Prater v. Three-C Body Shop, Unpublished Decision (3-29-2002)

CourtOhio Court of Appeals
DecidedMarch 29, 2002
DocketNo. 01AP-950 (REGULAR CALENDAR).
StatusUnpublished

This text of Prater v. Three-C Body Shop, Unpublished Decision (3-29-2002) (Prater v. Three-C Body Shop, Unpublished Decision (3-29-2002)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Prater v. Three-C Body Shop, Unpublished Decision (3-29-2002), (Ohio Ct. App. 2002).

Opinion

OPINION
On March 13, 2000, John C. Prater filed a complaint in the Franklin County Court of Common Pleas against Three-C Body Shop, Inc. ("Three-C"). Mr. Prater's automobile had been involved in a collision, and he had brought the automobile to Three-C for repairs. Mr. Prater averred that Three-C had failed to properly perform the repairs. In essence, Mr. Prater's claims sounded in breach of contract and fraud.

The parties filed motions for summary judgment. On June 14, 2001, the trial court rendered a decision granting partial summary judgment in favor of Three-C. The trial court found that Three-C was entitled to summary judgment on the issue of whether or not Three-C was in breach of contract for failure to make the repairs in a timely manner. However, the trial court concluded that genuine issues of fact remained as to whether Three-C was in breach of contract for the repair work performed. Summary judgment in favor of Three-C was also granted on the claims for fraud, tortious "threat of arrest," overpayment and punitive damages.

The only remaining claim — breach of contract in regard to the repairs performed — was tried before a jury. On July 26, 2001, a final judgment entry was journalized indicating that the jury had returned a verdict in favor of Three-C.

Mr. Prater (hereinafter "appellant") has appealed to this court, assigning the following errors for our consideration:

1. The trial court entered Summary Judgment in favor of Defendant despite factual disputes as to whether the contract between Plaintiff and Defendant had been fully performed.

2. The trial court committed error by adopting [the] opinion in Three-C's affidavit relating to industry standard and accepting that opinion as fact in the case in the process of narrowing Appellant's right to proceed to trial and in ruling on Summary Judgment.

3. The trial court committed error in denying Appellant the right to proceed to trial on the issue of breach of contract as established in the complaint, answer, and subsequent pleadings in the case.

Appellant's assignments of error, in essence, take issue with the trial court's granting of summary judgment in favor of Three-C (hereinafter "appellee") on certain claims. Accordingly, appellant's assignments of error will be addressed together.

Summary judgment is appropriate when, construing the evidence most strongly in favor of the nonmoving party, (1) there is no genuine issue of material fact; (2) the moving party is entitled to judgment as a matter of law; and (3) reasonable minds can come to but one conclusion, that conclusion being adverse to the nonmoving party. Zivich v. Mentor Soccer Club, Inc. (1998), 82 Ohio St.3d 367, 369-370, citing Horton v. Harwick Chem. Corp. (1995), 73 Ohio St.3d 679, paragraph three of the syllabus. Our review of the appropriateness of summary judgment is de novo. See Andersen v. Highland House Co. (2001), 93 Ohio St.3d 547,548.

Appellant first contends that the trial court improperly took away appellant's right to have a trial on the issue of whether the contract was performed in full. Specifically, appellant asserts the trial court erroneously limited the trial to the issue of whether or not the repairs were performed in a "workmanlike" manner. Appellant contends he also had claimed that work contracted for had not been performed and that the automobile was returned in a faulty and unsafe condition. In essence, appellant argues that the essential purpose of the contract — to repair the automobile — was not performed and that this issue should have been submitted for trial.

The record before us indicates that the issue of whether the contract was breached for failure to properly perform the repairs was not dismissed by way of summary judgment and was, presumably, tried to the jury. Other than granting summary judgment on the issue of the timeliness of the repairs, the trial court did not otherwise limit any remaining issues regarding breach of contract. No transcript of the trial was included in the record and, thus, we cannot ascertain whether or not any issue was erroneously excluded for consideration by the jury. Again, the record before us indicates that the trial court did not limit the issues relating to appellee's performance under the contract (other than the timeliness issue). Hence, appellant's contentions in this regard are not well-taken.

Appellant next contends that summary judgment was inappropriate as to the issue of whether appellee breached the contract for failing to make the repairs in a timely fashion. Specifically, appellant asserts the trial court erroneously relied on an affidavit submitted by one of appellee's employees regarding the industry standard as to timeliness. Again, we review the appropriateness of summary judgment on this issue independently. Accordingly, we will look to all the evidence on the issue of timeliness in order to ascertain whether or not a genuine issue of fact existed sufficient to withstand summary judgment.

The evidence shows appellant was told that the repairs would take seven to ten days. (Prater affidavit; Prater deposition at 41-42.) However, appellant also signed a document entitled "THREE-C BODY SHOP, INC. AUTHORIZATION FOR REPAIRS" which stated in paragraph two:

Due to unforeseen circumstances beyond the control of Three-C, estimated completion and delivery dates are to be considered an approximate date of completion of the repairs authorized hereunder. Delivery dates are not guaranteed and Three-C is not responsible for vehicle rental costs incurred by you after the estimated completion date.

The automobile was delivered to appellee on August 16, 1999. Appellant did not get his automobile back until October 26, 1999, seventy-one days later. The evidence shows that there were several reasons for the delay including the fact that the manufacturer had problems meeting demands for factory parts on older model automobiles due to a prior strike. Appellee completed its repairs on September 30, 1999. However, appellant expressed dissatisfaction with various repairs, and the automobile was kept in order to fix these problems. (LaFuze affidavit; Prater deposition at 59-63; Prater affidavit.) On October 26, 1999, appellant went to the shop to retrieve his automobile. (Prater deposition at 79-82.)

This evidence, construed most strongly in favor of appellant, does raise a genuine issue of fact as to whether appellee made untimely repairs in breach of the contract. The trial court concluded, however, that appellee completed the repairs within a reasonable amount of time and based its decision on the affidavit of appellee's employee, Ben J. LaFuze. Mr. LaFuze, appellee's production manager during the pertinent time, stated that the industry average among body shops for repairs was one week of repair for every $1,000 in repair costs. The trial court concluded that because the original repair estimates totaled over $10,000, the repairs were performed timely as the industry standard would give appellee approximately seventy-one days to complete the repairs.

We find that the trial court erred in concluding appellee performed the repairs in a reasonable amount of time and in basing such conclusion on the industry standard as set forth by appellee's employee. At the summary judgment stage, Mr. LaFuze's opinion should not have been accepted as true and certainly should not have been the standard under which reasonableness was based.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Textron Financial Corp. v. Nationwide Mutual Insurance
684 N.E.2d 1261 (Ohio Court of Appeals, 1996)
Horton v. Harwick Chemical Corp.
73 Ohio St. 3d 679 (Ohio Supreme Court, 1995)
Zivich v. Mentor Soccer Club, Inc.
696 N.E.2d 201 (Ohio Supreme Court, 1998)
Andersen v. Highland House Co.
757 N.E.2d 329 (Ohio Supreme Court, 2001)
DeCastro v. Wellston City School District Board of Education
94 Ohio St. 3d 197 (Ohio Supreme Court, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
Prater v. Three-C Body Shop, Unpublished Decision (3-29-2002), Counsel Stack Legal Research, https://law.counselstack.com/opinion/prater-v-three-c-body-shop-unpublished-decision-3-29-2002-ohioctapp-2002.