Principal Commercial Acceptance, LLC v. Buchanan Fund V, LLC

Court of Appeals of Texas·Decided December 6, 2012·No. 01-11-00782-CV·Published

Opinion

Opinion issued December 6, 2012.

In The

Court of Appeals

For The

First District of Texas

Guaranty ambiguous, found the evidence supported Buchanan’s interpretation of the Guaranty, and determined PCA had not proved that Buchanan breached. On appeal, PCA contends the trial court erred in finding the Guaranty ambiguous and in finding that the Guaranty was not breached. We affirm.

Background

PCA is a lender specializing in originating and underwriting commercial real estate loans. Buchanan and MAC Cypress Creek GP, LLC (“Macfarlan”) formed a partnership, Cypress Creek Centre LP, to purchase and renovate an office complex in northwest Houston. PCA agreed to be the lender for the project.

PCA and Cypress Creek entered into a Loan Agreement for the project.

The Loan Agreement provided that the purchase and redevelopment of the property, estimated to cost $100 million, would be funded at a 75% debt-to-25% equity ratio. PCA agreed to finance $75 million over time and Cypress Creek agreed to contribute $25 million in equity for the project. Before closing, Cypress Creek proposed that it contribute about half of the equity, approximately $12.2 million, at closing, and that it contribute the balance of the equity—$12,814,031— in stages throughout the life of the project, as costs were incurred. PCA agreed to this proposal. In the Loan Agreement, the parties defined that portion of the $25 million equity contribution as “Deferred Equity”:

The portion of the Borrower’s cash equity investment in the Project to be funded by Borrower after Closing as provided in Section 4.7

herein, in an aggregate amount of not less than Twelve Million, Eight Hundred Fourteen Thousand, Thirty One and 00/Dollars ($12,814,031.00).

The parties further agreed that Cypress Creek would fund the Deferred Equity as Disbursement Requests were made by PCA, as set forth in Section 4.7 of the Loan Agreement. Section 4.7 provides:

4.7 Deferred Equity. Notwithstanding any provision of this Agreement or the Loan Documents to the contrary, [PCA] shall have no obligation to disburse [project costs] except in accordance with the Project Budget and not to exceed seventy-five percent (75%) of each Disbursement Request approved by [PCA]. [Cypress Creek] shall fund twenty-five [percent] (25%) of each such Disbursement Request out of pocket as Deferred Equity when and as such amounts are due and shall provide [PCA] on a monthly basis with evidence of payment during the preceding month of such Deferred Equity. . . . [Cypress Creek] further acknowledges and agrees that [PCA] has agreed to fund the Loan in reliance upon [Cypress Creek’s] agreement to pay and contribute the Deferred Equity when and as due.

(Emphasis added). In other words, PCA would issue Disbursement Requests periodically, and each Disbursement Request would be funded proportionally, with PCA loaning 75% and Cypress Creek contributing equity to fund the remaining 25%.

On the same day the parties entered into the Loan Agreement, Buchanan entered into a “Limited Guaranty of Payment” with PCA. In it, Buchanan guaranteed to PCA:

(a) If for any reason whatsoever, [Cypress Creek] fails to timely fund the Deferred Equity when and as required pursuant to the Loan Agreement, [Buchanan] shall fund such amounts within ten (10)

business days after notice from [PCA] of such failure by [Cypress Creek], provided, however, [Buchanan] will not be obligated to fund Deferred Equity in excess of Twelve Million, Eight Hundred Fourteen Thousand Thirty-One and No/00 Dollars ($12,814,031.00) in the aggregate (the “Buchanan Funding Obligation”).

As the project unfolded, Cypress Creek made all periodic Deferred Equity contributions as required by the Loan Agreement, but failed to meet a separate funding obligation under the Loan Agreement, one that required Cypress Creek to fund approximately $2.1 million for net operating expenses through an escrow account. After Cypress Creek failed to fund the escrow, PCA informed Cypress Creek of its default and gave it time to cure. The parties negotiated to try to resolve this issue, but the negotiations ultimately failed, and PCA foreclosed on the property.

PCA then sued Buchanan under the Guaranty to recover Deferred Equity that Cypress Creek did not contribute in the amount of $8,359,245.1 Buchanan denied liability, responding that the Guaranty did not obligate Buchanan to contribute any remaining unfunded Deferred Equity because Cypress Creek was current on its payments of Deferred Equity “when and as required by [Section 4.7 of] the Loan Agreement” (i.e., in response to Disbursement Requests and in an amount equal to 25% of each Disbursement Request). Buchancan further

1 PCA calculated this number by subtracting the total of various amounts Cypress Creek had contributed as its 25% proportionate share in compliance with earlier Disbursement Requests from $12,814,03, the total Deferred Equity.

responded that the Loan Agreement did not accelerate the payment of Deferred Equity upon default, nor did Cypress Creek promise to pay the Deferred Equity except in connection with disbursement requests. In addition, Buchanan asserted the affirmative defense of ambiguity.

After a bench trial, the trial court concluded the Guaranty was ambiguous and imposed no further obligation on Buchanan. Based on these conclusions, the trial court rendered a take-nothing judgment. PCA appeals.

Discussion

In its first and second issues, PCA contends the Guaranty is unambiguous and requires Buchanan to pay the remaining amount of Deferred Equity that Cypress Creek did not pay. Thus, PCA argues, the trial court erred by failing to enforce the Guaranty. Buchanan responds that the Guaranty imposes no such obligation, and that the trial court correctly concluded the Guaranty is ambiguous. A. Law Pertaining to Construction of Contracts The interpretation of a guaranty is a question of law that this court reviews de novo. Wasserberg v. Flooring Servs. of Tex., LLC, 376 S.W.3d 202, 206 (Tex. App.—Houston [14th Dist.] 2012, no pet.) (citing Gulf Ins. Co. v. Burns Motors, Inc., 22 S.W.3d 417, 423 (Tex. 2000)). In construing a guaranty, as with other contracts, the primary concern of the reviewing court is to ascertain the intent of the parties. 84 Lumber Co. v. Powers, No. 01-09-00986-CV, 2012 WL 243524, at

*7 (Tex. App.—Houston [1st Dist.] Jan. 26, 2012, no pet.) (citing Coker v. Coker, 650 S.W.2d 391, 393 (Tex. 1983)). We begin our inquiry into the parties’ intent with the contract’s express language. Progressive Cnty. Mut. Ins. Co. v. Kelley, 284 S.W.3d 805, 807 (Tex. 2009). A guarantor’s liability is measured by the principal’s liability, unless the guaranty expressly provides for greater or lesser liability. Pham v. Mongiello, 58 S.W.3d 284, 288 (Tex. App.—Austin 2001, pet. denied). Any uncertainty in a guaranty must be resolved in favor of the guarantor. See Coker, 650 S.W.2d at 394 n.1; 84 Lumber Co., 2012 WL 243524, at *7.

If a contract is “so worded that it can be given ‘a certain or definite legal meaning or interpretation,’ it is not ambiguous and the reviewing court will construe it as a matter of law.” 84 Lumber Co., 2012 WL 243524, at *2 (quoting Coker, 650 S.W.2d at 393). An unambiguous contract will be considered the objective statement of the parties’ intent and enforced as written. Id. Extrinsic evidence may be admitted to determine the true meaning of the contract only after the contract had been determined to be ambiguous. Nat’l Union fire Ins. Co. of Pittsburgh, PA v. CBI Indus., Inc., 907 S.W.2d 517, 520 (Tex. 1995).

Free access — add to your briefcase to read the full text and ask questions with AI

Principal Commercial Acceptance, LLC v. Buchanan Fund V, LLC, (Tex. Ct. App. 2012).

Principal Commercial Acceptance, LLC v. Buchanan Fund V, LLC (Principal Commercial Acceptance, LLC v. Buchanan Fund V, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

J.M. Davidson, Inc. v. Webster
128 S.W.3d 223 (Texas Supreme Court, 2003)
Progressive County Mutual Insurance Co. v. Kelley
284 S.W.3d 805 (Texas Supreme Court, 2009)
In Re 24R, Inc.
324 S.W.3d 564 (Texas Supreme Court, 2010)
Fort Worth Independent School District v. City of Fort Worth
22 S.W.3d 831 (Texas Supreme Court, 2000)
Gulf Insurance Co. v. Burns Motors, Inc.
22 S.W.3d 417 (Texas Supreme Court, 2000)
Coker v. Coker
650 S.W.2d 391 (Texas Supreme Court, 1983)
Clark v. Walker-Kurth Lumber Co.
689 S.W.2d 275 (Court of Appeals of Texas, 1985)
Lenape Resources Corp. v. Tennessee Gas Pipeline Co.
925 S.W.2d 565 (Texas Supreme Court, 1996)
Pham v. Mongiello
58 S.W.3d 284 (Court of Appeals of Texas, 2001)
Cox v. Lerman
949 S.W.2d 527 (Court of Appeals of Texas, 1997)
Cleveland Construction, Inc. v. Levco Construction, Inc.
359 S.W.3d 843 (Court of Appeals of Texas, 2012)
84 Lumber Company, L.P. v. David Powers
393 S.W.3d 299 (Court of Appeals of Texas, 2012)