Preski v. Warchol Construction Co.

444 N.E.2d 1105, 111 Ill. App. 3d 641, 67 Ill. Dec. 621, 1982 Ill. App. LEXIS 2632
CourtAppellate Court of Illinois
DecidedDecember 30, 1982
Docket81-2973
StatusPublished
Cited by12 cases

This text of 444 N.E.2d 1105 (Preski v. Warchol Construction Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Preski v. Warchol Construction Co., 444 N.E.2d 1105, 111 Ill. App. 3d 641, 67 Ill. Dec. 621, 1982 Ill. App. LEXIS 2632 (Ill. Ct. App. 1982).

Opinion

JUSTICE ROMITI

delivered the opinion of the court:

After the completion of a construction project, both contractor and subcontractor sued each other. The contractor sued for the cost of completion of work not performed by the subcontractor, and the subcontractor sued for certain sums unpaid and for extras. The trial court found that the subcontractor had breached the subcontract and also denied sub silentio the subcontractor’s claims. It also refused to grant the contractor the full amount sought, finding that certain claimed expenditures were unproven. Both sides have appealed. We affirm in part, reverse in part and remand for trial.

In 1973 Warchol (hereinafter called contractor) entered into a construction contract with the Capitol Development Board of the State of Illinois. Thereafter contractor entered into a subcontract with Plaza Excavating Contractors (hereinafter called subcontractor). The subcontract provided that for the sum of $113,500 the “subcontractor shall furnish and install the following described work in accordance with the contract between the Owner and the General Contractor and the Drawings and Specifications titled” followed by the typed provision:

“The DAVEA CENTER, ***, as per drawings T, L, Cl to C5, 1 to 23, PS-1, FS-1M, FS1-V, FS-1E, SI to S10, PI to P13, HI to H15, ME1 to ME3, LC1 to LC8, El to E12, SE1 to SE9 all dated 3/23/73 and specifications. Addendum #1 dated 4/2/73, Addendum #2 dated 4/11/73 and Addendum #3 dated 4/18/73 all as prepared by Daverman Associates, Inc., Architect and Engineers.
EARTHWORK complete, including grabbing, tree removal, demolition, stripping, cut and fill work, excavating, trenching, backfilling (within the building and exterior sidewalks with granular fill), 4” minimum sand under slab, grading, removal of spoil, construct access road (stone excluded), retention pond, accessories and auxiliary work.
Work to be done in accordance with job schedule requirements.
Site to be rough graded and trenching started within 3 weeks.
Furnish excavating equipment for ground breaking ceremony.
If Warchol Construction Company authorizes in writing the following alternate work, same to be included for their respective prices:
Alternate G-ll (spreading of top soil) ...............$19,800.00
Alternate G-6...................................................$l,675.00[sic]
Alternate G-7...................................................$ 1,900.00
Alternate G-8...................................................$ 375.00
EXCLUSIONS
NO SHEETING, SHORING OR PUMPING
NO HAND LABOR
NO FROST RIPPING
NO ENGINEERING OR LAYOUT WORK
NO SOILS TESTING”

The subcontractor completed much of the work and was paid $96,300. In 1974 the contractor demanded that the subcontractor spread the topsoil which had been removed and stored in a mound. The subcontractor claiming this fell within alternate G-ll of the specifications refused to do so unless paid $19,800. The contractor took subcontractor’s claimed interpretation of the specifications first to the architect and then to arbitration; both ruled that the placement of topsoil was part of the base bid and not part of alternate G-ll. Capitol and contractor were parties to these proceedings; subcontractor was not. However, the evidence indicates that the subcontractor did attend the arbitration hearing and testified there. Contractor acquiesced in the findings and demanded that subcontractor perform. Subcontractor refused to return to the job and other subcontractors were hired.

The trial court, after hearing all of the evidence, found that the subcontractor had been paid $96,300 of the $113,500 contract price, leaving $17,200 unpaid. Certain work could not be done by subcontractor for various reasons beyond its control; this included completion of cutting and grading a retention pool, the backfilling of certain curbs, and the furnishing and compacting of sand for various sidewalks. The amount which would have been paid for the work if done would have been $8,272. The evidence also showed that subcontractor failed to complete other work, but as to some of its work the amount spent by contractor to have the work completed by others was insufficiently shown. It was established that $1,534 was spent for debris and the removal and the cutting of a loading dock and $12,022.05 to complete the grading and spreading of the topsoil, which work the court agreed was not the fine grading falling under G-ll. The court awarded the contractor $4,628.05, the difference between the total amount of proved expenses incurred by the contractor and the total amount unpaid under the contract.

I

The subcontractor’s defense is based on the premise the the words “spreading of top soil” controls the rights of the parties. It is, however, improper to take words of a contract out of context or read only one provision alone. Rather a contract must be read as a whole and all parts construed together. (White v. White (1978), 62 Ill. App. 3d 375, 378 N.E.2d 1255.) Furthermore, in light of the specific adoption in the subcontract of the drawings and specifications provisions of the prime contract, those provisions become as much a part of the subcontract as if they were expressly written in it. (City of Lake View v. MacRitchie (1890), 134 Ill. 203, 25 N.E. 663; Intaglio Service Corp. v. J. L. Williams & Co. (1981), 95 Ill. App. 3d 708, 420 N.E.2d 634; Heifner v. Board of Education (1975), 32 Ill. App. 3d 83, 335 N.E.2d 600.) They cannot be ignored.

Grading is defined in the specifications which are a part of the contract. The one doing the grading was required to “redistribute the stockpiled topsoil and/or additional topsoil as required to the final contours shown on the plot plan at the direction of the Engineer.” This, as the architect correctly ruled, was precisely what was demanded here. Accordingly, the subcontractor was obligated by the clear language of the basic subcontract to spread the stockpiled topsoil, and when it did not do so it breached its contract.

The existence of the alternate G-ll in the contract does not change .this result. The first listed alternate does not read “spreading of top soil” but “G-ll (spreading of top soil).” The meaning of G-ll, just as G-6, G-7 and G-8, must be determined from the specifications.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

MTGLQ Investors, LP v. Lisauskiene
2021 IL App (1st) 190608-U (Appellate Court of Illinois, 2021)
Babcock v. Martinez
857 N.E.2d 911 (Appellate Court of Illinois, 2006)
P.R.S. International, Inc. v. Shred Pax Corp.
686 N.E.2d 1214 (Appellate Court of Illinois, 1997)
Raithel v. Dustcutter, Inc.
634 N.E.2d 1163 (Appellate Court of Illinois, 1994)
Ridgeview Construction Co. v. American National Bank & Trust Co.
563 N.E.2d 986 (Appellate Court of Illinois, 1990)
A.E. Staley Manufacturing Co. v. Robertson
558 N.E.2d 434 (Appellate Court of Illinois, 1990)
Mercantile Holdings, Inc. v. Keeshin
543 N.E.2d 1031 (Appellate Court of Illinois, 1989)
Turner Construction Co. v. Midwest Curtainwalls, Inc.
543 N.E.2d 249 (Appellate Court of Illinois, 1989)
McDonald's Corp. v. Mazur
469 N.E.2d 430 (Appellate Court of Illinois, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
444 N.E.2d 1105, 111 Ill. App. 3d 641, 67 Ill. Dec. 621, 1982 Ill. App. LEXIS 2632, Counsel Stack Legal Research, https://law.counselstack.com/opinion/preski-v-warchol-construction-co-illappct-1982.