8) against DPR. Continental and the other two sureties filed (on April 15) a Motion To Stay the Proceedings and asked for a referral to binding arbitration under the contract and to defer its case until the matter between ProBuild and DPR had been resolved by arbitration. (On April 7, DPR had filed a Demand for Arbitration.) DPR filed to intervene in the case against Continental and sought to join in their Motion for a Stay. The two cases have now been consolidated and that is no longer an issue.

ProBuild replies that DPR is not entitled to now pursue arbitration (or rather to force ProBuild to engage in arbitration) for several reasons: (1) DPR did not file a formal Notice of Dispute, so they are not entitled to the procedures under 17.1 et seq. at all, (2) ProBuild did not demand mediation (under 17.2.2 and 17.2.3) when the negotiations failed, and that is a prerequisite of the procedure in 17.2.4, and (3) the parties did not engage in mediation at any point in time, so mediation under 17.2.3 did not fail, because it was never attempted; so DPR is not entitled to mandatory binding arbitration under 17.2.4 of the contract. In addition, ProBuild asserts that, particularly as to Continental, but also as to DPR, 17.6 states that they still maintain their full litigation rights and that the mediation/ arbitration provisions for dispute resolution cannot limit their rights to trial, including with a jury, on all disputed issues.

DPR responds that (1) the letter they sent to ProBuild October 17,2014, was the equivalent of a Dispute Notice, (2) they are a disputing party also because they have a counterclaim against ProBuild and there is clearly a dispute between them, (3) they did request mediation and that is sufficient, and (4) even if they are not the disputing party and did not request mediation at any time, they were not required to go to mediation first in order to be entitled to pursue mandatory binding arbitration, as the mediation is not a condition precedent, but a right of DPR under 17.2.4, with no prerequisites.

Analysis

This matter turns on the proper reading and application of the dispute resolution provisions (paragraphs 17.2.1, et seq.) of the subcontract.

A. What Triggers the Right To Demand Arbitration?

Although there are many factors to be considered in this case, and which the Court has considered, the Court will address ProBuild’s third assertion first. Regardless of who the disputing party is, and whether anyone suggested or requested mediation, I find that the phrase in 17.2.4 “are unable to resolve any dispute in mediation” implies that they tried [385]*385mediation and could not resolve the matter, but that they made the effort. I do not think there is any other reasonable reading of that provision. If it had said “if the parties do not resolve the matter,” or “if the parties did not pursue mediation,” or “if the parties choose not to pursue mediation,” or “if mediation did not occur,” or the like, my view likely would be different. But I read this to mean: “mediation was engaged in but was not successful.” Continental rephrases this provision as: if the matter “cannot be resolved” in good faith by negotiation or mediation, but even this looser interpretation, in my view, requires an effort at mediation.

Thus I find that it is a prerequisite, or condition precedent, so that since they did not try mediation — ProBuild did not elect mediation, and DPR did not attempt to pursue mediation under the agreement — DPR is not now in a position to say that the contract requires arbitration, or that they are in a position to demand arbitration. The fact that such is not labeled in the subcontract as a “condition precedent” does not mean that it is not one. I believe that what is set out in the dispute resolution section (17.1 ff.) is a set, required sequence of events: formal dispute notice, required informal negotiation, required mediation at the discretion of the disputing party, and mandatory binding arbitration at DPR’s discretion. It seems to me that each is anticipated as a required step before the next step is taken. Note that 17.2.3 clearly anticipates the “commencement” of mediation proceedings, prior to the Disputing Party being able to require arbitration.

The Court is not relying on Perdue Farms v. Design Build, 263 Fed. Appx. 380, 383 (4th Cir. 2008), but rather on a plain reading of the terms of the subcontract, but the reasoning and holding of Perdue is entirely consistent with my opinion, and we reach the same conclusion, based on similar provisions.

I, therefore, agree that DPR is not entitled beyond what ProBuild agreed to, and I do not find that they agreed to arbitration unless mediation was pursued and unsuccessful. Because, in my view, this is dispositive, I do not need to address the issue of whether DPR was in a position as the non-disputing party to request mediation, but I do find ProBuild’s argument as to it being “the Disputing Party” to be persuasive, and, because it is a second reason, I believe ProBuild prevails, I will address it.

B. Who Is the Disputing Party?

The Court does agree with ProBuild that, in this scenario, ProBuild is in fact “the” disputing party, and DPR did not file a formal dispute, and is not the disputing party in this case, under the pertinent subcontract provision. (The subcontract does not use the term “a” disputing party, but repeatedly “the” disputing party.) There is no evidence that DPR ever filed a formal Notice of Dispute; I do not find that the October 17,2014, letter (Exhibit B to Defendant’s Brief in Support of Motion To Stay), which merely discussed some of their differences and how they might proceed to address them, [386]*386was in fact a Notice of Dispute. And if it had been, they would have been required, within thirty days, to pursue informal discussions and settlement efforts, which both sides appear to agree did not occur until February.

So, I find that they were not in a position to demand mediation.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
90 Va. Cir. 383, Counsel Stack Legal Research, https://law.counselstack.com/opinion/probuild-co-llc-v-dpr-construction-vacccharlottesv-2015.