Price v. Kearney Canal & Water Supply Co.

45 N.W. 252, 29 Neb. 33, 1890 Neb. LEXIS 195
CourtNebraska Supreme Court
DecidedMarch 11, 1890
StatusPublished

This text of 45 N.W. 252 (Price v. Kearney Canal & Water Supply Co.) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Price v. Kearney Canal & Water Supply Co., 45 N.W. 252, 29 Neb. 33, 1890 Neb. LEXIS 195 (Neb. 1890).

Opinion

*35 Cobb, Ch. J.

The plaintiff brought his action against the defendant, as a private corporation, under a contract dated September 5, 1882, for the eonstruction of the defendant’s canal according to the plat and survey of J. B. Buckley, engineer, made for the defendant, and the specifications thereto annexed, at and for the prices specified, to-wit: The east mile of section 1, and all of sections 2, 3, 4, 5, 6, 7, 8, and 9, at nine cents per cubic yard, the remainder of section 1 at fifteen cents per cubic yard. Eor every 100 feet haul, after the first 100 feet, one cent per cubic yard, which the defendant agreed to pay upon the conditions of its specifications.

The plaintiff alleges that the canal was laid out by the defendant, as shown by its plats and profiles, through the following lands in Buffalo county, to-wit: Sections 1 and 2, in township 8 north, range 18 west; also section 6, township 8 north, range 18 west; also, sections 31, 32, 33, 34, 35, and 36, township 9 north, range 16 west; also, sections 4 and 5, township 8 north, range 16 west; that the defendant, by its engineer, made several changes in the location and line of the canal, and in the size and manner of executing the work during'its construction, thereby increasing the width of the canal at the bottom, and the distance the dirt [earth] was to be moved; that by the contract the plaintiff agreed to construct the earthwork of that portion of the line between and including section station 13 and 831, as then platted and surveyed, in accordance with the plat and specifications, and in consideration thereof the defendant agreed to pay fifteen cents for every cubic yard of earth entering into the construction of the canal, including excavation and embankment and fill for the west 5,000 feet in length of section 1, and the sum" of nine cents per cubic yard of earth for the remaining length thereof, being the east mile of section 1, and all of sections 2, 3, 4, 5, 6, 7, 8 and *36 9, excluding the work necessary to carry the water over and across certain ravines in the flumes.

That in pursuance of the contract the plaintiff on September 10, 1882, commenced the construction of the canal under the directions of the defendant and its engineer and completed the whole, according to contract and the direction of defendant, on May 1, 1884; that on the west 5.000 feet there were excavated 18,000 cubic yards of earth, and 9,000 cubic yards of earth were placed in the embankments of the same portion; that on the remaining portion, the east mile of section 1, and all of sections 2, 3', 4, 5, 6, 7, 8, and 9, he excavated 240,000 cubic yards, and placed 100.000 cubic yards in the embankments thereon, under the direction of the defendant, and accepted by it, exclusive of the extra work to be mentioned; that there is due plaintiff on said work, within the terms of the contract, exclusive of extra work done by direction of the defendant, $24,340.

II. That by the terms of the contract the first mile of the canal was to have been 30 feet wide at the bottom and no more, but afterwards the defendant required it to be constructed 31 feet wide at the bottom, which was done, and the defendant was informed of the extra work, performed on that account, and was charged therefor accordingly the sum of $500, no part of which has been paid.

III. That by the terms of the contract the plaintiff was to construct all embankments of the canal at and next to the excavations thereof, and that work was so performed, but subsequently during the construction thereof the defendant, disregarding the contract, directed the embankments to be constructed'with a shelf or berme bank, on each side, of six feet, and the embankments were so altered, removed, and constructed, which the defendant was informed was extra work, performed on that account, involving the removal of 258,000 cubic yards of earth, at three cents per yard, and was charged therefor accordingly the *37 sum of $7,740, and which the defendant agreed to pay a reasonable sum therefor.

IY. That by the terms of the contract, at a certain point on the line of the canal, at station —, the line was to be constructed around the side of a large sand hill with such excavation and embankments as to render the work convenient and easy, and through such earth and material as could be easily removed, which line was subsequently abandoned and a new one laid 'out, to be constructed by a heavy cut through the sand hill and through earth and material more laborious and expensive to move than that of the original line contracted for, which change was a departure from and a violation of the contract, and was so constructed by the order of defendant, involving an excavation of 4,000 cubic yards of earth, at thirty-five cents per yard, and was charged therefor accordingly, as extra work, at the sum of $1,400, and which the defendant agreed to pay a reasonable sum therefor.

Y. That by the terms of the contract there were certain road crossings to be made for the convenient crossing of the canal, and a certain excavation and fill to be made at a point where the Union Pacific railroad crosses the line of the canal, at which crossings and point, to be made, excavated, and filled, the defendant, at the time of construction, refused and neglected to specify, lay out, and plat, and to stake out and cross-section the work so required to be constructed, until after the plaintiff had finished that portion of the canal, and had moved his teams and laborers to other portions of the work at a considerable distance therefrom ; that subsequently the defendant demanded the completion of the work, which was done at an extra expense to the plaintiff than it would have cost at the time of constructing the work at such points, involving an excavation of 4,000 cubic yards of earth, and the moving of teams, at twenty cents per yard, and was extra work performed on that account and charged accordingly at the sum of $800, and has not been paid for.

*38 VI. That by the terms of the contract and the profile of the canal, by which the plaintiff entered upon the contract, that portion between stations 705 and 708-2 was through a deep run or draw in the surface of the land, through which the defendant intended to construct a flume for the canal, and was no part of plaintiff’s contract, and with which plaintiff had nothing to do either in construction or otherwise, but subsequently, at the request of defendant, he filled said run and draw, and constructed the canal across the same, involving a fill of 7,000 cubic yards of earth in embankment at twenty-five cents per yard, and was extra work, performed on that account, and charged accordingly at the sum of $1,750, which was accepted by defendant, and a reasonable sum agreed to be paid therefor, no part of which has been paid.

VII.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
45 N.W. 252, 29 Neb. 33, 1890 Neb. LEXIS 195, Counsel Stack Legal Research, https://law.counselstack.com/opinion/price-v-kearney-canal-water-supply-co-neb-1890.