Priewe v. Fitzsimons & Connell Co.

94 N.W. 317, 117 Wis. 497, 1903 Wisc. LEXIS 298
CourtWisconsin Supreme Court
DecidedApril 17, 1903
StatusPublished
Cited by5 cases

This text of 94 N.W. 317 (Priewe v. Fitzsimons & Connell Co.) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Priewe v. Fitzsimons & Connell Co., 94 N.W. 317, 117 Wis. 497, 1903 Wisc. LEXIS 298 (Wis. 1903).

Opinion

Maeshall, J.

The evidence abundantly shows that respondents, or those whose rights they assumed authority to summarily vindicate by removing appellant’s dam across the drainage ditch in the bed of the lake, were benefited by the work of the Wisconsin State Land & Improvement Company which was condemned in the’ suit of Priewe against such company (103 Wis. 537, 79 N. W. 780), and were parties to such work by acquiescence, and, under the principles laid down in such case, were bound not to complain of such work as regards the effect thereof upon their property. As to them the company could have successfully claimed protection on principles of estoppel in pais. In making the second drainage, it adopted the old canal as a basis, in part, for the new work. ' It so incorporated the old excavation in the bed of the lake into the new one that the identity of the former was in a great measure lost. On that account, when this court 'came to construe the judgment against the company in the former litigation the first canal was not regarded as having an identity distinct from the second one. It was said, in deciding the appeal, that the effect of the judgment in favor of 'Mr. Priewe, as rendered in the circuit court, was that he was entitled to have the condition of Muskego Lake, as the same existed prior to the second drainage, restored; and, to that end, that he was entitled to have so much of the canal in the bed of the lake, or elsewhere, filled up, as would accomplish [508]*508that result. Tbe thought, evidently, in the mind of the circuit court in rendering the judgment, as understood and approved here, was not merely that the original condition of the old ditch should be in all respects restored by the improvement company, but that the former condition of the level of the lake should be restored; that the canal in the bed of the lake, as it then existed, should be so dealt with as to accomplish that result. In that litigation appellant established his legal right to have such former condition restored as against the improvement company. He is evidently entitled to an equitable remedy to secure protection against it in the enjoyment of that right. Since respondents were, by acquiescence, parties to the second drainage work, he has an equitable right, as against them, to a' restoration of the former lake level by the same meanj that he may justly use as to the improvement company. They cannot be successfully heard to complain of any mere physical change in the canal which does not in fact raise the level of the lake higher than it was before being disturbed by the second drainage. Plence, they were wrongdoers in destroying any part of appellant’s work merely because it was done within the boundaries of the old canal. Their position in that regard was not and is not superior in any respect to that of the improvement company from the standpoint of right in the abstract. Therefore, if appellant did no more in fact by way of filling up the canal than was necessary to restore the former level of the lake, or, in other words, if, had such filling not been disturbed by respondents, the level of the water of the lake would not have been lifted above where appellant, as a party not bound by the second drainage operations, was entitled to have the same, then respondents, in destroying his work, were wrongdoers in any view of the case. The position of the trial court, it appears, is in harmony with that view, so far as the course of the trial and the findings of fact furnish any indication of the theory [509]*509upon wbicb the judgment was rendered. The judgment, we assume, went wholly on the ground that appellant changed the canal in the bed of the lake so that, had it so remained, in the natural course of things the level of the lake would have been raised so as to submerge lands owned by respondents, or some of them, which were uncovered by the first' drainage.

Passing the matter above discussed, we are met by the claim on the part of appellant that the trial court decided as a matter of fact that the dam placed across the canal by appellant was no higher than was necessary to restore him to his former situation as regards the water of the lake, and that such decision entitled him to the relief prayed for or some effective protection against lawless interference with his operations by respondents. There is good ground, it seems, for that claim, looking at one phase of the case as the learned trial court decided the issues. The findings, however, appear to be in irreconcilable conflict. Findings 1 to 8 inclusive may well have been prepared for judicial approval upon the court’s suggestion that-the issues made by the pleadings were decided in respondents’ favor; while findings 9 to 18 seem to have been made in response to requests by counsel for appellant that the matters referred to therein should be passed upon by the court favorably to his client. In the first group of findings we find this language:

“If said filling was not removed ... it [the water of the lake] would overflow the lands of these defendants . which were drained by the drainage commissioners’ work.”
“If filling was permitted to remain in said channel, as placed there by the plaintiff and his assistants, ... it would have backed the water over and upon large tracts of valuable tillable land which was reclaimed to the defendant landowners by the drainage done by the commissioners.”

Respondents’ .counsel point to that language with great confidence as justifying their clients in summarily ridding [510]*510the canal of tbe obstructions placed therein by appellant. In the second group of findings we find this language:

“The lake cannot be restored to its natural condition, or the level at which it ordinarily stood after the first drainage, . . -. so as to give plaintiff the beneficial use thereof as provided by the former judgment, without a literal compliance, at great expense, with the judgment rendered in said former action, or the partial damming or filling up of the said drain [meaning the drain in question] near the southerly end of said lake bed, substantially as done by the plaintiff. This finding is based not only on such testimony as is in the case on the subject-matter of this finding, but on . . . personal view.”

It seems useless to endeavor to read out of that language by construction any other idea than that appellant’s operations resulted in placing a dam across the canal no higher than was reasonably necessary to give him the benefit of the judgment in his favor by restoring the lake level to where it was when disturbed by the improvement company’s excavations. Such idea being entrenched as a verity in the findings, if all the other findings were in harmony therewith there could be. but little doubt that appellant would, be entitled to the relief he sought in this litigation instead of being compelled,to go remediless from court and be mulcted in costs for having invoked the arm of equity to protect him in doing the very thing that equity had decreed, after expensive litigation, he was entitled to do.

Counsel for respondents suggested on the oral argument, and there is something of the same sort in their brief, that the court, in making the finding under consideration, had in view merely tire level of the water as adjudged to appellant in the former case, not the actual fact as to where the level of the water was after the first drainage, and that respondents were not parties to such litigation, hence were not bound thereby.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Krueger v. Allenergy Hixton, LLC
2018 WI App 60 (Court of Appeals of Wisconsin, 2018)
Borowski v. Weinhold (Weinhold)
347 B.R. 887 (E.D. Wisconsin, 2006)
Citizens Bank of Sheboygan v. Rose
208 N.W.2d 110 (Wisconsin Supreme Court, 1973)
Muir v. Kay
244 P. 901 (Utah Supreme Court, 1925)
Luckow v. Boettger
121 N.W. 649 (Wisconsin Supreme Court, 1909)

Cite This Page — Counsel Stack

Bluebook (online)
94 N.W. 317, 117 Wis. 497, 1903 Wisc. LEXIS 298, Counsel Stack Legal Research, https://law.counselstack.com/opinion/priewe-v-fitzsimons-connell-co-wis-1903.