Prescott & Sons Construction v. Rogers

CourtCourt of Appeals of South Carolina
DecidedJune 21, 2017
Docket2017-UP-247
StatusUnpublished

This text of Prescott & Sons Construction v. Rogers (Prescott & Sons Construction v. Rogers) is published on Counsel Stack Legal Research, covering Court of Appeals of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Prescott & Sons Construction v. Rogers, (S.C. Ct. App. 2017).

Opinion

THIS OPINION HAS NO PRECEDENTIAL VALUE. IT SHOULD NOT BE CITED OR RELIED ON AS PRECEDENT IN ANY PROCEEDING EXCEPT AS PROVIDED BY RULE 268(d)(2), SCACR.

THE STATE OF SOUTH CAROLINA In The Court of Appeals

Prescott & Sons Construction, LLC, Respondent,

v.

Larry Rogers and Michelle Rogers, Appellants.

Appellate Case No. 2015-001115

Appeal From Aiken County Doyet A. Early, III, Circuit Court Judge

Unpublished Opinion No. 2017-UP-247 Heard May 4, 2017 – Filed June 21, 2017

AFFIRMED

M. David Scott, of Jordan, Rauton & Scott, LLC, of Lexington, for Appellants.

Lir Patrick Derieg, of Columbia, for Respondent.

PER CURIAM: In this breach of contract case arising out of renovations to their home, Larry and Michelle Rogers (the Rogers) appeal from a jury verdict in favor of their builder, Prescott & Sons Construction, LLC (Builder). The Rogers assert the trial court erred in (1) denying their judgment notwithstanding the verdict (JNOV) motion, (2) denying them a new trial, (3) admitting into evidence certain emails sent to them by Builder because the emails were never provided in discovery, and (4) awarding Builder attorney's fees without making sufficient findings of fact. We affirm.

I.

In 2011, the Rogers approached Josh Prescott, owner of Builder, about additions to their home. In April 2012, the Rogers and Builder executed a contract in which the Rogers agreed to pay Builder's costs plus a 15% fee. The contract stated "Buyers desire that Builder construct an attached garage, sunroom, patio & basement pad on the Lot . . . ."

In May 2012, the parties agreed to a new contract, which recited that "Buyers desire that Builder construct a residence on the Lot . . . ." and "'Residence' shall include the construction of a single-family residence addition of approximately 2300 Square feet of total area as well as porches, deck, and garage . . . ." The contract provided the Rogers would pay all costs of the work, estimated to be $200,000, plus a builder's fee of $25,000, payable as $5,000 per month for five months. If, however, the project lasted less than five months, the remainder of the builder's fee was to be paid upon issuance of the Certificate of Occupancy. If the project exceeded five months, the builder's fee would be reduced to $2,500 per month.

The contract further provided the project cost was only an estimate and did not include costs resulting from "unknown conditions . . . including rock or dirt removal" and changes in scope. The contract also prohibited the Rogers from interfering with or negotiating with Builder's subcontractors.

Josh testified the scope of work of the new contract was "only to do the garage, the porch, do a little patio, and the sunroom." He stated the Rogers deleted the concrete basement pad from the scope of work, yet kept bringing construction of the basement up in conversation. Because adding a basement with several bedrooms and bathrooms would entail a massive excavation of the dirt and support from under the home, Josh advised the Rogers he could not give them a price until they hired an engineer to draw plans. Josh and the Rogers ultimately met with an engineer, who completed a blueprint for the basement construction.

On June 26, 2012, Josh called the landscaper, Jeremy Kelley, and asked him to stop by so they could review the blueprint and calculate a price for the basement work. Kelley happened to be en route to the Rogers' house. Upon arrival, he told Larry Rogers, "I hear we're back on the basement . . . . Josh has called me for me to go by his office and pick up the new plans." Larry responded that if Josh "didn't do the basement under the current contract he wouldn't be allowed back on the property." Kelley then testified:

I left [Larry] and went straight to Josh's office. Kind of an odd coincidence but immediately when I walked in Ashley [Josh's wife and office manager] handed me the plans and [Josh's] phone rang. It was Larry. He walked out on the porch. I stayed in with Ashley. And when he c[a]me back in I said something about the plan. He said, well, you can take th[ose] plans and do what you want with them. I just got fired.

Josh gave this version of the events:

Q: And what did Larry tell you in that phone call?

A: Basically if you think I'm paying you a dime more than what I already agreed to pay you, the $25,000 flat fee, don't come back to my property. You're fired. . . .

Q: What was your response?

A: I said, Larry, there's no way in the world, there's nobody on this earth that would remove all this support from under your house and dig all the dirt out and add you a basement for free. I said, there's no way. And I said, so you're firing me, fine, fire me, but I'm not doing that for free.

Josh claimed that as of June 26, 2012, the project was 50% complete. The framing was finished, the roofing was "99% done," and he had been paid two months of his fee, or $10,000. Josh also testified the Rogers tried to hire his subcontractors out from under him, and he had sent eight invoices to the Rogers that were not paid. On cross- examination, Josh was asked repeatedly what "proof" he had that he had actually sent the invoices to the Rogers and the Rogers had actually received them.

Phillip Padgett, the framing subcontractor, testified that, when he stopped work, the framing was complete except for punch-list items the city building inspector issued. Padgett said he would have remedied the punch-list at no cost, as Builder had paid him in full for the job. Padgett also stated that, during the project, the Rogers had contacted him directly about prices. The inspector, Brian Stephen Smith, explained the punch-list items and also testified Larry told him Josh was not allowed back on the property to finish the work.

During a break outside the jury's presence, Builder's counsel advised the trial court he was providing the Rogers' counsel with copies of emails that proved Builder had actually sent—and the Rogers had actually received—the unpaid invoices.

When Ashley Prescott testified, the Rogers objected to admission of the emails on the ground they were not produced during discovery. The trial court overruled the objection.

Michelle Rogers testified she and her husband had always contemplated a finished basement and denied they fired Builder. She testified they received the mechanic's lien itemizing the unpaid invoices on July 14, 2012, but did not remember seeing the invoices or receiving them by email.

Larry Rogers stated the basement was within the contracted scope of work. He claimed the contract allowed the work to continue "indefinitely," even if they added an entire wing to their home. He testified he had paid other contractors $36,193.14 to repair Builder's poor work and noted Builder refused his invitation to return to the job. He denied telling Kelley that Builder was not allowed back on the job.

During closing, Builder argued the Rogers breached the contract by (1) conditioning further payment on completion of the basement, which was outside the scope of work, (2) trying to hire Builder's subcontractors from underneath him, and (3) not paying the invoices. He requested damages of $15,000 for the unpaid balance of the builder's fee, and $5,086 for the unpaid invoices.

The Rogers claimed Builder abandoned the project and had given them permission to communicate with the subcontractors on several occasions. They sought damages of $36,193.14, the amount Larry testified he had paid to complete the work.

The jury found the Rogers breached the contract and awarded Builder $18,166.03 in actual damages.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Curcio Ex Rel. Estate of Turner v. Caterpillar, Inc.
585 S.E.2d 272 (Supreme Court of South Carolina, 2003)
Vinson v. Hartley
477 S.E.2d 715 (Court of Appeals of South Carolina, 1996)
Blumberg v. Nealco, Inc.
427 S.E.2d 659 (Supreme Court of South Carolina, 1993)
Jamison v. Ford Motor Co.
644 S.E.2d 755 (Court of Appeals of South Carolina, 2007)
Noisette v. Ismail
403 S.E.2d 122 (Supreme Court of South Carolina, 1991)
Jumper v. Hawkins
558 S.E.2d 911 (Court of Appeals of South Carolina, 2001)
Conner v. City of Forest Acres
611 S.E.2d 905 (Supreme Court of South Carolina, 2005)
Champion v. Whaley
311 S.E.2d 404 (Court of Appeals of South Carolina, 1984)
Baron Data Systems, Inc. v. Loter
377 S.E.2d 296 (Supreme Court of South Carolina, 1989)
Bensch v. Davidson
580 S.E.2d 128 (Supreme Court of South Carolina, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
Prescott & Sons Construction v. Rogers, Counsel Stack Legal Research, https://law.counselstack.com/opinion/prescott-sons-construction-v-rogers-scctapp-2017.