Power City Electric, Inc. v. Dep't of Labor & Indus.

CourtCourt of Appeals of Washington
DecidedNovember 15, 2018
Docket35676-1
StatusUnpublished

This text of Power City Electric, Inc. v. Dep't of Labor & Indus. (Power City Electric, Inc. v. Dep't of Labor & Indus.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Power City Electric, Inc. v. Dep't of Labor & Indus., (Wash. Ct. App. 2018).

Opinion

FILED NOVEMBER 15, 2018 In the Office of the Clerk of Court WA State Court of Appeals, Division III

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON DIVISION THREE

POWER CITY ELECTRIC INC., ) ) No. 35676-1-III Appellant, ) ) v. ) ) WASHINGTON STATE DEPARTMENT ) UNPUBLISHED OPINION OF LABOR AND INDUSTRIES, ) ) Respondent. )

KORSMO, J. — Power City Electric (PCE) appeals from a decision of the Board of

Industrial Insurance Appeals that found it to have committed four serious violations of

the Washington Administrative Code (WAC). Concerned about the adequacy of the

Board’s factual findings, we remand for more detailed findings and clarification of the

standard applied by the Board in its ruling.

FACTS

An effort to reroute underground power cables in Pasco is the basis for this case.

PCE was hired to move the power cables and had to dig a hole on the side of Court Street

to do so. A Department of Labor and Industries (DLI) compliance officer, Reynaldo No. 35676-1-III Power City Elec. v. Dep’t of Labor & Indus.

Gomez, was driving by the scene when he noticed only the helmeted head of a worker in

the hole. Concerned about the depth of the dig, he stopped to investigate.

Two men stepped out of the excavation by use of a notch dug into the shallower

south side of the hole. Dirt from the dig was piled immediately next to the deep end of

the trench.1 The excavation measured about six feet wide by ten feet long. A one foot

section on the north side of the dig was measured to be six feet deep. The depth ranged

from 30 to 48 inches in the remainder of the dig. Gomez graded the sandy soil in the

excavation as Type C—unstable. There were no measures in place to prevent collapse of

either the hole or of the spoils pile. Photographs of the scene were taken.

The two workers had been clearing fiber optic lines by shovel in the shallower side

of the trench. Their work zone was within 3.5 feet of the six foot deep section where the

backhoe was excavating.

DLI issued four major infraction notices, fining PCE $7,200. The Industrial

Appeals Judge (IAJ) heard testimony from Mr. Gomez and the PCE foreman, Julian

McCarthy. The IAJ upheld the citation for failure to provide a safe means of ingress and

egress, but rejected the other citations. Both PCE and DLI appealed.

The Board upheld all four citations and the $7,200 in total fines for the four

serious violations. The Board entered a decision that included an extensive discussion as

1 This is referred to as the “spoils pile.”

2 No. 35676-1-III Power City Elec. v. Dep’t of Labor & Indus.

well as findings of fact and conclusions of law. Clerk’s Papers (CP) at 5-12. The

superior court adopted the Board’s conclusions of law and affirmed its decision.

PCE appealed to this court. A panel heard oral argument on the case.

ANALYSIS

This appeal challenges, for varying reasons, whether the record supports the

Board’s factual findings. PCE also alleges that the Board applied the wrong standard in

assessing the risk of danger to workers. In order to explain our uncertainty and the need

for clarification by the Board, we need to address some of the regulations at issue and the

corresponding findings.

In order to establish a serious violation of state worker safety standards, RCW

49.17.180 requires proof that “death or serious physical harm could result” from an

existing condition. With respect to construction work, state safety standards are set out in

chapter 296-155 WAC. Washington adopted the federal standards governing the role of

likelihood of harm in assessing a violation of the state safety standards in Adkins v.

Aluminum Company, 110 Wn.2d 128, 750 P.2d 1257, 756 P.2d 142 (1988). A violation

of safety standards is established when an employee has “access” to the unsafe condition;

access is established when DLI shows “a reasonable predictability that, in the course of

their duties, employees will be, are, or have been in the zone of danger.” Id. at 147

(emphasis omitted). Accord, Mid Mountain v. Labor & Indus., 136 Wn. App. 1, 5, 146

P.3d 1212 (2006) (applying Adkins standard to an excavation setting).

3 No. 35676-1-III Power City Elec. v. Dep’t of Labor & Indus.

WAC 296-155-657(1) requires that workers in an excavation be protected from

the dangers of cave-ins by either sloping the excavation or installing protective systems.

WAC 296-155-657(2), (3). No protection is needed if the excavation is less than four

feet and an examination reveals “no indication of a potential cave-in.” WAC 296-155-

657(1).

Although the discussion segment of the Board’s decision addressed the facts in a

detailed manner similar to (but more extensive than) our brief recitation of them at the

beginning of this opinion, its formal findings of fact are more conclusory. Finding 2

states in part that PCE:

exposed its employees to potential cave-ins in a trench excavation of four feet or more in depth. The workers had access to the hazard posed by the unprotected portion of the excavation while in the course of their normal duties.

CP at 10.

This finding lacks detail allowing this court to understand how PCE exposed its

workers and how they had access to the hazard. Several possibilities exist in the record

that would support the Board’s ruling. The excavation was not sloped, nor were there

protective systems installed. Thus, if the workers were working in a portion of the trench

that was four feet or deeper, the violation would be clear. However, there is no fact

finding that the men were working in that area. Similarly, the south side of the trench

was described as 30 to 48 inches deep, with no clear finding that the men worked in that

4 No. 35676-1-III Power City Elec. v. Dep’t of Labor & Indus.

portion of the trench either. Moreover, the lack of sloping or protective equipment, in

combination with the Type C soil, may have been hazardous in and of itself. The Board’s

reasoning on this point is unclear.

Instead, finding 2 simply says that the men had “access” to areas “four feet or

more in depth.” The word “access” is insufficiently descriptive to explain how the men

were endangered. Were they working in an area that was four feet deep? Was the soil in

danger of collapsing on them? Did the hole slope sufficiently that a worker might be

expected to tumble into the deep end? Were they working so close to the deeper portion

of the trench that they would have been endangered by a collapse occurring on the north

side?

In contrast to these findings are the details in Mid Mountain. There the excavation

occurred in Type B soil that required an excavation of four feet six inches deep to have a

similar set back and that the “zone of danger” was an area within four feet six inches of

the south wall. 136 Wn. App. at 6. As in this case, the employer there argued that its

employees “were working in a portion of the trench that was less than four feet deep and

more than five feet away from the zone of danger.” Id. at 5. Based on the requirements

for Type B soil and the evidence of the dimensions of the excavation, the Mid Mountain

court was able to conclude that the worker was working within close proximity of the

zone of danger and it was reasonably likely that he could have walked into that zone

during the normal course of his work. Id. at 7.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Adkins v. ALUMINUM COMPANY OF AM.
756 P.2d 142 (Washington Supreme Court, 1988)
Mid Mountain Contractors, Inc. v. Department of Labor & Industries
146 P.3d 1212 (Court of Appeals of Washington, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
Power City Electric, Inc. v. Dep't of Labor & Indus., Counsel Stack Legal Research, https://law.counselstack.com/opinion/power-city-electric-inc-v-dept-of-labor-indus-washctapp-2018.