Premier Roofing Co., Inc. v. Ins. Co. of N.A., No. 31 24 38 (Nov. 22, 1996)

1996 Conn. Super. Ct. 9930
CourtConnecticut Superior Court
DecidedNovember 22, 1996
DocketNo. 31 24 38
StatusUnpublished

This text of 1996 Conn. Super. Ct. 9930 (Premier Roofing Co., Inc. v. Ins. Co. of N.A., No. 31 24 38 (Nov. 22, 1996)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Premier Roofing Co., Inc. v. Ins. Co. of N.A., No. 31 24 38 (Nov. 22, 1996), 1996 Conn. Super. Ct. 9930 (Colo. Ct. App. 1996).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]MEMORANDUM OF DECISION CT Page 9931 ON MOTION FOR ORDER COMPELLING ARBITRATION AND FOR STAY PENDING ARBITRATION # 143

The plaintiff, Premier Roofing Company, Inc. ("Premier"), commenced this action against Insurance Company of North America ("INA") by complaint dated January 6, 1993. In its revised amended complaint dated September 15, 1995, Premier alleges that INA breached its statutory duty as a surety pursuant to General Statutes § 49-42 and violated the Connecticut Unfair Trade Practices Act, General Statutes § 42-110a et seq., by failing to respond to Premier's claim in good faith.

This action arises out of a dispute between the parties regarding INA's obligation to pay Premier for work performed, pursuant to a construction contract. Premier entered into a subcontract with Saturn Construction Co., Inc. ("Saturn"), a general contractor with the state of Connecticut for a construction project known as the Western Connecticut Correctional Center located in Newtown, Connecticut. Under the subcontract, Premier agreed to perform certain roofing work on the project. Pursuant to the general contract, INA provided a labor and materials payment bond for the project, under which INA was surety, Saturn was principal, and the state was obligee.

During the course of the project, a dispute arose regarding Saturn's nonpayment to Premier for roofing work completed. On March 16, 1992, Premier brought a breach of contract claim in arbitration against Saturn. Subsequently, Premier commenced this civil action against Saturn and INA by complaint dated January 6, 1993, alleging the defendant's bad faith in responding to Premier's claim. On April 23, 1993, pursuant to the Premier-Saturn arbitration, Premier withdrew this case as against Saturn, leaving INA as the sole defendant in the civil action. Ultimately, on June 29, 1994, as a result of the arbitration between Premier and Saturn, Premier received an award in the amount of $292,500 plus interest and legal fees.

Premier has now moved for an order compelling arbitration and for stay of this action pending arbitration pursuant to General Statutes § 52-409. In support of its motion, Premier asserts that it has the right to invoke the arbitration clause contained in the general contract between Saturn and the state against INA in CT Page 9932 the following manner. The general contract between Saturn and the state includes an agreement to arbitrate "any dispute" arising out of performance of work under the contract. As discussed above, pursuant to the general contract, INA issued a labor and material bond under which Saturn is principal, the state is obligee, and INA is surety. The payment bond incorporates by reference the contract between Saturn and the state in its entirety, and gives any subcontractor who performs labor or services under the general contract and who is not paid for their services, the right to bring suit on the bond. Finally, according to Premier, the contract between Saturn and Premier contains a "flow through" clause which, Premier contends, gives Premier the same rights against Saturn and INA that Saturn and INA have against the state, including, specifically, the right to arbitrate any and all disputes. Under this scenario, therefore, Premier contends that INA is obligated to arbitrate this dispute with Premier.

In its opposition to Premier's motion for an order to compel arbitration and for stay pending arbitration, INA argues that: (1) Premier has admitted that no written agreement to arbitrate exists between Premier and INA as required by General Statutes § 52-409; (2) Premier's statutory claims, pursuant to General Statutes §§ 49-42 and 42-110g, are nonarbitrable and are subject to the exclusive jurisdiction of the Superior Court; and (3) Premier has waived any right to arbitration due to its three year pursuit of litigation without seeking to arbitrate its claim against INA. Because this court finds that Premier has waived any right to arbitration, this memorandum addresses solely the last of INA's arguments.

Both Premier and INA have litigated this action contentiously over the last three and a half years. Not only have the parties engaged in extensive and voluminous pleadings and motion practice, filing in excess of sixty pleadings, motions, and legal memoranda, but the parties have also attended numerous oral arguments before the court, engaged in substantial discovery, and pretried the case at least twice.

In particular, since its original complaint filed in January of 1993, Premier has defended INA's motion to strike and request to revise, filed an amended complaint on March 20, 1995, and a revised amended complaint on September 15, 1995, claimed this matter to the trial list on November 28, 1995, and attended pretrial conferences on January 24, 1996 and August 2, 1996. CT Page 9933 Premier, signalling its desire to proceed with litigation, has moved to exempt this case from dormancy on at least six occasions.1 On October 2, 1995, INA filed an answer including seven special defenses to which Premier replied.

In addition to participating fully in the pleadings and motion process, the parties have engaged in substantial discovery, including at least two sets of interrogatories and several document production requests and requests for admission. Furthermore, on at least three occasions INA has attempted to schedule depositions for January, February and May of 1996. Each of INA's attempts was met by Premier's motions to quash, causing INA to move to compel the taking of the depositions, an action which was vigorously contested by the Premier.

Ironically, Premier has further indicated an intent not to arbitrate when INA filed two motions, dated March 23, 1993 and June 27, 1994, requesting to stay the proceedings pending the arbitration between Premier and Saturn. In opposing these motions, Premier argued on each occasion that there was no written agreement to arbitrate between Premier and INA. In addition, although the Premier-Saturn arbitration involved issues arising from the same dispute and same series of contracts as the present litigation, Premier did not name INA as a respondent in that arbitration, and at no other time did Premier attempt to pursue arbitration against INA.

General Statutes § 52-409 provides in pertinent part: "If any action for legal or equitable relief or other proceeding is brought by any party to a written agreement to arbitrate, the court . . . upon being satisfied the any issue involved in the action or proceeding is referable to arbitration under the agreement, shall, on motion of any party to the arbitration agreement, stay the action. . . ." General Statutes § 52-409. A party's waiver of a right to arbitration is a consideration in determining whether an order staying the proceedings is warranted. See, e.g., Waterbury Teachers Association v.Waterbury, 164 Conn. 426, 434-35, 324 A.2d 267 (1975); Gilmartinv. Liberty Mutual Insurance Co., 23 Conn. Sup. 70 (1961).

"`[A]n arbitration clause [in a contract] may be waived by the parties or by the one entitled to its benefit.'" Advest, Inc.v. Wachtel, 235 Conn.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alan S. Kramer v. Gaines W. Hammond
943 F.2d 176 (Second Circuit, 1991)
Batter Building Materials Co. v. Kirschner
110 A.2d 464 (Supreme Court of Connecticut, 1954)
Gilmartin v. Liberty Mutual Insurance
176 A.2d 883 (Connecticut Superior Court, 1961)
Richter v. Danbury Radiological Assoc., No. 316199 (Apr. 17, 1995)
1995 Conn. Super. Ct. 4493-B (Connecticut Superior Court, 1995)
Waterbury Teachers Ass'n v. City of Waterbury
324 A.2d 267 (Supreme Court of Connecticut, 1973)
Advest, Inc. v. Wachtel
668 A.2d 367 (Supreme Court of Connecticut, 1995)
City of New Haven v. Local 884, Council 4, AFSCME
677 A.2d 1350 (Supreme Court of Connecticut, 1996)
Naftzger v. Naftzger & Kuhe, Inc.
602 A.2d 606 (Connecticut Appellate Court, 1992)
State v. Laws
655 A.2d 1131 (Connecticut Appellate Court, 1995)
Stevens v. Hartford Accident & Indemnity Co.
664 A.2d 826 (Connecticut Appellate Court, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
1996 Conn. Super. Ct. 9930, Counsel Stack Legal Research, https://law.counselstack.com/opinion/premier-roofing-co-inc-v-ins-co-of-na-no-31-24-38-nov-22-1996-connsuperct-1996.