Princess Furnace Co. v. Virginia-Carolina Chemical Co.

215 F. 329, 131 C.C.A. 471, 1914 U.S. App. LEXIS 1245
CourtCourt of Appeals for the Fourth Circuit
DecidedJune 12, 1914
DocketNo. 1196
StatusPublished
Cited by3 cases

This text of 215 F. 329 (Princess Furnace Co. v. Virginia-Carolina Chemical Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Princess Furnace Co. v. Virginia-Carolina Chemical Co., 215 F. 329, 131 C.C.A. 471, 1914 U.S. App. LEXIS 1245 (4th Cir. 1914).

Opinion

KNAPP, Circuit Judge.

The plaintiff in error, defendant below, is a Virginia corporation which operated a blast furnace at Glen Wilton, [330]*330Va , and in connection therewith maintained a desulphurizing plant for the extraction of sulphur from pyrites cinder and nodulizing the same for use with its raw ores in the production of pig iron.

The defendant in error, plaintiff below, is a New Jersey corporation which was engaged, among other things, in the reduction of pyrites ores and extracting sulphur therefrom for the manufacture of sulphuric acid, leaving a by-product known as pyrites cinder which contains a large percentage of iron. It maintained several plants, one of which was located near Lynchburg, Va., and another at Richmond, Va., known as the Allison & Addison plant.

Pyrites ores are of two sizes or classes, namely, one known as lump and the other as fines, and each class requires a different furnace for its treatment. Lump ores were treated at the Allison & Addison plant and fines at the Lynchburg and other plants. The cinder produced from the treatment of lump ore is known as lump pyrites cinder, while, that produced in the treatment of fines ore is known as fines pyrites cinder. The general term “Pyrites Cinder” embraces both classes.

In April, 1907, the parties named entered into a contract whereby the furnace company purchased the entire output of fines cinder from certain plants of the chemical company, amounting to approximately 1,000 tons a month, for a period of five years. Prior to June, 1909, the furnace company was in default under this contract, and a large amount of fines cinder accumulated on the hands of the chemical company, entailing a loss of some $6,000 for which the furnace company appears to have been liable. Various negotiations thereupon followed, with ’the result that a new contract was made under date of June 12, 1909, which is the basis of the present suit. The provisions of this contract,' so far as they require’ recital, are substantially as follows:

The prior contract of April, 1907, was annulled without recourse or claim of damages by either party.

The chemical company agreed to sell to the furnace company all of its stock of cinder on hand at its plant known as the Allison & Addison, plant at Richmond, and all of its stock of cinder at its plant near’Lynch-burg, together with all cinder that should be produced at these plants prior to June 1, 1912; and it was specified that the chemical company made no representations as to the amount or quality of its stocks of cinder then on hand, nor as to the amount or quality of cinder which it might produce during the period mentioned.

The furnace company agreed to purchase from the chemical company, and pay for at the rate of $1.25 per ton, a minimum of 500 tons of pyrites cinder per month, beginning with June, 1909, and to continue to order and receive cinder at the rate of not less than 500 tons per month during the life of the contract.

In case the furnace company failed to order and receive as much as a thousand tons of cinder in any two consecutive months, the chemical company had the option of revoking the contract and demanding payment from the furnace company of $5,000 as liquidated damages.

It will be observed that the first contract related specifically to “fines” cinder, while the second contract covered all the “cinder” output of two named plants, one of which produced only lump cinder. There may have been at one time some misunderstanding on the pai t of the [331]*331furnace company as to the kind of cinder which it had agreed to take, but the contract in that regard is perfectly plain, and the chemical company was entitled to have it performed according to its terms.

Shipments of cinder under this contract were begun about the date of its execution and continued from time to time, in varying amounts per month, until some time in November. 1910. There were no shipments after that date. In November, 1911, the chemical company, alleging that the furnace company had made default and become liable under the terms of its contract, served a notice of revocation and informed the furnace company that at the expiration of 90 days it would demand payment of the $5,000 liquidated damages provided in the contract. Thereafter in July, 1912, this action was commenced. The defendant pleaded the general issue and also filed a number of special pleas setting up various defenses. Upon the trial of the case, and after all the evidence was submitted, the District Court refused to direct a verdict for the forfeiture named in the contract, but did direct a verdict for actual damages in the sum of $3,115.20, together with interest in the sum of $1,238.50, or a total of $4,353.70.

This was the amount of damages shown by undisputed evidence which is summarized in the following statement:

[332]*332. The assignments of error present three general questions, only one of which goes to the real merits of the controversy. It is contended by the furnace company that there was no violation of the contract on its part because the chemical company had consented to postpone shipments and in effect waived its right to cancel the contract and demand damages for nonperformance. A careful examination of the record satisfies us that this contention cannot be sustained. The numerous letters which passed between the parties indicate that the business of the furnace company was not prosperous, and consequently it was not in a situation to make use of the quantity of binder for which it had contracted. The chemical company was asked to defer deliveries and thus give the furnace company an opportunity to take advantage of more favorable business conditions. Without going into the correspondence in detail, it is sufficient to say that the furnace company was seeking delay and the chemical company disposed to be accommodating. Shipments were in fact suspended at one time and another, but we find nothing which can be fairly construed as a waiver by the chemical company of its right to have the contract executed in accordance with its terms. The situation in this regard, as we see it, is summed up in a letter of the chemical company of September 18, 1911, which reads as follows:

“Shipments under this contract were suspended, as you know, at the urgent request of your company, although the Virginia-Carolina Chemical Company has always been ready and anxious to make shipments to your company in compliance with the contract.
“We now write to say that, in reply to your request to still further defer the resumption of shipments, we will be willing to defer shipments of cinder to your company until November 1st next, provided you will write and forward to us the inclosed letter stating that our noninsistence on your taking the cinder as provided for in the contract with your company shall in no way impair or annul our contract with your company and our rights under the same, and that you will begin to accept on of before November 1st next shipments of cinder in accordance with the contract and fulfill the requirements of the same thereafter; it being understood that the Virginia-Carolina Chemical Company is not in any way to be prejudiced by acceding to your request for indulgence now or heretofore, nor by your default in complying with this contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
215 F. 329, 131 C.C.A. 471, 1914 U.S. App. LEXIS 1245, Counsel Stack Legal Research, https://law.counselstack.com/opinion/princess-furnace-co-v-virginia-carolina-chemical-co-ca4-1914.