Power Control Devices, Inc. v. Lerner

437 P.3d 66, 56 Kan. App. 2d 690
CourtCourt of Appeals of Kansas
DecidedJanuary 25, 2019
Docket117705
StatusPublished
Cited by1 cases

This text of 437 P.3d 66 (Power Control Devices, Inc. v. Lerner) is published on Counsel Stack Legal Research, covering Court of Appeals of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Power Control Devices, Inc. v. Lerner, 437 P.3d 66, 56 Kan. App. 2d 690 (kanctapp 2019).

Opinion

Arnold-Burger, J.:

In order to prevail in a claim of legal malpractice, "a plaintiff must establish the validity of the underlying claim by showing that it would have resulted in a favorable judgment in the underlying lawsuit had it not been for the attorney's error." Canaan v. Bartee , 276 Kan. 116 , 120, 72 P.3d 911 (2003). This is commonly referred to as proving the "case within a case." Here Power Control Devices (PCD) hired Michael "Mick" W. Lerner to represent it in a federal court breach of contract lawsuit against Orchid Technologies Engineering and Consulting (Orchid). The federal district court overseeing the case dismissed it, holding that PCD failed to bring the claim within the statute of limitations. PCD then sued Lerner for legal malpractice, alleging that he was negligent by filing the suit after the statute of limitations had passed. A jury agreed and awarded damages to PCD.

But following the verdict, the district court granted Lerner's motion for judgment as a matter of law, overturning the jury verdict in favor of PCD, on the basis that PCD failed to prove that it would have succeeded against Orchid at trial. In the alternative, the district court judge conditionally granted Lerner a new trial based on a separate instructional error-in case his judgment of no liability was overturned on appeal. However, the judge did not err when he ruled in favor of Lerner. The case between PCD and Orchid was highly technical, yet PCD failed to present any expert testimony to establish that it would have been successful against Orchid if its lawsuit against Orchid had been timely. Accordingly, we affirm the district court's decision granting judgment as a matter of law to Lerner.

FACTUAL AND PROCEDURAL HISTORY

Lerner is an attorney licensed to practice law in Kansas. PCD hired Lerner to represent it in a lawsuit against Orchid. Now, PCD is suing Lerner and The Lerner Law Firm for malpractice. In order to understand the malpractice suit, we begin by examining the underlying litigation.

PCD's case against Orchid is examined.

PCD manufactures electronic devices. Its primary product is servo amplifiers, which are used to drive motors in products such as radar systems, cameras, surveillance systems, and weapons control systems.

In the early 2000s, PCD's Israeli representative informed PCD of an advanced technology that presented a potential business opportunity worth millions of dollars to PCD if PCD could design and sell it. The product was a brushless direct current motor controller used in a missile navigation system. Another company, ELMO, was already making the controller. ELMO supplied the controller to Rafael Aerospace, the largest aerospace company in Israel. Rafael Aerospace provided the specifications of the controller to PCD. It also provided the ELMO controller to PCD. PCD attempted to create the controller on its own but was unsuccessful due to its lack of technical expertise. As a result, PCD reached out to Orchid, an engineering firm, to see if Orchid could design the controller.

Michael Allmayer, PCD's vice president of marketing, emailed Orchid's president Paul Nickelsberg in January 2004 to begin discussing the project. Eventually, the parties entered into a contract. The contract provided that Orchid would design and create a prototype of a brushless DC motor controller (BLDC1). PCD did not provide the ELMO controller to Orchid or even show it to Orchid as part of the negotiations with Orchid. It did not want Orchid to reverse engineer the ELMO controller, it wanted one made from scratch based solely from the ELMO specifications.

While the contract mentioned three different phases of project development, it only contained the Phase 1 development plan. In Phase 1, Orchid was required to provide four BLDC1 prototype circuit boards to PCD. The boards had to be "assembled, debugged and delivered to [PCD]" pursuant to a schedule in the contract. There were numerous specifications in the contract. However, at the time the contract was written the specifications were still being developed so the contract specifications were expressly defined as merely "guidelines." The contract required PCD to "supply all prototype testing." The contract did not specify how the prototypes should be tested. The contract simply stated that Phase 1 would be completed when Orchid delivered the prototype boards to PCD.

Over the course of the next few months, Orchid worked on designing and programming the prototype. At the end of 2004, Orchid began sending prototypes to PCD. PCD would test them and give feedback to Orchid about what needed to be adjusted to comply with the specifications. Orchid ultimately sent four sets of prototypes.

Orchid sent its final prototypes to PCD on March 16, 2005. Orchid notified PCD that the prototypes were within specification and that it was ready to move on to the next phase of development. PCD tested the prototypes on April 4, 2005. PCD's tests showed that the prototypes were not within the specifications. Allmayer emailed Nickelsberg that day to inform Orchid of its test results.

"We took measurements on the BLDC output current, which I've attached. So far, we haven't been able to verify the correct gain structure for the BLDC. At the 1 Volt command, the output shows a gain of approximately 9. Have you been able to externally verify that the unit is producing a current gain of 3 for every volt input command?
"I'm interested in hearing your ideas on this."

After discussing the discrepancies in testing results, it was discovered that Orchid had been testing the total output current of the prototype current at the servo current node of the BLDC1 prototype while PCD measured the phase current of the prototype at the shunt current node. Orchid conducted more tests, including testing in the manner that it discovered PCD had been using. On April 29, 2005, Nickelsberg emailed Allmayer a report-the BLDC1 Control Discussion and Review (Report). In the Report, Nickelsberg again asserted that Orchid's BLDC1 was performing correctly when tested "using industry-standard constant current monitoring techniques." The Report went on:

" The current measured at the BLDC SERVO CURRENT node and the current measured at the SHUNT CURRENT nodes are not equivalent. The BLDC SERVO CURRENT node measures the actual amplifier output current. The SHUNT CURRENT nodes measure both forward and free-wheeling currents within the load. Once again, the measurements are not equivalent. The freewheeling currents in the load, measured at the shunt point present a false indication of the actual real current within the system."

Finally, the report stated that "very significant changes to the BLDC1 design will be required" if PCD wished to use the alternate phase current testing method. Allmayer explained that this Report was the first time he believed that Orchid would be unable to fulfill the contract.

When Orchid told PCD that PCD was measuring the prototypes incorrectly, PCD believed that Orchid was acting in good faith. PCD was relying on Orchid's expertise in design.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

LeTourneau v. Law Offices of Richard Lester
Court of Appeals of Kansas, 2026

Cite This Page — Counsel Stack

Bluebook (online)
437 P.3d 66, 56 Kan. App. 2d 690, Counsel Stack Legal Research, https://law.counselstack.com/opinion/power-control-devices-inc-v-lerner-kanctapp-2019.