Price v. Burke

145 N.W. 405, 27 N.D. 65, 1914 N.D. LEXIS 24
CourtNorth Dakota Supreme Court
DecidedJanuary 20, 1914
StatusPublished

This text of 145 N.W. 405 (Price v. Burke) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Price v. Burke, 145 N.W. 405, 27 N.D. 65, 1914 N.D. LEXIS 24 (N.D. 1914).

Opinion

Goss, J.

The decision of this case involves little more than a review of fact only. It is an equitable action brought to establish a right to recovery for alleged improvements to realty by foreclosure of a mechanics’ lien. The improvement was a deep' well alleged as drilled under contract between the well digger, Price, and Burke, the owner of the land.

Some facts are uncontroverted, but as to the greater portion a square conflict exists in the evidence. The well was drilled by the plaintiff to a depth of 401 feet, for which he has filed his lien for $601.50, or at the alleged agreed rate of $1.50 a foot. The well drilling was done after an interview plaintiff had with defendant in Yelva, on June 3, 1907. What was there said is in direct conflict, plaintiff claiming that Burke then gave him authority to see Myatt, Burke’s tenant on the land, and that whatever Myatt authorized done would be all right, and that he had to have a well. Plaintiff testifies he then told Burke that his price was $1.50 a foot, everything furnished, and that Burke told him he wanted everything furnished as he was to be away at Willeston or Montana for a considerable time, and could not look after it himself, and in effect authorized Price to deal with the tenant Myatt. All parties agree that a conversation occurred between Price and Burke at said place and date, that Sunday afternoon, as they were coming from a ball game. Burke denies plaintiff’s statement of the conversation, and testifies that he was accosted by plaintiff, who told him his business, and “said that he understood I had trouble getting water enough at my farm, and I told him I had. lie said he was a well driller and wanted to know if he could make a well for me, and I told him no, I had already made arrangements to fix the well I had on the place.” That he [68]*68had no further conversation whatever with Price; that he did not refer Price to Myatt; that “I did not speak to him more than two seconds; I told him that I had already told Myatt what to do with the well, fix up the old well.” That nothing was said in regard to the price of digging wells nor about a pump for the well. Burke testifies that the only authority in the matter he had given to Myatt was to dig down deeper a well already upon the place; that such well already there had been- in use for five years and had always before furnished plenty of -water for farm use; that he had never authorized the drilling of a well or anything more than the mere digging out of the old one; that this moment’s talk was the only conversation he says he had with Price until after the .completion of the well. Concerning the Velva incident, Burke is corroborated by Joe Strong, who, when asked to state what he recollected of the conversation, says: “Well, there "was not much conversation; Price asked him in regard to digging a well, and Burke said he had made arrangements with Myatt out there to dig down the well. It only lasted, about a minute or half a minute. That was all that was said. There was nothing talked about the price of drilling a well or anything of that kind. They did not' talk together after that. Burke walked down town (from the place where the talk occurred) with me and Flatner; we all walked down together.” On cross-examination he testified: “Burke said he had made arrangements with Myatt to look after the well;” which statement was explained on redirect examination to mean the well he was going to have “dug down or dug out.” Price had been looking for work and had previously asked Myatt for the job of drilling a well, and Myatt had referred him to Burke.

Price says he started in at drilling the well after he had procured from Myatt consent to do the work, he informing Myatt of the price he would charge. The work was begun on the 19th, 20th, or 21st of June, according to plaintiff’s testimony, he being uncertain as to the exact date, and he testifies the well was completed some time from the 11th to the 16th of July, being uncertain as to that date also, which date is very material, as will hereafter appear. The bill attached to the verified lien claim recites the commencement of the work on June 19th, and its completion July 11, 1907, and that the same was done under a contract made by plaintiff with the defendant on June 17th, or as would appear, two days before the work was commenced. The date of the veri[69]*69fication of this lien, filed September 3, 1907, is August 29, 1907. This was after the presentation to Burke of a bill for the work, which bill is dated July 23d, and is in evidence as Exhibit A, and is stamped received by Burke July 26, 1907, and answered by him July 27, 1907. It thus appears that the mechanics’ lien was prepared within a day after the receipt of the answer to the presentation of the claim, evidently adverse to payment, or the lien would not have been filed forthwith.

Burke appeared at his farm again July 12th, or nearly six weeks after the talk had with Price in Yelva, Burke making the trip to his farm with an automobile from Sawyer, and then discovered, as he says for the first time, the well in question, and that the same was already completed. That Price was away; that one Newman was there with the well-drilling outfit; that he started to tálk with Newman; that he was sore about them being there, and Newman told him he had nothing to do with it or with the outfit; that it used to belong to him, but Price had the job; that he asked him where Price was and was told he had gone to Sawyer; that he then found Myatt and wanted to know what they were doing and what authority Myatt had for doing that, and he was then told by Myatt that Price had informed Myatt that he, Price, had seen Burke in Yelva and had made arrangements with him, Burke, and that he, Myatt, considered he had nothing to do with it, and was sore because Burke blamed him for it. At that time they had pumped the well and had made ditches to drain off the water, and the water so pumped had splashed all over. Burke was positive that this was on the 12th day of July, fixing the date from memoranda and his whereabouts and other events; that he was then told by Newman in charge of the outfit, “they were down 401 feet and the water supply was sufficient,” and that they had pumped it four days in testing it. Myatt did not testify, the inference from the testimony being that he had left the country. Burke traced his own whereabouts from the 3d day of June until the 12th of July. It appears that he was in Bismarck June 4th and obtained a pardon for one Alice Hale, leaving Bismarck for Detroit, Minnesota, where he attended a wedding June 5th, leaving there for Eargo and Minneapolis, returning to Minot June 9th, then going to Towner, and on June 12th to Berthold, on the 13th to Williston, and on the 14th to Poplar, Montana, returning to Minot June 18th, and going back to Williston on the 19th, then engaging from June 20th un[70]*70til July 6th in the trial of the Heddrick will case, in which trial he was one of counsel. engaged. Witness then returned from Williston, went to Towner, Minot, and Velva, and from there to the farm. Witness testifies from memoranda consisting of sleeping car checks and checks drawn by him, to fix dates, refreshing his recollection, and from which witness is able to fix positively the date of his only visit to the farm as of the 12th of July, 1907. The importance of fixing the date of this visit with reference to the time of completion of this well is the question decisive of this case. If the well was completed in advance of the visit, then all the work was done before Burke had any notice that plaintiff was drilling the well. Such was Burke’s contention, and the one evidently accepted as the fact by the trial court.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
145 N.W. 405, 27 N.D. 65, 1914 N.D. LEXIS 24, Counsel Stack Legal Research, https://law.counselstack.com/opinion/price-v-burke-nd-1914.