Pro-Built Construction Firm

CourtArmed Services Board of Contract Appeals
DecidedJune 1, 2017
DocketASBCA No. 59278
StatusPublished

This text of Pro-Built Construction Firm (Pro-Built Construction Firm) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pro-Built Construction Firm, (asbca 2017).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Pro-Built Construction Firm ) ASBCA No. 59278 ) Under Contract No. W5J9JE-10-D-0016 )

APPEARANCE FOR THE APPELLANT: William J. Spriggs, Esq. Spriggs Consulting Services Lynchburg, VA

APPEARANCES FOR THE GOVERNMENT: Thomas H. Gourlay, Jr., Esq. Engineer Chief Trial Attorney Pietro 0. Mistretta, Esq. Matthew S. Tilghman, Esq. Michael A. Rea, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Middle East Winchester, VA

OPINION BY ADMINISTRATIVE JUDGE D' ALESSANDRIS

In July 2011, the United States Army Corps of Engineers (Corps) awarded Contract No. W5J9JE- l O-D-0016 to appellant, Pro-Built Construction Firm (Pro-Built) for construction of a police station in Atghar District, Zabul Province, Afghanistan. The Corps did not issue a notice to proceed before terminating the contract for the convenience of the government in March 2012. In March 2012 Pro-Built first submitted a termination for convenience settlement proposal. In March 2014, following several revisions, and a Defense Contract Audit Agency (DCAA) audit, Pro-Built submitted a certified claim of roughly $1.1 million. In a final decision dated 4 April 2014, the Corps' contracting officer issued a unilateral determination that Pro-Built was entitled to $48,972. Pro-Built timely appealed that final decision to this Board. We sustain the appeal in part.

FINDINGS OF FACT

I. The Contract

1. The U.S. Army Corps of Engineers Afghanistan District North issued a Multiple Award Task Order Contract (MATOC) No. W5J9JE-10-D-0016 to Pro-Built on 18 March 2010 (R4, tab 3). On 31July2011 the Corps awarded Task Order No. 0009 (the contract or task order 9) in the amount of $4,976,022.32 to Pro-Built (R4, tab 16). Pro-Built performed other task orders pursuant to the MA TOC in other parts of Afghanistan (tr. 1144, 60).

2. Task order 9 was a firm-fixed-price contract for the design and construction of an Afghanistan National Police Uniformed Police District Headquarters Compound in Atghar District, Zabul Province (R4, tabs 16-17). The contract required site adaption and construction including an administration building, a well house, guard shacks, guard towers, barracks buildings, women's barracks, a Criminal Investigative Directorate/Family Response Unit building, a water tower and tank, a fuel storage facility, a vehicle refuel point, septic tank, perimeter security wall, and primary and secondary entry control points (R4, tab 1 at 5, tab 13 at 65). The contract required approval of a security plan before the contractor could start work on the project site, and submission of a quality control plan not later than five days after the notice to proceed (R4, tab 13 at 131, 219).

3. The contract had a performance period of 365 days from receipt of the notice to proceed (R4, tab 17 at 14). Although the Corps informed Pro-Built that it planned to issue the notice to proceed at the Pre-construction Conference (R4, tab 16 at 1), the notice was never issued (R4, tab 1 at 5).

4. Relevant to this appeal, the contract contained Federal Acquisition Regulation (FAR) 52.211-10, COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) (R4, tab 17 at 14).

5. The contract also contained FAR 52.249-2, TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED-PRICE) (MA y 2004) which provides that:

(g) If the Contractor and the Contracting Officer fail to agree on the whole amount to be paid because of the termination of work, the Contracting Officer shall pay the Contractor the amounts determined by the Contracting Officer as follows ... :

(2) The total of -

(i) The costs incurred in the performance of the work terminated, including initial costs and preparatory expense allocable thereto, but excluding any costs attributable to

2 supplies or services paid or to be paid under subparagraph ( f)( 1) of this clause;

(ii) The cost of settling and paying termination settlement proposals under terminated subcontracts that are properly chargeable to the terminated portion of the contract if not included in subdivision (g)(2)(i) of this clause; and

(iii) A sum, as profit on subdivision (g)(2)(i) of this clause, determined by the Contracting Officer under 49.202 of the Federal Acquisition Regulation, in effect on the date of this contract, to be fair and reasonable; however, if it appears that the Contractor would have sustained a loss on the entire contract had it been completed, the Contracting Officer shall allow no profit under this subdivision (iii) and shall reduce the settlement to reflect the indicated rate of loss.

(R4, tab 3 at 53-55)

6. The contract provided for liquidated damages of $1,579.00 from Pro-Built per calendar day of delay of completion of the contract beyond the 365-day performance period (R4, tab 17 at 14).

7. The contract also included a provision entitled "Sequence of Design-Construction (Fast-Track)" providing:

After receipt of the Contract Notice to Proceed (NTP) the Contractor shall initiate design, comply with all design submission requirements and obtain Government review of each submission. The contractor may begin construction on portions of the work for which the Government has reviewed the final design submission and has determined satisfactory for purposes of beginning construction. The Contracting Officer will notify the Contractor when the design is cleared for construction.

(R4, tab 13 at 197)

8. The contract scope of work provided in~ 3.1.1 "Design Concept Coordination Meeting" that, shortly after the notice to proceed, the government or contractor could suggest a meeting to review the design submittal process (R4, tab 13

3 at 189). The scope of work described the design submittal process, including~ 3.8.2 "Sequence of Design-Construction (Fast-Track)" which provided that the contractor could begin construction on portions of the project for which the government had approved the submittals while other portions of the design were still being reviewed (id. at 197). The scope ofwork specification also contained~ 3.8.5 "Commencement of Construction" which provided that commencement of construction prior to the notice to proceed would "be at the Contractor's own risk and expense" (id. at 197).

9. The DD Form 1155 awarding Task Order No. 9 to Pro-Built provided for the base bid proposal line items that, "THIS DOES NOT CONSTITUTE YOUR NOTICE TO PROCEED" (R4, tab 17 at 6). The same warning was included for the optional bid line items (id. at 7).

10. The Notice of Award letter advised Pro-Built that it was required to account for "all contractor personnel, to include subcontractors and vendors, performing services under this contract in the U.S. [Central Command] Area of Responsibility" in the Synchronized Pre-deployment Operational Tracker (SPOT) (R4, tab 16 at 1). The letter provided that SPOT registration demanded Pro-Built's "immediate attention in advance of the preconstruction conference" and additionally required Pro-Built to "enter 'all' your personnel under this contract within ten ( 10) calendar days from the date of this letter" (R4, tab 16 at 1-2).

11. Mr. Ismail Amiri, managing consultant and acting chief executive officer for Pro-Built testified that he was familiar with the SPOT system and that the contract required Pro-Built to identify its employees within ten days (tr. 1/66-67). However, Mr. Amiri testified that usually after receiving an award Pro-Built would enter three or four names into the SPOT system and that this was acceptable to the contracting officer (tr. 1/67). Mr. Amiri was unable to recall if any employees were entered into the SPOT system for task order 9 (tr. 1167-68).

12. Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Meeks v. United States
758 F.2d 661 (Federal Circuit, 1984)
Kellogg Brown & Root Services, Inc. v. United States
728 F.3d 1348 (Federal Circuit, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Pro-Built Construction Firm, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pro-built-construction-firm-asbca-2017.