Premier Signature Renovations, LLC, et al. v. Loan Depot, Inc., et al.

CourtDistrict Court, S.D. Ohio
DecidedApril 22, 2026
Docket1:25-cv-00494
StatusUnknown

This text of Premier Signature Renovations, LLC, et al. v. Loan Depot, Inc., et al. (Premier Signature Renovations, LLC, et al. v. Loan Depot, Inc., et al.) is published on Counsel Stack Legal Research, covering District Court, S.D. Ohio primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Premier Signature Renovations, LLC, et al. v. Loan Depot, Inc., et al., (S.D. Ohio 2026).

Opinion

UNITED STATES DISTRICT COURT SOUTHERN DISTRICT OF OHIO WESTERN DIVISION

PREMIER SIGNATURE RENOVATIONS, LLC, et al.,

Plaintiffs, Case No. 1:25-cv-494

v. JUDGE DOUGLAS R. COLE

LOAN DEPOT, INC., et al.,

Defendants. OPINION AND ORDER Defendant Wright Patt Credit Union moves to dismiss Plaintiffs’ claims in this matter under Federal Rule of Civil Procedure 12(b)(6). For the reasons stated below, the Court GRANTS Wright Patt’s Motion to Dismiss (Doc. 24). BACKGROUND Plaintiffs Jason Kreusch and Premier Signature Renovations, LLC, filed their Complaint (Doc. 1) on July 16, 2025, and filed an Amended Complaint (Doc. 6) shortly thereafter. The dispute stems from a construction project that Plaintiffs—a contracting company and its owner, (see Doc. 6, #28, 31)—undertook on an investment property owned by certain of the Defendants, (id. at #28). Specifically, Defendants Karan Motiani and Mary Kathryn Lash (who are allegedly members of Defendant Molano Properties, LLC)1 hired Plaintiffs to “rehab” a residential investment property located at 1230 Myrtle Avenue, in Cincinnati, Ohio. (Id.).

1 The Court refers to Motiani, Lash, and Molano Properties, LLC, collectively as “Molano.” Plaintiffs entered into an agreement with Molano in late July 2019. (Id.). And on July 31, 2019, Molano closed on a construction loan from Defendant Loan Depot, Inc., to finance the project. (Id. at #28–29). It turns out, though, that this loan was

not in keeping with Plaintiffs’ expectations. Molano allegedly represented the loan to Plaintiffs as a so-called “homestyle loan.” (Id. at #29). In reality, Defendants, unbeknownst to Plaintiffs, took out a “203(k) loan,” which, Plaintiffs say, wrongfully “removed” them “from the function(s) associated with a general contractor, including control over job costs and the typical ‘draw’ process.” (Id.). Plaintiffs commenced work in August 2019, but did not receive any funds from Loan Depot until the end of September or early October. (Id.). And when that first

payment came through, it was $8,000 short. (Id.). Plaintiffs allege that this is because the “[t]hen inspector, Larry Davidson, falsely claimed … that the work was not complete, and that he could not sign off on it.” (Id.). But, according to Plaintiffs, Davidson himself “submitted photographs with evidence that the work had, in fact, been completed.” (Id.). The alleged “falsehood,” which “was perpetuated by all Defendants to Plaintiff[s’] detriment,” “pushed … Plaintiff[s] behind in receiving

further payments from the lender.” (Id.). But that’s not all. Once Plaintiffs started the job, they discovered that the project required extra work not contemplated by the parties’ original agreement. (Id.). This included, for example, “repair and replacement of joists,” “extra can-lights” that Molano ordered, and “other structural issues such as bathroom/kitchen floors, and the reframing of a new wall in the downstairs bathroom due to water damage.” (Id.). Plaintiffs asked Davidson, the inspector, to submit these extra items to the lender so that they could be paid for “out of the contingency fund,” but to no avail. (Id.). Davidson informed Plaintiffs that no money remained in that fund because “[Molano]

had to purchase a new furnace.” (Id.). That Molano was purchasing a new furnace for the property was news to Plaintiffs. (Id.). Indeed, when Plaintiffs submitted their proposal for the renovation work, they “included a price for a new HVAC system.” (Id.) But Molano asked Plaintiffs to remove that item because they intended to keep the HVAC system that was already installed at the property. (Id.). In any event, the new and unforeseen HVAC system installation required Plaintiffs to complete unanticipated work on the

property—namely, drywall and ceiling work to accommodate the new system’s ductwork and electrical requirements. (Id. at #30). Once the ducts and wiring were in place, a company called “Isabella Painters” replaced the drywall, and Plaintiffs painted the walls. (Id.). Plaintiffs allege that none of this was contemplated by the contract. Under the parties’ agreement, painting services were to be furnished by a “painting contractor,” not Plaintiffs. (Id.). Additionally, Plaintiffs say that Molano

failed to pay Isabella Painters, which led to the company filing a mechanic’s lien on the property and subsequent litigation (although that litigation has since ended). (Id.). Other issues arose in connection with the additional can-lights noted above, which Molano purchased despite the parties having already agreed to the submitted price for electrical contracting. (Id.). While the Amended Complaint’s allegations on this front are not a model of clarity, it appears that Molano somehow “pressured” Plaintiffs into paying the full amount of the electrical subcontractor’s bill after Plaintiffs already paid 60% of the total balance owed. (Id.). Additionally, the

electrician allegedly “illegally altered documents.” (Id.). Finally, the electrician (along with the HVAC contractor) allegedly failed an inspection, thus delaying Isabella Painters’ work for about a month. (Id.). Finally, a dispute regarding the project’s deadline cropped up as the project neared completion. Under the parties’ agreement, Plaintiffs had until January 31, 2020, to complete the work. (Id. at #31). Yet Molano insisted that Plaintiffs complete the job a month earlier, by December 31, 2019. (Id.). And when Plaintiffs responded

that they could not guarantee completion by that date, Molano “threatened Plaintiffs with fines and other consequences.” (Id.). Loan Depot then “put a halt to the project” until the parties resolved the issue. (Id.). As a result of the dispute, the work environment became “extremely hostile.” (Id.). Not long after, Molano had new contractors at the property, “thereby effectively terminating Plaintiff[s’] agreement, making contractual fulfillment an impossibility.” (Id.).

Looking to resolve the matter, Molano contacted Plaintiffs and told them that Molano had found an “arbitrator,” whom they represented as the “CEO of a construction company that does multimillion-dollar contracts.” (Id.). Based on that representation, Plaintiffs agreed to arbitrate their differences. But Plaintiffs later discovered that Molano’s “arbitrator,” Philip Lash, was not, in fact, the CEO of a construction company. (Id.). More importantly, Plaintiffs discovered that Lash is related to Defendant Lash, which, Plaintiffs say, gave rise to a “clear biased conflict of interest and misrepresentation.” (Id.). Although the Amended Complaint does not specify how, these events also led

to Plaintiff Kreusch’s arrest. (Id. at #35). He was charged criminally, but those charges were later dismissed pursuant to an agreement with the state. (Id.). As part of its investigation, the state apparently requested information about Plaintiffs from Defendant Wright Patt Credit Union, to which Plaintiffs belong. (See id. at #31–32). On Plaintiffs’ telling, Wright Patt’s compliance with that request (which appears to have taken the form of a grand jury subpoena2) “allowed or facilitated the wrongful dissemination of Plaintiff’s bank records for a governmental investigation without

Plaintiff’s knowledge, notice, ability to protest or object, and upon information and belief, without a subpoena or other legal process.” (Id. at #32). Based on these allegations, Plaintiffs assert five counts against all Defendants: (1) breach of contract, (2) fraud and conspiracy, (3) a count for punitive and statutory damages, (4) malicious prosecution/abuse of process, and (5) frivolous conduct. (Id. at #32–36).3

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Neitzke v. Williams
490 U.S. 319 (Supreme Court, 1989)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Kenneth C. Voyticky v. Village of Timberlake, Ohio
412 F.3d 669 (Sixth Circuit, 2005)
V & M STAR STEEL v. Centimark Corp.
678 F.3d 459 (Sixth Circuit, 2012)
Frank v. Dana Corp.
547 F.3d 564 (Sixth Circuit, 2008)
Hensley Manufacturing, Inc. v. Propride, Inc.
579 F.3d 603 (Sixth Circuit, 2009)
Gupta v. Terra Nitrogen Corp.
10 F. Supp. 2d 879 (N.D. Ohio, 1998)
The Keene Group, Inc. v. City of Cincinnati, Ohio
998 F.3d 306 (Sixth Circuit, 2021)
Hershey v. Edelman
932 N.E.2d 386 (Ohio Court of Appeals, 2010)
Bishop v. Grdina
485 N.E.2d 704 (Ohio Supreme Court, 1985)
Gaines v. Preterm-Cleveland, Inc.
514 N.E.2d 709 (Ohio Supreme Court, 1987)
Trussell v. General Motors Corp.
559 N.E.2d 732 (Ohio Supreme Court, 1990)
Yaklevich v. Kemp, Schaeffer & Rowe Co.
626 N.E.2d 115 (Ohio Supreme Court, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
Premier Signature Renovations, LLC, et al. v. Loan Depot, Inc., et al., Counsel Stack Legal Research, https://law.counselstack.com/opinion/premier-signature-renovations-llc-et-al-v-loan-depot-inc-et-al-ohsd-2026.