Prewett v. Van Pelt

235 P. 1059, 118 Kan. 571, 1925 Kan. LEXIS 240
CourtSupreme Court of Kansas
DecidedMay 9, 1925
DocketNo. 26,141
StatusPublished
Cited by10 cases

This text of 235 P. 1059 (Prewett v. Van Pelt) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Prewett v. Van Pelt, 235 P. 1059, 118 Kan. 571, 1925 Kan. LEXIS 240 (kan 1925).

Opinion

The opinion of the court was delivered by

Harvey, J.:

This is a suit for the specific performance of a contract to purchase an oil" and gas lease, and for an accounting. The petition upon which the case was first tried contained three causes of action. The first set up plaintiff’s contract for the purchase of a six-eighths interest in an oil and gas lease and the performance of plaintiff’s part of the agreement, but that the vendors had sold the entire lease to J. B. Kirk, who purchased with knowledge of plaintiff’s contract and interest, and plaintiff prayed that the terms of his contract of purchase should be specifically performed. The second set out that J. B. Kirk had gone into possession of the premises, claiming to be the sole owner of it, and plaintiff prayed that he be put into possession. The third averred that Kirk had gone into possession of the premises and drilled a well and obtained a producing gas well therepn, and converted the gas to his own use, and prayed for an accounting of the gas produced from the well. Kirk’s answer admitted that he had drilled a well, but averred he had purchased the lease, was entitled to possession and the products in the well, to the exclusion of plaintiff. Upon a trial, judgment was rendered for defendant. Upon an appeal to this court the judgment of the court below was reversed (114 Kan. 833, 220 Pac. 1045). Thereafter plaintiff filed a supplemental petition alleging that after the defendant Kirk went into possession of the premises and drilled a well thereon, the defendant, the J. B. Kirk Gas and Smelting Company, constructed a pipe line to the premises and attached the same to the well and took all the available gas therefrom and distributed the same through its pipe lines, and sold the gas to the Lehigh Portland Cement Company and the city of Iola. These parties were all made defendants, and plaintiff prayed judgment against the defendant Kirk and each of the three corporation defendants “for the value of the gas received by said defendants and belonging to the plain[573]*573tiff.” Kirk filed a supplemental answer in which he averred that he had drilled a well upon the premises at an actual cost of $1,790.85; that the well had a capacity and produced gas amounting to a total of 399,003,994 cubic feet; that the market for gas was to the extent of only two per cent of that produced at 15 cents per thousand, and that the fair market value of plaintiff’s interest in the lease was at no time worth in excess of $897.75, and he prayed for the difference between that and the cost of drilling the well, $893.10, and for general relief. The J. B. Kirk Gas and Smelting Company filed an answer to the supplemental petition and referred to and adopted the answer of J. B. Kirk. The city, of Iola and the Lehigh Portland Cement Company filed answer denying liability, claiming that they had bought without notice of plaintiff’s claim.

Upon the trial, the court made findings of fact and conclusions of law as follows:

“Findings op Fact.
“(Unless otherwise specified, the term ‘defendants’ used herein, means J. B. Kirk and The J. B. Kirk Gas and Smelting Company.)
“The defendants took from the well in controversy in this case 399,000,496 cubic feet of gas, of which the plaintiff is entitled to six-eighths of the seven-eighths, or 261,846,438 cubic feet. The reasonable market value of said gas was 15 cents per 1,000 cubic feet. The defendants paid persons other than the plaintiff who were interested in the gas coming from said well, 16 cents per 1,000 cubic feet. The installation of the well cost the defendant $1,750.00.
"After the’ well had been drilled in by the defendants a meter was placed thereon and a by-pass, that is to say, a pipe around the meter, was installed. No appreciable amount of gas, however, was taken by the defendants from said well that did not pass through the meter. If gas was allowed to flow through the meter and the by-pass at the same time, something more than forty per cent of such gas would escape through the by-pass and eventually find its way into the pipe lines of the defendant.
in.
“The defendants are engaged among other things, in marketing gas produced from the various wells through a pipe line system of its own, and the gas produced from the well in litigation was mingled with the gas produced from other wells and such mingled gas was sold in considerable quantities to the defendants, the City of Iola and The Lehigh Portland Cement Company, the amount received by each of said defendants being considerably in excess of the total amount produced from the well in question, and they have paid for the same.
[574]*574IV.
“The Kansas Natural furnished about the only general market there was at Colony for gas produced from wells in“the Colony field, of which the well in question constituted one. The Kansas Natural took only a small portion of the gas produced from the wells in the Colony field, -probably less than two per cent of their possible production.
“The pipe line system of the defendant was laid at a considerable cost, and it was because of the fact that they owned „this system that they were able to receive and market all of the gas from the well in question. The pipe line system was in operation prior to the drilling of this well.
“Conclusions.
“1. The defendants were not trespassers under § 21-2435, Revised Statutes, and the plaintiff is not entitled to judgment for treble the value of the gas taken.
“2. The plaintiff is not entitled to any judgment at this time against the defendant, The City of Iola or The Lehigh Portland Cement Company.
“3. The defendants are not entitled to have off-set against the value of the gas taken the cost or any part thereof of installing its pipe line system.
“4. There should be a judgment for specific conveyance and for the value of the gas taken, less $1,750 or $37,526.97.”

Judgment was rendered accordingly. Both the plaintiff and the defendants against whom judgment was rendered filed motions for a new trial and,both have appealed.

Plaintiff contends he should have had treble damages because of the trespass of Kirk in going upon this lot and drilling. (R. S. 21-2435.) This contention cannot be sustained. Neither the original petition nor the supplemental petition charged Kirk with being a trespasser, nor did plaintiff ask for triple damages. In fact, he alleged Kirk is owner of one-eighth interest in the lease and plaintiff owner of six-eighths. Being joint owners, as lessees of the lease, it was not only the right but the duty, both of plaintiff and of Kirk, to go upon the premises and drill. Kirk cannot be charged with being a trespasser for doing that which the lease required of the lessee. Plaintiff’s real complaint against Kirk was that Kirk claimed to be the sole owner. The simple question was one of ownership, of a part interest in the lease as between plaintiff and Kirk. After plaintiff’s ownership of an interest in the lease was established, the question then was, what sum should plaintiff recover for his share of the product of the well.

Plaintiff contends the court should have found the market price of the gas at the well to be sixteen cents per thousand cubic feet [575]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Krug v. Krug
618 P.2d 323 (Court of Appeals of Kansas, 1980)
Mobil Oil Corp. v. Kansas Corporation Commission
608 P.2d 1325 (Supreme Court of Kansas, 1980)
Thaxton v. Beard
201 S.E.2d 298 (West Virginia Supreme Court, 1973)
Columbian Fuel Corp. v. Panhandle Eastern Pipe Line Co.
271 P.2d 773 (Supreme Court of Kansas, 1954)
Carlock v. Krug
99 P.2d 858 (Supreme Court of Kansas, 1940)
Winters v. Bisaillon
54 P.2d 1169 (Oregon Supreme Court, 1936)
Turner v. George Rushton Baking Co.
32 P.2d 211 (Supreme Court of Kansas, 1934)
Grindley v. Woods
282 P. 573 (Supreme Court of Kansas, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
235 P. 1059, 118 Kan. 571, 1925 Kan. LEXIS 240, Counsel Stack Legal Research, https://law.counselstack.com/opinion/prewett-v-van-pelt-kan-1925.