Princess Cruises, Inc. v. General Electric Co.

950 F. Supp. 151, 1997 A.M.C. 1168, 1996 U.S. Dist. LEXIS 19064
CourtDistrict Court, E.D. Virginia
DecidedDecember 23, 1996
DocketCivil Action 2:96cv391
StatusPublished
Cited by6 cases

This text of 950 F. Supp. 151 (Princess Cruises, Inc. v. General Electric Co.) is published on Counsel Stack Legal Research, covering District Court, E.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Princess Cruises, Inc. v. General Electric Co., 950 F. Supp. 151, 1997 A.M.C. 1168, 1996 U.S. Dist. LEXIS 19064 (E.D. Va. 1996).

Opinion

OPINION AND ORDER

MORGAN, District Judge.

On April 22, 1996, Princess Cruises, Inc. (“Princess”), filed a Four-Count Complaint against General Electric Company (“GE”) alleging: (1) breach of contract; (2) breach of express warranty; (3) breach of implied maritime warranty; and (4) negligence. All claims arise from a contract obligating GE to inspect turbines, make recommendations and perform other related services on Princess’s ship, the S.S. Sky Princess.

Pending before the Court is GE’s Motion for Summary Judgment as to all claims and Princess’s Motion for Partial Summary Judgment as to the contractual claims. On November 15, 1996, the Court heard arguments concerning Princess’s negligence claim and GRANTED GE’s Motion for Summary Judgment as to that claim only, postponing arguments on all contractual claims until November 22, 1996. At the conclusion of the November 22, 1996, hearing, the Court DENIED GE’s Motion for Summary Judgment as to all other claims and DENIED Princess’s Motion for Partial Summary Judgment. This opinion will further explain the Court’s reasoning for these respective rulings.

I. Facts.

Princess’s cruise ship, the S.S. Sky Princess (the “Ship”) was scheduled for routine inspection services and repairs in December 1994, at Norfolk Shipbuilding & Dry-dock Corporation’s (“Norshipco”), facility in Portsmouth, Virginia. Princess requested that GE, the original manufacturer of the Ship’s main turbines, prepare an estimate for the inspection work to be performed. On July 13,1994, GE prepared a Rough Order of Magnitude (“ROM”) for the scheduled inspection and services. The parties agree that the ROM was not a contract, but merely an estimate for informational purposes.

Around the end of September 1994, Richard Neary, GE’s Proposal Engineer, requested that Michael Stephen-McRae, Princess’s representative, provide some assurance that GE would be awarded the inspection contract. In response, Princess issued a purchase order which GE received on October 24, 1994. The purchase order included a proposed contract price of $260,000.00 and contained a brief description of the work to be performed. The reverse side of the purchase order contained a list of Princess’s terms and conditions. These terms and conditions indicated that the purchase order was *153 intended to be an offer and provided that: (1) the purchase order could be accepted through either acknowledgment or performance; (2) the terms and conditions could not be changed unilaterally; and (3) the Seller would provide a warranty of workmanlike quality and fitness for the use intended.

On October 24, 1994, the same day that GE received the purchase order, GE telefaxed a Fixed Price Quotation (“Quotation One”) to Princess. Quotation One provided a more detailed work description than the purchase order, a materials list, an offering price of $201,888.00, and GE’s own terms and conditions. Later that same day, GE reviewed Princess’s purchase order and discovered that it requested work not contemplated by GE when calculating the offering price in Quotation One. GE notified Princess of the same, and on October 28, 1994, telefaxed a Final Quotation (“Quotation Two”) to Princess, offering to provide all the requested services for $231,925.00, approximately $30,000.00 less than the offering price of Princess’s Purchase Order, but approximately $30,000.00 more than GE’s Quotation One. Attached to both Quotation One and Quotation Two was a copy of GE’s own terms and conditions. These terms and conditions purported to: (1) reject any terms and conditions set forth in a Customer’s purchase order; (2) reject any liquidated damages; (3) limit GE’s liability to the repair or replacement of any defective goods or damaged equipment resulting from defective service, exclusive of all written, oral, implied or statutory warranties; (4) limit GE’s liability on any claims to not more than the greater of either five thousand dollars ($5,000.00) or the contract price; and (5) disclaim any liability for consequential damages, loss profits or lost revenue.

Neither Princess nor GE ever indicated any written or verbal acceptance of the other party’s terms and conditions. On November 1, 1994, GE did send a letter to Princess acknowledging receipt of their purchase order and expressing GE’s intent to perform the services. However, the letter also restated GE’s $231,925.00 offering price from Quotation Two, and specified that GE’s terms and conditions, attached to the letter, were to govern the contract.

In December 1994, the Ship arrived at Norshipco’s facilities in Portsmouth, Virginia. While performing the inspection and repairs, GE noted surface rust on the rotor and recommended that it be taken ashore to Norshipco for fly ash blast cleaning and balancing. Allegedly, Norshipco unevenly and excessively removed good metal from the rotor during the fly ash blasting, and as a result the rotor was no longer properly balanced. GE allegedly reinstalled new balance weights matching original specification, rather than properly testing and balancing the rotor. Upon departing Norshipco on December 18, 1994, the Ship experienced excessive vibration, allegedly from the unbalanced rotor, and was forced to return to port on December 19, 1994. GE shipped the rotor to its facility in Richmond, Virginia for inspection, blast cleaning and balancing. The rotor was reinstalled and other services, intended to eliminate the vibration, were completed by December 28, 1994. Nevertheless, Princess was forced to cancel a ten-day Christmas cruise as a result of the delay.

Princess alleges that the Ship continued to experience problems as a result of GE’s failure to properly perform its obligations under the survey and service contract. Specifically, excessive vibration, high temperatures, and damage to the rotor shaft, bearings, and labyrinth, forced additional repairs and the cancellation of a ten-day Easter cruise.

II. Maritime Law and the Standard for Summary Judgment.

Maritime law governs any contract action which primarily makes reference to maritime services or transactions. Todd, Marine Enterprises, Inc. v. Carter Machinery Co., Inc., 898 F.Supp. 341, 343 (E.D.Va. 1995). Thus, all parties agree and the Court FINDS that maritime substantive law governs this ease.

Summary judgment under Rule 56 is appropriate only when the court, viewing the record as a whole and in the light most favorable to the nonmoving party, determines that there exists no genuine issue of material fact and that the moving party is *154 entitled to judgment as a matter of law. See, e.g., Celotex Corp. v. Catrett, 477 U.S. 317, 322-24, 106 S.Ct. 2548, 2552-53, 91 L.Ed.2d 265 (1986); Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248-50,106 S.Ct. 2505, 2510-11, 91 L.Ed.2d 202 (1986); Terry’s Floor Fashions, Inc. v. Burlington Indus., Inc., 763 F.2d 604, 610 (4th Cir.1985).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ruggerio v. Harleysville Preferred Insurance Co.
278 F. Supp. 3d 536 (D. Connecticut, 2017)
Aliki Foods, LLC v. Otter Valley Foods, Inc.
726 F. Supp. 2d 159 (D. Connecticut, 2010)
Alejandre v. Bull
153 P.3d 864 (Washington Supreme Court, 2007)
Maersk Line Ltd. v. Care
271 F. Supp. 2d 818 (E.D. Virginia, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
950 F. Supp. 151, 1997 A.M.C. 1168, 1996 U.S. Dist. LEXIS 19064, Counsel Stack Legal Research, https://law.counselstack.com/opinion/princess-cruises-inc-v-general-electric-co-vaed-1996.