Premier Land Development Company, LLC v. Bedrock Contracting, Inc.

CourtDistrict Court, W.D. Kentucky
DecidedSeptember 7, 2021
Docket3:20-cv-00149
StatusUnknown

This text of Premier Land Development Company, LLC v. Bedrock Contracting, Inc. (Premier Land Development Company, LLC v. Bedrock Contracting, Inc.) is published on Counsel Stack Legal Research, covering District Court, W.D. Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Premier Land Development Company, LLC v. Bedrock Contracting, Inc., (W.D. Ky. 2021).

Opinion

UNITED STATES DISTRICT COURT WESTERN DISTRICT OF KENTUCKY LOUISVILLE DIVISION PREMIER LAND DEVELOPMENT Plaintiff COMPANY, LLC Vv. Civil Action No. 3:20-cv-149-RGJ BEDROCK CONTRACTING, INC. Defendant OK OK OK OK MEMORANDUM OPINION AND ORDER Defendant Bedrock Contracting, Inc. (“Bedrock”) moves for partial summary judgment. [DE 29]. Briefing is complete and the matter is ripe. [DE 37; DE 42]. For the reasons below, Bedrock’s Motion for Partial Summary Judgment [DE 29] is GRANTED. 1. BACKGROUND In late 2016, Premier Land Development Company, LLC (“Premier”) contacted Bedrock, a demolition company, about “perform[ing] certain blasting work” at one of its property developments. [DE 29-1 at 146]. In December 2016, Bedrock sent Premier a quote (“First Quote”) for the blasting work. [DE 29-2 at 154]. After negotiations, resulting in Bedrock lowering the cost of the bid, Bedrock sent Premier a revised quote (“Second Quote”). /d. The Second Quote provided that: The scope of work for Bedrock Contracting, Inc. includes e Blasting for Sanitary Trench Rock e Labor, Equipment & Materials e Pre Blast & Seismograph Monitoring e Traffic Control, Blasting-Related Only The scope of work does NOT include: e Engineering e Any blasting within 10’ of existing utilities e Silt fence or temporary fence e Excavating or clearing

e Cleanup, Pavement Repair Cost Breakdown: Description Unit Lump Sum Price §29.75 Mobilization & Pre LS $10,575.00 Blast Surveys NOTES 1. There will be no back charges associated with this work. 2. Should either party employ an attorney to institute suit to enforce any of the provisions hereof, to protect its interest in any matter arising under this contract, or to collect damages for the breach of this contract, the prevailing party shall be entitled to recover damages for the breach of this contract, the prevailing party shall be entitled to recover reasonable attorney's fees, costs, charges and expenses incurred or expended therein. 3. Blasting shall be per current best common standards and practices, but Bedrock Contracting shall not be responsible for any over breakage due to laminations or any unusual geological conditions in rock formation. 4. All Trench Rock will be blasted to 2.0' plus O.D. pipe in this contract. 5. Any problems with rock breakage, elevations, or any other potential back charge shall be faxed to Bedrock Contracting at (859) 224-8533 and Bedrock Contracting given a reasonable time to remedy the problem. If any back charges are acceptable, they must be approved in writing on a daily basis by a responsible representative of Bedrock Contracting. 6. Payment for work done by Bedrock Contracting in a pay period shall be made within 5 days after end of time allowed for payment of any funds by owner to the prime contractor for that period, regardless of the amount of funds due the prime contractor. 7. Retainage to be paid first pay estimate after all excavation in rock is complete. Id. at 158-59 (emphasis added). According to Brian Lewis (“Lewis”), the estimator for Bedrock who prepared both quotes, “it is Bedrock’s business practice to send a written proposal to its potential clients. The proposal

serves to illustrate the scope of work, a breakdown of the cost, as well as the proposed terms and conditions.” Id. at 154. Premier alleges that the terms of its blasting agreement with Bedrock are contained not in the Second Quote but in an oral agreement reached between the parties at some unspecified point before Bedrock was hired. [DE 9 at 63 (“Plaintiff and Defendant had an oral agreement wherein

Defendant agreed to appropriately blast the underground rock for Plaintiff to be able to excavate the land for its Hidden Forest development”)]. On February 13, 2017, Bedrock began blasting. [DE 29-2 at 154]. When Bedrock finished blasting in March 2017, Premier paid it $97,053.52. [DE 37 at 215]. However, Premier was “unhapp[y]” with Bedrock’s “deficient” blasting work: 11. On or about April 10, 2017, Premier’s project manager, Will Hurst, met with a Bedrock foreman, Jerry (last name unknown), at the project site.

12. Jerry looked at the area in which Bedrock had blasted and admitted that Bedrock had drilled three (3) inch holes instead of the three and one-half (3 1/2) holes that were required to obtain the desired results.

13. Jerry also acknowledged that Bedrock had utilized “wetpack”: (ammonia nitrate) instead of dynamite.

14. On April 28, 2017, Will Hurst met with Bedrock representative Paul Wingo at jobsite to discuss Premier’s unhappiness with the work performed by Bedrock.

15. Mr. Wingo also acknowledged that the blasting work that had been performed was deficient, and he agreed that Bedrock would return to the project site and re- blast some of the areas to satisfy Premier.

16. Bedrock performed additional drilling and blasting in limited areas, it wholly failed to satisfactorily resolve the issue.

17. On or about May 10, 2017, I, along with Will Hurst, met with Paul Wingo at Premier’s office in Clarksville, Indiana. At the conclusion of the meeting, Mr. Wingo represented that Bedrock would address the issues Premier had with the work performed. 18. On or about June 7, 2017, I and Will Hurst against met with Paul Wingo. The meeting again concluded with Mr. Wingo offering the hollow assurance that Bedrock would work with Premier

19. Since the conclusion of this meeting, Mr. Wingo did not answer or not return any of Premier’s calls.

20. As a result of Bedrock’s continued failure to address the deficient work, Premier was forced to rent equipment and provide labor to hoe-ram the entirety of the underground rock in order to enable excavation and removal. to make the situation right.

[Aff. Jeff Corbett, DE 37-2 at 225-26].1

Bedrock did not charge Premier for the additional blasting. [DE 29-2 at 154]. Premier alleges that Bedrock’s promises on May 10, 2017 and June 7, 2017 that it would “remedy the situation” constitute two additional oral contracts. [DE 9 at 63-64]. Premier also alleges that Bedrock breached both of those oral contracts by failing to “appropriately address the situation.” Id. In February 2020, Premier sued Bedrock in this Court. [DE 1]. In April 2020, Premier filed an amended complaint. [DE 9]. Premier asserts three counts of breach of contract against Bedrock. Id. Bedrock answered and cross-claimed against Premier. [DE 12]. Bedrock now moves for partial summary judgment on Premier’s claims against it. [DE 29].

1 Fed. R. Civ. P. 56(c)(4) provides that “[a]n affidavit . . . used to . . . oppose a motion must be on personal knowledge, set out facts that would be admissible in evidence, and show that the affiant . . . is competent to testify on the matters stated.” The Court notes that, at best, only paragraphs 17 through 20 appear to satisfy this requirement. Along with the issue of whether the double-hearsay in paragraphs eleven through sixteen is admissible, it is unclear how Mr. Corbett has personal knowledge of conversations he did not participate in. See Brainard v. Am. Skandia Life Assur. Corp., 432 F.3d 655, 667 (6th Cir. 2005) (“All affidavits, regardless of the author, must be made on personal knowledge and set forth facts that would be admissible in evidence. Thus, to the extent that the Solum affidavit was not based on personal knowledge, the district court improperly considered it”) (internal citations omitted). II. STANDARD Summary judgment is required when “there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” Fed. R. Civ. P. 56(a).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Daugherty v. Sajar Plastics, Inc.
544 F.3d 696 (Sixth Circuit, 2008)
Huff Contracting v. Sark
12 S.W.3d 704 (Court of Appeals of Kentucky, 2000)
Victor's v. Monson
283 S.W.2d 175 (Court of Appeals of Kentucky (pre-1976), 1955)
Robert Shreve v. Franklin Cnty., Ohio
743 F.3d 126 (Sixth Circuit, 2014)
Kellum v. Browning's Administrator
21 S.W.2d 459 (Court of Appeals of Kentucky (pre-1976), 1929)
Grass v. Akins
368 S.W.3d 150 (Court of Appeals of Kentucky, 2012)
Energy Home, Division of Southern Energy Homes, Inc. v. Peay
406 S.W.3d 828 (Kentucky Supreme Court, 2013)
Williams v. International Paper Co.
227 F.3d 706 (Sixth Circuit, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
Premier Land Development Company, LLC v. Bedrock Contracting, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/premier-land-development-company-llc-v-bedrock-contracting-inc-kywd-2021.