Preuit v. Lail

1925 OK 538, 243 P. 927, 116 Okla. 184, 1925 Okla. LEXIS 369
CourtSupreme Court of Oklahoma
DecidedJune 23, 1925
Docket15164
StatusPublished
Cited by1 cases

This text of 1925 OK 538 (Preuit v. Lail) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Preuit v. Lail, 1925 OK 538, 243 P. 927, 116 Okla. 184, 1925 Okla. LEXIS 369 (Okla. 1925).

Opinion

Opinion by

RAY, O.

This suit was commenced by Luther Lail to foreclose a lien for labor performed and material furnished i n certain property of Frank N. Preuit, deceased, alleged to have been furnished under oval contract with the deceased. The defendant’s unverified answer included a general denial and a specific denial that the labor and material were furnished under a contract with the owner, and denied that the deceased ever undertook and agreed to pay for the labor and material. The only evidence offered 'by plaintiff was the lien statement which was filed in the office of "he court clerk on the 16th day of May, 1921. The demurrer to plaintiff’s evidence was overruled, as was Idefendant’s motion for a directed verdict.

The Question to be determined is, Was the lien statement sufficient evidence to make a prim i facie case? The lien statement con-tamed the recital that the claim was made for and on account of work and materials furnished between the dates of June 15, 3920, and March IT, 1921, according to an item! zed statement thereto attached and madi a part of the statement, and that such wort labor, and materials were furnished upon the building and .premises owned by Frank N. Preuit (described), and that the sum claimed was just, due, and unpaid. The den statement was verified by the affi-davii of the lien claimant.

Th! itemized statement attached to and made a part of the lien statement was as follows:

Amended Statement
40(4 eu. ft. of concrete footing_$ 36.20
Brick f irnished on fire wall of brick building located on the north 50 ft. the south 50 ft. of lot 2, block 82_,_ 283.00
Extra 4 inches < n fire wall_ 147.00'
Anchors in joist holes_ 28.00
Concrete footing under pilaster_ ' 9.00
Pilaster labor and material_ 28 80
Two downspouts_,_ 32.70
Plastering _ 72.00
Taking up concrete floor_ 110.63
Taking up and replacing floor_ 50.40
Removing old roof and placing new one on the N. 59 ft. of lot 1, block S2 _ 190.00
Plumbing for fountain in drug store building located in building on N. 50 ft. of lot 1, block 82_ 149.45
$1137.18
Credits

It is contended on the part of the plaintiff that the lien statement was admissible in evidence and of the same probative value as a verified account, and, not being denied under oath, was sufficient to make a prima facie case, while defendant contends that it did not furnish proof of the contract with the owner, or that the material and labor were furnished within four months next preceding the filing of the lien statement in the office of the court clerk, and, for these reasons, did not make a prima facie ca.se.

That the lien statement was admissible in evidence for the purpose of showing that the contractor had taken the necessary steps to preserve the lien claimed is not questioned by the plaintiff in error, but it is contended that the lien statement, being the ex parte affidavit of plaintiff, did not fur *185 nish proof of a contract with the owner. Assuming, as contended for the contractor, but not deciding, that the verification of the lein statement was suifieient under section 287, Comp. Stat.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pirtle v. Brown
1928 OK 589 (Supreme Court of Oklahoma, 1928)

Cite This Page — Counsel Stack

Bluebook (online)
1925 OK 538, 243 P. 927, 116 Okla. 184, 1925 Okla. LEXIS 369, Counsel Stack Legal Research, https://law.counselstack.com/opinion/preuit-v-lail-okla-1925.