Praxair, Inc. v. Public Service Commission

346 S.W.3d 377, 2011 Mo. App. LEXIS 999
CourtMissouri Court of Appeals
DecidedAugust 2, 2011
DocketWD 72119, WD 72120
StatusPublished
Cited by1 cases

This text of 346 S.W.3d 377 (Praxair, Inc. v. Public Service Commission) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Praxair, Inc. v. Public Service Commission, 346 S.W.3d 377, 2011 Mo. App. LEXIS 999 (Mo. Ct. App. 2011).

Opinion

JAMES M. SMART, JR., Judge.

The Appellants in this case sought judicial review in Cole County Circuit Court of the decision of the Public Service Commission authorizing a general rate increase for the Empire District Electric Company and also allowing the implementation of a “fuel adjustment clause,” pursuant to section 386.266.1, RSMo Cum.Supp.2009. The circuit court affirmed the Commission’s Report and Order, dated July 30, 2008. This appeal is brought pursuant to section 386.540, RSMo 2000.

The Appellants are the Office of Public Counsel (OPC) 1 and two industrial consumers of electric power, Praxair, Inc., and Explorer Pipeline Company (hereafter collectively, “the Industrials”). The Appellants do not challenge the decision of the Commission to .allow a general rate increase. Rather, the Appellants challenge the approval by the Commission of the fuel adjustment clause, contending it was prematurely considered. 2 Further, they object to the fact that the fuel adjustment clause allows the utility a 95% pass-through. They believe that a lower pass-through rate was supported in the evidence and that the higher level was not. The issues thus presented focus on the record evidence and the law relevant to the allowance of the fuel adjustment clause and the relative rate of pass-through.

*379 The OPC and the Industrials filed separate briefs. All Appellants contend, however, that the Commission was precluded from allowing Empire District Electric Company the benefit of a fuel adjustment clause in this case because of a binding stipulation preventing Empire District Electric Company from requesting a fuel adjustment clause during the time that an “interim energy charge” was in effect. 3 Further, the Industrials contend that section 386.266.8 precludes the Commission from prematurely terminating the previously allowed interim energy charge (“IEC”).

The OPC also contends that the Commission erred in allowing the fuel adjustment clause to include a “95% pass-through” because such authorization was not supported by adequate findings of fact on the whole record.

Standard of Review

This court reviews the decision of the Commission (not the ruling of the circuit court) to determine whether the Commission’s ruling is both lawful (within the statutory authority of the Commission) and reasonable (supported by substantial and competent evidence on the whole record). See State ex rel. Office of Pub. Counsel v. Pub. Serv. Comm’n, 289 S.W.3d 240, 246-47 (Mo.App.2009). This court’s determination of lawfulness is made de novo, without deference to the views of the Commission or the circuit court. See State ex rel. Aquila, Inc. v. Pub. Serv. Comm’n, 326 S.W.3d 20, 22 (Mo.App.2010). A Commission ruling is reasonable if it is supported by competent and substantial evidence on the whole record and is not arbitrary, capricious, or an abuse of discretion. Office of Pub. Counsel, 289 S.W.3d at 246. This court, in considering the factual record, does not substitute its judgment as to credibility determinations. Id. at 247.

The Commission’s task is to determine whether the rates and mechanisms proposed are just and reasonable. See section 393.150.2. In determining whether a Commission ruling related to rates is “just” and “reasonable,” we consider whether the evidence indicates that the decision is fair to both the company and its customers. State ex rel. Valley Sewage Co. v. Pub. Serv. Comm’n, 515 S.W.2d 845, 850 (Mo.App.1974). The ratemaking function involves the making of “pragmatic adjustments.” State ex rel. Assoc. Natural Gas Co. v. Pub. Serv. Comm’n, 706 S.W.2d 870, 873 (Mo.App.1985).

Factual Background

Empire District Electric Company (hereafter “Electric Company”) is an investor-owned public utility providing service to approximately 147,000 customers in southwest Missouri. Section 393.140(11), RSMo 2000, gives the Commission the authority to regulate the rates charged by public utilities. See also section 386.250(1). On October 1, 2007, Electric Company filed its tariff seeking a rate increase of $34.7 million per year. The Commission suspended the tariff until August 28, 2008. “The Industrials” were allowed to intervene in the case. After public hearings, the evidentiary hearing before the Commission was conducted in May 2008.

On July 30, 2008, the Commission issued its Report and Order granting a rate in *380 crease with a fuel adjustment clause. The OPC and the Industrials filed applications for rehearing, which were denied by the Commission. Thereafter, the Appellants filed their petitions for judicial review in Cole County Circuit Court. The circuit court affirmed the ruling of the Commission.

In its Report and Order, the Commission considered such matters as Electric Company’s capital structure and the need for a just and appropriate return on equity sufficient to attract and keep investors. The Commission considered the expert testimony presented by Electric Company and by the Industrials, and the expert testimony provided by its own staff. The Commission noted that, according to the record, Electric Company is a “riskier” investment than most utility companies. No party makes it a point to dispute that observation. Electric Company has a BBB-bond rating from Standard and Poor’s. The Commission considered the needs of Electric Company, an integrated utility, and the rates of return on equity allowed other integrated utilities. The Commission also considered, inter alia, that between 2002 and 2006, Empire’s shareholders absorbed $85.5 million in fuel and power costs that were not recoverable in rates. The Commission stated that there “really is no dispute that the implementation of a fuel adjustment clause will reduce the level of operating risk that Empire faces.”

The production of electrical power requires the purchase and consumption of the sources of electrical power, such as natural gas and coal. Because the regulatory process is slow to respond to volatility in fuel prices, the efficiency of electrical utilities can be hampered when there are no mechanisms that are utilized to more promptly respond to price fluctuations. In an earlier Electric Company rate case, the Commission had allowed Electric Company the benefit of a fuel and purchased-power expense recovery mechanism referred to as an “interim energy charge” or IEC.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
346 S.W.3d 377, 2011 Mo. App. LEXIS 999, Counsel Stack Legal Research, https://law.counselstack.com/opinion/praxair-inc-v-public-service-commission-moctapp-2011.