Priola Construction Corp. v. Profast Development Group, Inc.

21 So. 3d 456, 9 La.App. 3 Cir. 342, 2009 La. App. LEXIS 1735, 2009 WL 3191130
CourtLouisiana Court of Appeal
DecidedOctober 7, 2009
DocketNo. CA 09-342
StatusPublished
Cited by4 cases

This text of 21 So. 3d 456 (Priola Construction Corp. v. Profast Development Group, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Priola Construction Corp. v. Profast Development Group, Inc., 21 So. 3d 456, 9 La.App. 3 Cir. 342, 2009 La. App. LEXIS 1735, 2009 WL 3191130 (La. Ct. App. 2009).

Opinion

EZELL, Judge.

_JjThis appeal involves application of the Louisiana Credit Agreement Statutes, La. R.S. 6:1121-6:1124, and accession principles. At issue is whether Capital One, N. A., is liable to Priola Construction Corporation for improvements Priola made to the Capital One building in downtown Lake Charles. The improvements were made pursuant to a Letter of Agreement with several defendants referred to for simplicity as the “Johnson Defendants.”1 The trial court granted Capital One’s motions for summary judgment and dismissed all of Priola’s claims against Capital One. Priola appealed, and for the following reasons, we affirm the judgment of the tidal court.

FACTS

Blake McCaskill, a commercial loan officer with Capital One, knew one of the Johnson Defendants, Fulton “Flip” Johnson, from their days of playing football together at McNeese State University. Mr. McCaskill heard that Mr. Johnson was looking at constructing a modular building facility in addition to some condominiums in the Lake Charles area, so he contacted Mr. Johnson about Capital One doing business with him. Discussions soon evolved into discussing the need for office space, so Mr. McCaskill told him about the Capital One Building.

On October 18, 2006, Capital One entered into a lease agreement with the Johnson Defendants to lease Suites 2100 and 2200, the twenty-first and twenty-second floors, in the Capital One Building. The twenty-first floor had been a restaurant, and the Johnson Defendants wanted to open a restaurant and sports bar. The twenty-second floor was to be the private offices for Mr. Johnson.

| ¡According to Mr. McCaskill, he had discussed the potential projects with a client of Priola. Josh Priola wanted to be introduced to Mr. Johnson, so Mr. McCas-kill took him upstairs in the Capital One Building for an introduction. At the time, the Johnson Defendants had actually started some demolition work. On October 27, 2006, Priola entered into a Letter of Agreement with the Johnson Defendants to renovate the twenty-first floor of the Capital One Building. The anticipated costs were between $400,000.00 and $600,000.00. Priola agreed to be paid in a lump sum upon completion of the work or no later than January 31, 2007.

The Letter of Agreement further stated that Priola was agreeable to such terms provided:

[458]*458Pro Fast Development Group, LLC, provides Priola Construction Corporation, on or before October 30, 2006, proof satisfactory to Priola Construction Corporation that Pro Fast Development Group, LLC, has obtained a line of credit from a federally insured lending institution in an amount not less than $600,000.00, and that its agreement with the lender with respect to said line of credit provides that monies may be drawn against the line of credit only if disbursed by draft or electronic funds transfer payable solely and directly to Priola Construction Corporation; and (2) Fulton Johnson and any and all other members/owners of Pro Fast Development Group, LLC, on or before October 30, 2006, execute within a reasonable time after acceptance of this proposal all contracts and related documents necessary to effect the agreements proposed herein on terms mutually agreeable to the parties.

The Johnson Defendants wanted the work completed in order to host a New Year’s Eve grand opening on December 31, 2006. Priola never received the proof that the Johnson Defendants had secured a line of credit. Due to the time constraints, Josh Priola claims he approached Mr. McCaskill a few days after the agreement was signed to inquire if Capital One had agreed to finance the improvements. Priola claims that Mr. McCaskill advised “they were collecting information, had one more piece of information to get. They got it, and it looked great and it was more than what they hoped for and the commitment process would begin when he got back in the | ^office.” At that point, Priola began and completed the improvements at a cost in excess of $1.1 million.

Prior to completion, Priola entered into an amended contract with the Johnson Defendants on November 15, 2006, which increased the budget to between $850,00.00 and $950,000.00. On December 22, 2006, a separate contract was entered into between the Johnson Defendants and Priola for renovations to a separate space known as The Y.I.P. Room for a proposed budget of $70,000.00.

A loan application to Capital One by the Johnson Defendants was not submitted until November 14, 2006. On December 4, 2006, the loan was denied for failure to submit proper financial documentation and supporting schedules. Priola found out that the loan had been denied on December 21, 2006.

On May 9, 2007, Priola filed suit against the Johnson Defendants claiming that they had paid nothing for the work performed by Priola and that it was owed $1,133,116.49. On June 1, 2007, the petition was amended to add Capital One as a defendant on the basis of negligent misrepresentation, detrimental reliance, and breach of contract. A preliminary default was entered against the Johnson Defendants on August 27, 2007. Capital One filed a motion for summary judgment.

A hearing on Capital One’s motion for summary judgment was held on August 19, 2008. The trial court granted Capital One’s motion and dismissed Priola’s claims against it. Priola then filed a supplemental and amending petition elaborating on its claim for damages under the principles of accession. Again, Capital One moved for summary judgment. A hearing on the matter was held on December 17, 2008, with the trial court again ruling in favor of Capital One. Judgment was signed that same day which also included the ruling on the previous motion for summary judgment, thereby dismissing all of Priola’s claims against Capital One in this matter. Priola 14then appealed the judgment.

[459]*459SUMMARY JUDGMENT

Appellate review of the granting of a motion for summary judgment is de novo, using the identical criteria that govern the trial court’s consideration of whether summary judgment is appropriate. Bonin v. Westport Ins. Corp., 05-0886, p. 4 (La.5/17/06), 930 So.2d 906, 910; Schroeder v. Bd. of Sup’rs of La. State Univ., 591 So.2d 342, 345 (La. 1991). A motion for summary judgment is a procedural device used when there is no genuine issue of material fact. The summary judgment procedure is designed to secure the just, speedy, and inexpensive determination of every action and shall be construed to favorably accomplish these ends. La. C.C.P. art. 966(A)(2). A motion for summary judgment is properly granted only if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show there is no genuine issue of material fact, and the mover is entitled to judgment as a matter of law. La. C.C.P. art. 966; Duncan v. USAA Ins. Co., 06-0363, p. 4 (La.11/29/06), 950 So.2d 544, 546-547. A fact is material if it potentially insures or precludes recovery, affects a litigant’s ultimate success, or determines the outcome of the legal dispute. Hines v. Garrett, 04-0806, p. 1 (La.6/25/04), 876 So.2d 764, 765 (citing Smith v. Our Lady of the Lake Hosp., Inc., 93-2512, p. 27 (La.7/5/94), 639 So.2d 730, 751). A genuine issue of material fact is one as to which reasonable persons could disagree; if reasonable persons could reach only one conclusion, there is no need for trial on that issue and summary judgment is appropriate. Hines, 876 So.2d at 765-766.

King v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kano Investments, L.L.C. v. Kojis Construction, L.L.C.
113 So. 3d 1113 (Louisiana Court of Appeal, 2013)
Ames v. Ohle
97 So. 3d 386 (Louisiana Court of Appeal, 2012)
Anthony Mose, Jr. v. Keybank National Assoc
464 F. App'x 260 (Fifth Circuit, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
21 So. 3d 456, 9 La.App. 3 Cir. 342, 2009 La. App. LEXIS 1735, 2009 WL 3191130, Counsel Stack Legal Research, https://law.counselstack.com/opinion/priola-construction-corp-v-profast-development-group-inc-lactapp-2009.