Pro-Built Construction Firm

CourtArmed Services Board of Contract Appeals
DecidedFebruary 13, 2018
DocketASBCA No. 59278
StatusPublished

This text of Pro-Built Construction Firm (Pro-Built Construction Firm) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pro-Built Construction Firm, (asbca 2018).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Application Under the Equal Access ) to Justice Act of -- ) ) Pro-Built Construction Firm ) ASBCA No. 59278 ) Under Contract No. W5J9JE-I0-D-0016 )

APPEARANCE FOR THE APPELLANT: William J. Spriggs, Esq. Spriggs Consulting Services Lynchburg, VA

APPEARANCES FOR THE GOVERNMENT: Thomas J. Warren, Esq. Acting Engineer Chief Trial Attorney Pietro 0. Mistretta, Esq. Matthew S. Tilghman, Esq. Michael A. Rea, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Middle East Winchester, VA

OPINION BY ADMINISTRATIVE JUDGE D' ALESSANDRIS

Pending before the Board is the application for fees pursuant to the Equal Access to Justice Act (EAJA), 5 U.S.C. § 504, submitted by appellant, Pro-Built Construction Firm (Pro-Built). Because we find that the government's litigating position was substantially justified, we deny Pro-Built's application. In addition, we deny the motion for leave to file a sur-reply filed by the United States Army Corps of Engineers (Corps or government).

BACKGROUND

In a 1 June 2017 decision on the merits, the Board awarded Pro-Built $289,736.47, plus Contract Disputes Act (CDA) interest from the date of Pro-Built's claim. Pro-Built Construction Firm, ASBCA No. 59278, 17-1 BCA ,-J 36,774. The appeal involved a task order issued by the Corps on 31 July 2011, for construction of a police station in the Zabul Province of Afghanistan. On 4 March 2012, just over eight months later, the Corps terminated the task order for convenience of the government, due to "negative security conditions." The Corps did not issue a notice to proceed on the project. Id. at 179,191-93. Pro-Built submitted a termination settlement proposal, and later a certified claim, seeking payment of pre-performance costs of approximately $1.1 million. The contracting officer eventually issued a settlement by determination in the amount of $48,972. In the settlement by determination, the contracting officer found the costs to be unreasonable pursuant to Federal Acquisition Regulation (FAR) 31.201-2, Determining allowability, and also cited to the findings by the Defense Contract Audit Agency (DCAA) that the contractor began charging costs to the contract before the notice to proceed was issued. Pro-Built, 17-1BCA136,774 at 179,193. (R4, tabs 2, 34)

Before the Board, Pro-Built presented a revised damages calculation in the amount of $816,273 (including the $48,972 already paid in the settlement by determination). Pro-Built, 17-1 BCA 136,774 at 179, 190-95. James McGovern, Pro-Built's expert witness, testified that he removed the costs of employees that he determined could have worked on other projects. Id. at 179,194. At the hearing, and in post-hearing briefing, the Corps argued that it was unreasonable for Pro-Built to have incurred costs before the notice to proceed, but also that there were multiple deficiencies in Pro-Built's termination for convenience claim, including the fact that individuals identified as working full-time on the task order appeared to have done work on other Pro-Built projects during the period in question. Id. at 179,196.

By application dated 28 August 2017, Pro-Built sought reimbursement of $39,087.50 in attorney fees and $62,955.98 1 in fees and expenses for Pro-Built's expert witness (app. mot. at 1-2).

DECISION

The EAJA provides that a business with a net worth less than $7,000,000 that prevails before the Board "shall [be] award[ ed]" the fees and other expenses that it incurred unless the position of the government was "substantially justified" or other circumstances make such an award unjust. 5 U.S.C. § 504; see also Rex Systems, Inc., ASBCA No. 52247, 02-1BCA131,760 at 156,854. The Corps does not oppose Pro-Built's EAJA application on the basis of Pro-Built's status as a prevailing party, its net worth, or the timeliness of its application. Rather, the Corps argues that Pro-Built is not eligible for EAJA fees, because the Corps' litigating position was substantially justified. (Gov't opp'n at 4)

To prevail in its substantial justification defense, the government is not required to prove that it had a substantial likelihood of victory in the litigation, but it does bear the burden of proof to demonstrate that "a reasonable person could think [the government's position is] correct, that is [that] it has a reasonable basis in law and fact." Pierce v. Underwood, 487 U.S. 552, 566 n.2 (1988); Rex Systems, 02-1 BCA

1 Attachment C to Pro-Built's motion claims $62,955.18 rather than $62,955._28.

2 131,760 at 156,854. Substantial justification is determined on the basis of the entire record before the Board, and the entirety of the government's conduct. Job Options, Inc., ASBCA No. 56698, 11-1 BCA 134,663 at 170,761. The government's litigating position is more likely to be substantially justified when greater "legal uncertainty" is presented, such as when there is a question of first impression. Rex Systems, 02-1 BCA 131,760 at 156,855 (citing Pat's Janitorial Service, Inc., ASBCA No. 29129, 86-2 BCA 1 18,995 at 95,923). In addition, the government's litigating position is more likely to be substantially justified when there are close factual questions and the Board's resolution of the appeal turns upon the weight, persuasiveness and credibility assigned to conflicting evidence. Job Options, 11-1 BCA 1 34,663 at 170,761.

The Corps contends that its litigating position was substantially justified because it successfully challenged a substantial portion of the costs claimed by Pro-Built. According to the Corps, at the hearing it established that Pro-Built's daily standby labor rate was unreasonable, that Pro-Built had not established that the Corps provided continued representations that the notice to proceed would be issued shortly, and that there were numerous questionable employee costs contained in Pro-Built's claim. The government additionally argues that the law was unclear regarding the reasonableness of incurring pre-contract costs. (Gov't opp'n at 7-10)

Pro-Built contends that the government's litigating position was unreasonable because the contracting officer's final decision, the DCAA audit report, and the Corps' briefing before the Board took the position that the notice to proceed clause prevented recovery of any costs by Pro-Built (app. resp. at 1-2). Pro-Built contends that our opinion held that the Corps' litigating position was unreasonable by characterizing the Corps' position as being that "none of the costs were reasonable" (app. resp. at 2 (citing Pro-Built, 17-1BCA136,774 at 179,196)).

Upon review of the entire record before us, we find that the Corps' overall litigating position was substantially justified. Admittedly, the contracting officer's settlement by determination, which constituted the contracting officer's final decision, does cite the DCAA audit report's finding that Pro-Built was not authorized to incur costs prior to the notice to proceed, but the actual basis for the final decision was that the costs were unreasonable pursuant to FAR 31.201-2, Determining allowability (R4, tab 34). Additionally, the Corps' position in its post-hearing briefing was not that pre- performance costs were strictly unallowable, but that Pro-Built' s claimed costs were unreasonable (gov't br. at 16-18).

Our damages award was based upon a determination of reasonableness, an issue of fact.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pierce v. Underwood
487 U.S. 552 (Supreme Court, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
Pro-Built Construction Firm, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pro-built-construction-firm-asbca-2018.