Princes Point LLC v. Muss Development L.L.C.

138 A.D.3d 112, 24 N.Y.S.3d 292
CourtAppellate Division of the Supreme Court of the State of New York
DecidedFebruary 4, 2016
Docket601849/08 16045
StatusPublished
Cited by2 cases

This text of 138 A.D.3d 112 (Princes Point LLC v. Muss Development L.L.C.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Princes Point LLC v. Muss Development L.L.C., 138 A.D.3d 112, 24 N.Y.S.3d 292 (N.Y. Ct. App. 2016).

Opinion

OPINION OF THE COURT

Acosta, J.

The questions raised by this appeal are whether a prospective purchaser of real property anticipatorily breaches a contract of sale by commencing an action against the seller for rescission of the contract before the closing date, and whether, in the event of the buyer’s repudiation, the seller is required to *114 show that it was ready, willing, and able to complete the sale (by obtaining certain government approvals as a condition precedent to closing) in order to retain the deposit and certain other payments as liquidated damages. We hold that, because a rescission action unequivocally evinces the plaintiffs intent to disavow its contractual obligations, the commencement of such an action before the date of performance constitutes an anticipatory breach. As to the second question, we hold that the seller was not required to show that it was ready, willing, and able to complete the sale because the buyer’s anticipatory breach relieved it of further contractual obligations.

I. Facts

The Muss family acquired a 23-acre parcel of land in Staten Island known as Princes Point in the early 1970s. The family formed two limited partnerships to own the property: defendants Allied Princes Bay Co. and Allied Princes Bay Co. #2 (collectively, APB). Defendant Joshua Muss is the general partner of APB, and defendant Muss Development L.L.C. is the management company that oversaw various entities and development projects in which the Muss family holds an interest, including Princes Point.

In the 1980s, the New York State Department of Environmental Conservation (DEC) declared the property an inactive hazardous waste site. To obtain a delisting of the property as a hazardous waste site, APB, Joshua Muss, and Muss Development L.L.C. (collectively, defendants) conducted remediation work, which involved the construction of a revetment (a seawall designed to prevent erosion) along the entire shoreline of the property. The property was delisted in 2001, and defendants began to seek the government approvals necessary to develop the property (the development approvals).

In 2004, plaintiff entered into an agreement with APB to purchase the property for $35,910,000, making an initial down payment of $1,878,500. One of the conditions precedent to closing was defendants’ having delivered to plaintiff the development approvals (except for any waived by the relevant city agencies). The contract provided for a closing date 30 days after the date on which defendants provided notice to plaintiff that all development approvals had been obtained, “but in no event later than the Outside Closing Date,” which was defined as 18 months from the execution and delivery of the agreement by each of the parties. If, despite diligent efforts, defendants were unable to obtain all development approvals on or prior to *115 the outside closing date, either party could terminate the agreement upon 30 days’ notice. In the event of termination, plaintiff would receive a refund of the deposit (and “compaction payments”), 1 and the parties would be released from the majority of their obligations. As an alternative to terminating the contract, plaintiff had the option of waiving the development approvals and closing the sale with an abatement in the purchase price.

In 2005, after Hurricane Katrina, the DEC conducted a visual inspection of the revetment, discovered problems, and called for additional work to be done. Because of the resulting increase in time and cost needed to obtain the requisite development approvals, defendants advised plaintiff that they would exercise their right to terminate the contract and return the down payment unless plaintiff agreed to amend the contract according to certain terms.

In March 2006, the parties amended their contract in writing to include the following terms: (1) extend the outside closing date to July 22, 2007 (the new outside closing date); (2) increase the purchase price to $37,910,000; (3) increase the down payment to $3,995,500; (4) require plaintiff to reimburse defendants for 50% of the costs related to completing the revetment work and obtaining the development approvals; and (5) require plaintiff to forbear from commencing “any legal action” against defendants in the event that the development approvals were not issued or the revetment work was not completed by the new outside closing date (the forbearance provision).

Facing additional problems with the revetment, the parties extended the new outside closing date on a month-to-month basis, because defendants, as stated in a May 2008 email, believed they were “on track” to receive the few remaining government approvals. The final date to which the new outside closing date was extended was July 22, 2008 (the final outside closing date).

Despite the contract’s forbearance provision, plaintiff commenced the instant action on June 20, 2008 — prior to the final outside closing date — claiming that it had been defrauded into entering into the contract and the 2006 amendment by defendants’ alleged misrepresentation that the revetment had been *116 built in accordance with the DEC’S specifications. In effect, plaintiff sought rescission of the 2006 amendment and specific performance of the 2004 contract (with an abatement in the purchase price to account for defendants’ failure to acquire the development approvals).

All of plaintiff’s causes of action have since been dismissed (.see 94 AD3d 588, 588 [1st Dept 2012] [“(P)laintiff accepted all defects in the premises and was not relying on any assurances made by defendants as to the condition of the property”]; 110 AD3d 564 [1st Dept 2013]; 116 AD3d 574 [1st Dept 2014]). All that remained after the dismissal of plaintiff’s claims was the counterclaims of defendants, who moved for partial summary judgment (on their counterclaims to declare the contract terminated, to declare that plaintiff materially breached the contract, thereby entitling defendants to retain the down payment and compaction payments, and to award defendants attorneys’ fees and costs). The motion court granted the motion in its entirety, determining that the contract had expired and was terminated by its own terms, that plaintiff anticipatorily breached the contract by commencing this action, and that defendants were entitled to retain the down payment and compaction payments as liquidated damages, and referred the matter to a special referee to determine contractual attorneys’ fees and costs in favor of defendants. Plaintiff appeals.

II. Discussion

a. Whether Plaintiff Anticipatorily Breached the Contract by Commencing the Instant Action

An anticipatory breach, or repudiation, occurs when a party to a contract unequivocally communicates to its counterpart before performance is due, by a statement or voluntary affirmative act, that it will avoid performance of its contractual duties (see Norcon Power Partners v Niagara Mohawk Power Corp.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
138 A.D.3d 112, 24 N.Y.S.3d 292, Counsel Stack Legal Research, https://law.counselstack.com/opinion/princes-point-llc-v-muss-development-llc-nyappdiv-2016.