Premium Valve Services, LLC v. Comstock Oil & Gas, LP, Comstock Oil & Gas-Louisiana, LLC and Certain Underwriters

Court of Appeals of Texas·Decided August 11, 2016·No. 01-15-00108-CV·Published

Opinion

Opinion issued August 11, 2016

In The

Court of Appeals

For The

First District of Texas

by failing to apply the proper measure of damages. We reverse and remand for a new trial.

Background

Appellees are the owners of the Collins #1 oil well located in Louisiana. PVS, which supplies rental equipment for the oil and gas industry, provided a frack stack1 that was used on the Collins #1 well. During fracking operations on the Collins #1 well, the flow cross on the rented frack stack supplied by PVS failed, causing the frack stack to explode. The well was immediately shut down.

Appellees later sued PVS for negligence and products liability.2 In their pleading, appellees alleged that the Collins #1 well was damaged as a result of the blowout caused by PVS and that the “physical damage to the well included, but was not limited to, the well-bore being filled with formation materials (that eventually caused the well to have to be abandoned and re-drilled despite [appellees’] attempts to save the well) and damage to other property at the well site.” PVS generally denied appellees’ claims and alleged, among other things, that most of the damage to the well was caused by appellees’ negligent remedial efforts,

1 A “frack stack” is a piece of well head equipment used during completion and well stimulation operations to pump fluids and proppants into the well and to flowback materials from the well. Frack stacks consist of numerous component parts, including a flow cross and various valves for controlling pressure.

2 The trial court granted summary judgment in PVS’s favor with regard to appellees’

other causes of action.

not the blowout. Specifically, PVS argued that the well could have been repaired after the blowout, but that appellees’ flawed remedial efforts caused a tool to be lodged in the well, and it was the inability to retrieve the tool that ultimately caused appellees to abandon the well.

At trial, appellees presented evidence that PVS negligently supplied them with a frack stack that contained a manufacturing defect, i.e., a pre-existing crack in the flow cross, and that the defective equipment was a producing cause of the blowout that caused permanent damage to the Collins #1 well. Witnesses testified that appellees attempted to restore and repair the Collins #1 well but those attempts proved unsuccessful. Appellees then abandoned the well and began drilling the Collins #2 well. The parties presented conflicting testimony regarding whether the Collins #2 well was a replacement well for the Collins #1 well.

The parties also presented conflicting testimony regarding whether the Collins #1 well was capable of being repaired after the blowout and the reasonableness of appellees’ remedial efforts. In particular, PVS’s expert testified that the blowout did not cause any downhole damage; it only damaged the well’s surface casing which appellees were able to completely repair. The expert further testified that the well had been cleaned out all the way to the last frack plug, and had been returned to the condition it was prior to the blowout when a tool being used in the remediation became stuck in the hole. According to PVS’s expert, the tool only became stuck in

the hole during the repair process because appellees did not follow their own remedial procedures and appellees were forced to abandon the well after they could not dislodge the tool. Appellees’ expert, on the other hand, testified that the blowout caused downhole damage to the Collins #1 well which required appellees to attempt to clean out and restore the well, and that appellees’ remedial efforts were both reasonable and necessary.

During the charge conference, PVS objected to the trial court’s failure to submit to the jury the following question: “Was the Collins No. 1 well damaged to such an extent as a result of the occurrence that it could not be reasonably repaired?” The trial court overruled the objection and refused to include appellees’ proposed question in the charge.

The jury found that PVS’s negligence proximately caused the blowout and that the equipment PVS had provided to appellees contained a manufacturing defect that was a producing cause of the blowout.3 In addition to these liability findings, the jury was also asked to determine what sum of money would fairly and reasonably compensate appellees for their damages that resulted from the blowout. The jury made the following three findings: (1) the difference in the market value of the Collins #1 well immediately before and immediately after the blowout was $7,562,000; (2) the reasonable and necessary cost to repair and restore the Collins

3 PVS is not challenging the jury’s liability findings on appeal.

#1 well was $5,138,000; and (3) the reasonable and necessary cost to re-drill and complete a well to replace the Collins #1 well was $0.

After the jury returned its verdict, appellees filed a Motion for Omitted Finding and for Entry of Judgment asking the court to make a finding as to whether the Collins #2 well was a replacement well for the Collins #1 well. The trial court granted the motion in its entirety and expressly found that the Collins #1 well “could not be reproduced.” The trial court awarded appellees damages in the amount of $12,700,000,4 plus pre-judgment interest, costs of court, and post-judgment interest.

Jury Charge

On appeal, PVS argues that damage to an oil and gas well is damage to real property, and therefore, the proper measure of damages in this case is dependent upon whether the damage to the Collins #1 well was temporary or permanent. See Gilbert Wheeler, Inc. v. Enbridge Pipelines (E. Tex.), L.P., 449 S.W.3d 474, 481– 82 (Tex. 2014) (setting forth general measure of damages in injury to real property cases and discussing distinction between temporary and permanent damages to real property). According to PVS, the trial court erred by failing to submit a question to the jury regarding the repairability of the well because the jury’s answer to that

4 The $12,700,000 award is the total value of the damages assessed by the jury: the difference in the market value of the Collins #1 well immediately before and immediately after the blowout ($7,562,000), plus the reasonable and necessary costs to repair and restore the well ($5,138,000).

question would have provided the court with a factual basis from which the court could have determined whether the injury to the well was temporary or permanent. Id. at 481 (holding that whether injury to real property is temporary or permanent is question of law for court and that disputed facts that underlie temporary-versus- permanent distinction must be resolved by factfinder). A. Standard of Review A properly requested jury question must be submitted if the question is on a controlling issue that is raised by the pleadings and supported by some evidence. TEX. R. CIV. P. 278; Union Pac. R.R. Co. v. Williams, 85 S.W.3d 162, 166 (Tex. 2002). A trial court may refuse to submit a jury question only if no evidence exists to warrant its submission, i.e., less than a scintilla. See Elbaor v. Smith, 845 S.W.2d 240, 243 (Tex. 1992). To rise above a scintilla, the evidence offered to prove a vital fact must do more than create a mere surmise or suspicion of its existence. See Kindred v. Con/Chem, Inc., 650 S.W.2d 61, 63 (Tex. 1983). The standard of review for an allegation of jury charge error is an abuse of discretion. Tex. Dep’t of Human Servs. v. E.B., 802 S.W.2d 647, 649 (Tex. 1990). A trial court abuses its discretion by acting arbitrarily, unreasonably, or without consideration of guiding principles. Walker v. Gutierrez, 111 S.W.3d 56, 62 (Tex. 2003).

Free access — add to your briefcase to read the full text and ask questions with AI

Premium Valve Services, LLC v. Comstock Oil & Gas, LP, Comstock Oil & Gas-Louisiana, LLC and Certain Underwriters, (Tex. Ct. App. 2016).

Premium Valve Services, LLC v. Comstock Oil & Gas, LP, Comstock Oil & Gas-Louisiana, LLC and Certain Underwriters (Premium Valve Services, LLC v. Comstock Oil & Gas, LP, Comstock Oil & Gas-Louisiana, LLC and Certain Underwriters) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Wagner & Brown, Ltd. v. Sheppard
282 S.W.3d 419 (Texas Supreme Court, 2008)
Columbia Rio Grande Healthcare, L.P. v. Hawley
284 S.W.3d 851 (Texas Supreme Court, 2009)
Texas Department of Human Services v. E.B.
802 S.W.2d 647 (Texas Supreme Court, 1990)
Kindred v. Con/Chem, Inc.
650 S.W.2d 61 (Texas Supreme Court, 1983)
Union Pacific Railroad v. Williams
85 S.W.3d 162 (Texas Supreme Court, 2002)
Wal-Mart Stores, Inc. v. Johnson
106 S.W.3d 718 (Texas Supreme Court, 2003)
Walker v. Gutierrez
111 S.W.3d 56 (Texas Supreme Court, 2003)
Cressman Tubular Products Corp. v. Kurt Wiseman Oil & Gas, Ltd.
322 S.W.3d 453 (Court of Appeals of Texas, 2010)
Elbaor v. Smith
845 S.W.2d 240 (Texas Supreme Court, 1993)
Exxon Corp. v. Perez
842 S.W.2d 629 (Texas Supreme Court, 1992)
Gilbert Wheeler, Inc. v. Enbridge Pipelines (East Texas), L.P.
449 S.W.3d 474 (Texas Supreme Court, 2014)