UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLUMBIA
POWDER RIVER BASIN RESOURCE COUNCIL, et al.,
Plaintiffs,
v. Case No. 22-cv-2696 (TSC)
U.S. DEPT. OF THE INTERIOR, et al.,
Defendants.
MEMORANDUM OPINION
Plaintiffs Powder River Basin Resource Council and Western Watersheds Project, two
environmental advocacy groups, challenge the U.S. Department of the Interior and the U.S. Bureau
of Land Management’s (“BLM”) approval of the Converse County Oil and Gas Project
(“Project”), alleging violations of the National Environmental Policy Act (“NEPA”), the
Administrative Procedure Act (“APA”), the Federal Land Policy and Management Act
(“FLPMA”), and the Mineral Leasing Act (“MLA”). Wyoming intervened, along with private
energy companies Continental Resources, Inc., Devon Energy Production Company, L.P.,
Anschutz Exploration Corporation, and Petroleum Association of Wyoming (“Intervenors”). The
court previously denied Plaintiffs’ motion for a preliminary injunction, ECF No. 64, granted in
part and denied in part Intervenors’ motion to dismiss, ECF No. 67, and denied Intervenors’
Motion to Transfer, ECF No. 68. See ECF Nos. 105–08. The court also granted in part and denied
in part Plaintiffs’ motion for summary judgment, ECF No. 116, and denied cross motions for
summary judgment filed by Defendants, Intervenors, and Wyoming, ECF Nos. 118, 121, 123. See
Page 1 of 21 ECF No. 130. Before the court are Plaintiffs’ remaining claims on summary judgment, as well as
Defendants’ Motion to Dissolve the Injunction, ECF No. 145, Intervenors’ Motion to Dissolve the
Interim Injunction, ECF No. 148, and Plaintiffs’ Motion for Leave to File a Second Amended
Complaint, ECF No. 155.
For the reasons below, the court will GRANT Plaintiffs’ motion for summary judgment,
DENY as moot Defendants’ and Intervenors’ motions to dissolve the injunction, and DENY
Plaintiffs’ motion for leave to file a Second Amended Complaint.
I. BACKGROUND
In 2013, energy companies (“Operator Group”) submitted a proposed development plan to
drill thousands of oil and gas wells in Converse County, Wyoming and amend the 2007 Casper
Resource Management Plan (“RMP”). BLM published a draft, supplemental, and final
Environmental Impact Statement (“EIS”) analyzing the Project’s anticipated environmental
effects. See AR 1183, 1190–93, 1277–78, 1292, 3143–234, 8413–94, 12362–13469. According
to the final EIS, 10 percent of the Project area consists of federal surface overlaying federal
minerals and 54 percent consists of non-federal surface overlaying federal minerals. See AR 46,
12426. As part of its NEPA analysis, the EIS examined three alternatives: Alternative A, a no-
action alternative, in which no new drilling would be authorized; Alternative B, the Operator
Group’s proposed alternative, which would authorize 5,000 new wells on 1,500 new well pads
over ten years; and Alternative C, a modified alternative, which would authorize the same number
of wells, but would also require some additional mitigation measures such as water recycling and
clustering of wells to reduce surface disturbance. See AR 1190–93. In December 2020, the
Secretary of the Interior issued a Record of Decision (“ROD”) selecting Alternative B and
approving an amendment to the Casper RMP. AR 16735–38. BLM then began issuing
Page 2 of 21 Applications for Permit to Drill (“APDs”) pursuant to the ROD. See Defs’ Opp’n to Pls’ Mot. for
Prelim. Inj., Ex. 1 ¶ 4, ECF No. 83-1.
In September 2022, Plaintiffs filed this action challenging the Project approval. See
Compl., ECF No. 1. They claim that Defendants violated NEPA, the APA, the FLPMA, and the
MLA in approving the Project and issuing hundreds of APDs without taking a “hard look” at
various environmental impacts like impacts to groundwater and greenhouse gas emissions,
justifying elimination of alternatives from further analysis, mitigating air emissions, and
preventing unnecessary or undue degradation of the public lands. 1st Am. Compl. ¶¶ 1, 112, 121–
58, ECF No. 44.
In March 2023, Plaintiffs moved for a preliminary injunction, seeking to enjoin the Project
and any further APDs pending the court’s decision on the merits, ECF No. 64, and Intervenors
moved to dismiss, arguing in relevant part that Plaintiffs lacked standing to challenge the APDs,
ECF No. 67. The court denied the motion for a preliminary injunction, holding that Plaintiffs
failed to demonstrate a likelihood of success on the merits or a likelihood of irreparable harm. See
Mem. Op. at 18–30, ECF No. 105. The court also granted in part and denied in part Intervenors’
motion to dismiss, finding Plaintiffs lacked standing to challenge the APDs. See id. at 12. In
January 2024, Plaintiffs moved for summary judgment, ECF No. 116, and Defendants,
Intervenors, and Wyoming all separately cross moved, ECF Nos. 118, 121, 123. In September
2024, the court entered partial summary judgment in Plaintiffs’ favor, holding that BLM’s use of
an erroneous specific storage value to model groundwater drawdown was arbitrary and capricious.
See Mem. Op. at 15–16, ECF No. 130. The court did not reach Plaintiffs’ remaining claims, and
instead requested supplemental remedies briefing and temporarily enjoined further permit
approvals based on the deficient EIS. Id. at 16–17.
Page 3 of 21 In April 2025, BLM published a White Paper finding no significant changes to
groundwater drawdown even accounting for a wider range of specific storage values. See Defs.’
Mot. to Dissolve Inj. at 2–3, ECF No. 145. In June 2025, based on the White Paper, BLM
published a supplemental Environmental Assessment (“EA”) of groundwater impacts, and a
corresponding Finding of No New Significant Impact (“FONNSI”) and Decision Record (“DR”)
affirming the Converse County ROD. See id. at 3–4.
In August 2025, relying on the White Paper, BLM issued an EA, Finding of No Significant
Impact (“FONSI”), and DR for the development of 212 horizontal oil and gas wells drilled on non-
federal surface land. See Defs.’ Opp. to Pls.’ Mot. for 2d Am. Compl. at 4–5, ECF No. 162. The
following month, BLM issued another EA, FONSI, and DR associated with 58 APDs on fee or
federally owned surface land. See id. at 5. These two EAs provided the basis for BLM’s approval
of another 60 APDs through 20 Categorical Exclusions that allowed BLM to circumvent further
site-specific NEPA analysis. See Pls.’ Mot. for 2d Am. Compl. at 9, ECF No. 155. Plaintiffs seek
to file a Second Amended Complaint challenging BLM decisions that (a) reaffirm the 2020 EIS
and ROD based on the June 2025 Supplemental EA, FONNSI, and DR; and (b) authorize 255 new
APDs under the two EAs and 20 Categorical Exclusions issued since August 2025. See id. at 10.
II. LEGAL STANDARD
Federal Rule of Civil Procedure 56(a), which typically supplies the legal standard on
summary judgment, does not apply to motions for summary judgment in APA cases “because of
the court’s limited role in reviewing the administrative record.” Coe v. McHugh, 968 F. Supp. 2d
237, 239 (D.D.C. 2013). Instead, the court must decide, as a matter of law, “whether the agency
action is supported by the administrative record and otherwise consistent with the APA standard
of review.” Id. at 240. Under this standard, the court is “highly deferential” to agency action,
Env’t Def. Fund, Inc. v. Costle, 657 F.2d 275, 283 (D.C. Cir. 1981), setting it aside only if the Page 4 of 21 action is “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law,”
5 U.S.C. § 706(2).
“To satisfy the APA’s ‘arbitrary and capricious’ standard, an agency must ‘articulate a
satisfactory explanation for its action including a rational connection between the facts found and
the choice made.’” Owner-Operator Indep. Drivers Ass’n v. Fed. Motor Carrier Safety Admin.,
494 F.3d 188, 203 (D.C. Cir. 2007) (quoting Motor Vehicle Mfrs. Ass’n v. State Farm Mut. Auto.
Ins. Co., 463 U.S. 29, 43 (1983)). That means the agency must “explain the assumptions and
methodology used in preparing” any models, id. at 204 (quoting U.S. Air Tour Ass’n v. FAA, 298
F.3d 997, 1008 (D.C. Cir. 2002)), and “provide a full analytical defense” of any challenged aspects,
Eagle–Picher Indus., Inc. v. EPA, 759 F.2d 905, 921 (D.C. Cir. 1985). In doing so, the court may
not “supply a reasoned basis for the agency’s action that the agency itself has not given.” State
Farm, 463 U.S. at 43. The plaintiff bears the burden of establishing that the agency’s action is
invalid. Fulbright v. McHugh, 67 F. Supp. 3d 81, 89 (D.D.C. 2014).
The APA standard of review applies to NEPA claims, as NEPA does not provide an
independent private right of action. See Theodore Roosevelt Conservation P’ship v. Salazar, 661
F.3d 66, 72 (D.C. Cir. 2011). As part of its “broad national commitment to protecting and
promoting environmental quality,” Robertson v. Methow Valley Citizens Council, 490 U.S. 332,
348 (1989), NEPA requires agencies to prepare an EIS for all “major Federal actions significantly
affecting the quality of the human environment,” 42 U.S.C. § 4332(2)(C); see id. § 4336(b)(1).
First, the agency must determine whether its proposed action is the type for which a full EIS is
normally required, or whether it falls within a Categorical Exclusion, a category of actions that
“normally does not significantly affect the quality of the human environment within the meaning
of [NEPA].” 42 U.S.C. § 4336e(1). “If the proposed action falls into neither category, NEPA
Page 5 of 21 directs the agency to prepare an EA that provides ‘sufficient evidence and analysis for determining
whether to prepare an environmental impact statement or a finding of no significant impact.’” In
re Polar Bear Endangered Species Act Listing & 4(d) Rule Litig., 818 F. Supp. 2d 214, 238 (D.D.C.
2011) (citation omitted); see 42 U.S.C. § 4336(b)(2). If, based on the EA, the agency concludes
that the action will not have a significant environmental effect, it may issue a FONSI in lieu of
preparing an EIS. See Sierra Club v. FERC, 827 F.3d 59, 63 (D.C. Cir. 2016).
III. ANALYSIS
A. Summary Judgment Motions
As discussed above, the court’s previous Memorandum Opinion addressing Plaintiffs’
motion for summary judgment and Defendants’ and Intervenors’ cross motions for summary
judgment held that Defendants’ choice of specific storage value was arbitrary and capricious, but
ordered supplemental briefing addressing the appropriate remedy. In doing so, the court left
unadjudicated Plaintiffs’ remaining summary judgment claims. Having considered the parties’
remedies briefing, ECF Nos. 135, 137, 138, 139, 142, as well as Plaintiffs’ remaining summary
judgment claims, the court finds that vacatur is appropriate based on another NEPA deficiency:
Defendants’ failure to adequately conduct an analysis of reasonable alternatives.
1. Mootness
As a preliminary matter, Defendants argue that because they have remedied the only error
the court identified in the Converse County EIS and ROD, Plaintiffs’ remaining claims are moot
and any further order on remedy is unwarranted. See Defs.’ Mot. to Dissolve Inj. at 7. Defendants
put the cart before the horse. In focusing on the specific storage value as grounds for determining
that the Project approval was deficient, the court did not implicitly hold that Plaintiffs’ remaining
grounds were meritless. And contrary to Defendants’ representation, the June 2025 DR does not
“supersede[]” the 2020 ROD. Defs.’ Opp. to Pls.’ Mot. for 2d Am. Compl. at 8. The 2025 Page 6 of 21 supplemental EA makes clear on its face that it does not displace the 2020 EIS: the EA is expressly
“limited to the analysis of potential groundwater drawdown impacts” and serves only to “provide
additional NEPA analysis using revised specific storage values.” U.S. Dep’t of the Interior,
Bureau of Land Mgmt., CCOGP Environmental Assessment 2 (June 6, 2025). The June 2025 DR
likewise “incorporates by reference” the 2020 EIS. U.S. Dep’t of the Interior, Bureau of Land
Mgmt., CCOGP Decision Record 1 (June 6, 2025).
Moreover, even assuming the June 2025 DR legally displaces the ROD, it would not
moot Plaintiffs’ claims, as BLM has not corrected the allegedly deficient analysis. Intervening
events moot a claim if “the [challenged] decision will neither presently affect the parties’ rights
nor have a more-than-speculative chance of affecting them in the future.” Am. Freedom Def.
Initiative v. Wash. Metro. Area Transit Auth., 901 F.3d 356, 361 (D.C. Cir. 2018) (quoting
Initiative & Referendum Inst. v. USPS, 685 F.3d 1066, 1074 (D.C. Cir. 2012)). In the case of
superseding agency action, the court must ensure that “(1) there is no reasonable expectation that
the alleged violation will recur, and (2) interim relief or events have completely or irrevocably
eradicated the effects of the alleged violation.” Id. at 362 (quoting Nat’l Black Police Ass’n v.
District of Columbia, 108 F.3d 346, 349 (D.C. Cir. 1997)). As noted above, the DR “affirm[ed]”
the ROD, “incorporat[ing] by reference” the 2020 EIS. U.S. Dep’t of the Interior, Bureau of
Land Mgmt., CCOGP Decision Record (June 6, 2025). In other words, even assuming the 2025
documents somehow “replaced” the 2020 documents, it is not “correct to say [BLM] has ceased
the challenged conduct; instead, [it] has renewed the challenged conduct in a new form.” Am.
Freedom Def. Initiative, 901 F.3d at 362. “In these circumstances, the [new actions] preserve,
rather than moot, the original controversy . . . .” Pickus v. U.S. Bd. of Parole, 507 F.2d 1107,
1111 (D.C. Cir. 1974); see Organic Trade Ass’n v. U.S. Dep’t of Agric., 370 F. Supp. 3d 98, 111
Page 7 of 21 (D.D.C. 2019) (“Agencies can moot claims against them by promulgating new rules that cure
previous procedural defects . . . .”).
2. NEPA Alternatives Analysis
“The heart of an EIS is its analysis of a reasonable range of alternatives to the agency’s
proposed action.” Oceana, Inc. v. Evans, 384 F. Supp. 2d 203, 240 (D.D.C. 2005). An
alternative is “reasonable,” and should be considered if it is “technically and economically
practical or feasible” and “meet[s] the purpose and need of the proposed action.” 43 C.F.R. §
46.420(b). The court evaluates “both an agency’s definition of its objectives and its selection of
alternatives under the ‘rule of reason.’” Theodore Roosevelt, 661 F.3d at 73 (quoting Citizens
Against Burlington, Inc. v. Busey, 938 F.2d 190, 195–96 (D.C. Cir. 1991)). If an agency’s
objectives are not “unreasonably narrow,” the court “will uphold the agency’s selection of
alternatives that are reasonable in light of those objectives.” Id. But “for alternatives [that the
agency] eliminated from detailed study,” the agency must “briefly discuss the reasons for their . .
. eliminat[ion].” Stand Up for California! v. U.S. Dep’t of the Interior, 919 F. Supp. 2d 51, 77
(D.D.C. 2013) (citation omitted).
a. Paced Development Alternative
BLM “eliminated from further detailed analysis” an alternative limiting the total number
of wells developed annually because “its implementation is remote or speculative, and it is
inconsistent with the basic policy objectives for the management of the area.” AR 12492. BLM
reasoned that implementation was speculative because “[a] reduction in the number of wells
drilled in a year may not reduce surface disturbance (i.e., the number of pads may not be
reduced)” and any limit on the number of wells “could not be imposed on approximately one-
third of the CCPA.” Id. Similarly, BLM “eliminated from further analysis” an alternative
Page 8 of 21 limiting the number of wells per operator because it “would not be consistent with the purpose of
the agency action,” “would not address a known resource conflict in the CCPA,” “could not be
imposed on approximately one-third of the CCPA,” and because the agency lacks “the authority
to infringe upon existing lease rights by imposing limits on the pace of development or selecting
which operator(s) are allowed to drill.” Id.
The court addresses each rationale in turn. Contrary to BLM’s representation, a slower
pace of development is not inconsistent with the agency’s stated purpose and need for agency
action. The EIS states the relevant purpose and need as follows:
The need for [BLM] action is to respond to this proposal while allowing the OG to exercise its valid lease rights under pertinent laws, rules, and regulations. The Federal Land Policy and Management Act of 1976 (Public Law 94 579, 43 United States Code 1701 et seq.) recognizes oil and gas development as one of the “principal” uses of public lands. Federal mineral leasing laws (Mineral Leasing Act of 1920, 30 USC 188 et seq.) and regulations recognize the statutory right of lease holders to develop federal mineral resources to meet continuing national needs and economic demands. The purpose of this EIS is to evaluate potential impacts resulting from implementing future plans and applications related to this proposal; to facilitate the decision-making process to approve, approve with modifications, or disapprove the proposed project or project components based on an evaluation of the expected impacts; and to the extent possible, minimize or avoid environmental impacts.
AR 12370.
BLM does not attempt to defend its contention that phased development is inconsistent with
these stated objectives. Nor could it, because such a rationale fails to pass muster even under a
deferential review for reasonableness. Contrary to Intervenors’ representation, BLM’s stated
purpose is not to “enact or adopt the Operators’ proposal,” but rather “to decide whether to adopt
the proposal at all, and if so, to what degree.” Theodore Roosevelt, 661 F.3d at 73. “This
objective permits a reasonable range of alternatives that either reject the proposal or adopt it to
varying degrees or with alterations.” Id. And while Intervenors stress that a reduced rate of
development runs contrary to the “main” purpose and need for agency action, which they assert
Page 9 of 21 is to promote the exercise of lease rights and development of federal mineral resources,
Intervenors’ Cross Mot. Summ. J. at 23–24, ECF No. 121, the statement of purpose expressly
contemplates that BLM should “minimize or avoid environmental impacts” when “possible”
based on its “evaluation of [] expected impacts,” AR 12370. It is also “past doubt” that the
FLPMA “does not require BLM to prioritize [oil and gas] development over other [land] uses,”
which include “conservation to protect environmental values.” New Mexico ex rel. Richardson
v. BLM, 565 F.3d 683, 710 (10th Cir. 2009). Similarly, the MLA requires BLM to include in
each lease provisions to ensure “the safeguarding of the public welfare” and regulate “surface-
disturbing activities . . . in the interest of conservation of surface resources.” 30 U.S.C. §§ 187,
226(g); see Copper Valley Mach. Works, Inc. v. Andrus, 653 F.2d 595, 601 (D.C. Cir. 1981)
(“[S]uspending operations to avoid environmental harm is definitely a suspension in the interest
of conservation in the ordinary sense of the word.”); Nat. Res. Def. Council, Inc. v. Berklund,
458 F. Supp. 925, 936 n.17 (D.D.C. 1978) (interpreting “safeguarding of [] public welfare” to
provide “broad authority to set lease terms to prevent environmental harm”). Because, as BLM
recognized, “a reduction in the number of wells drilled in a year may result in a reduction in air
emissions and a potential reduction in air quality impacts,” it is consistent with its statement of
need and purpose to examine that alternative. AR 12492.
BLM also eliminated this alternative on the basis that it lacks “authority to infringe upon
existing lease rights.” Id. Again, Intervenors alone defend this rationale, which is irreconcilable
with statutory authority. Under the MLA, the Secretary of the Interior “has discretion to
determine where, when, and under what terms and conditions oil and gas development should
occur.” WildEarth Guardians v. Zinke, 368 F. Supp. 3d 41, 52 (D.D.C. 2019) (citing 30 U.S.C. §
226); cf. 43 U.S.C. § 1732(b) (requiring BLM to “take any action necessary to prevent
Page 10 of 21 unnecessary or undue degradation of the lands”). “Accordingly, the federal government may
impose a broad range of stipulations on oil and gas leases for federal land, including concerning
the timing, pace, and scale of development.” Zinke, 368 F. Supp. 3d at 52.
BLM also stated that a paced development alternative “would not address a known
resource conflict,” AR 12492, presumably in reference to NEPA’s requirement that agencies
“study, develop, and describe appropriate alternatives to recommended courses of action in any
proposal which involves unresolved conflicts concerning alternative uses of available resources,”
42 U.S.C. § 4332(H). Again, Intervenors alone defend this rationale, arguing that BLM need
only consider conflicts between oil and gas development and “recovery of other mineral
resources,” not air quality. Intervenors’ Cross Mot. Summ. J. at 25 (emphasis added) (quoting
43 C.F.R. § 3162.1(a) (setting forth general operating requirements for oil and gas lessees and
operators on public lands)). But nowhere does § 4332(H) exempt BLM from examining
alternatives that mitigate general environmental harms. It is beyond doubt that NEPA requires
consideration of reasonable alternatives to a contemplated action that minimize or reduce the
environmental effects of its decision. See Citizens Action Coal. of Ind., Inc. v. FERC, 125 F.4th
229, 235 (D.C. Cir. 2025).
BLM further reasoned that the fact that it could limit the pace of development in only
about two-thirds of the Project area rendered a phased development alternative overly “remote or
speculative.” AR 12492. Taken at face value, this rationale does not withstand scrutiny: it is not
obvious to the court why a slower rate of development in well over half of the Project area
renders implementation “speculative.” In its briefing, BLM explains that because the areas it
controls are interspersed with areas under state and private control, state and private actors could
offset any reduction in the pace of development in federally controlled areas. Defs.’ Cross Mot.
Page 11 of 21 Summ. J. at 37. But this explanation was absent from the EIS, and neither the court nor BLM
may “fill in critical gaps in the [agency]’s reasoning” at this stage. Point Park Univ. v. NLRB,
457 F.3d 42, 50 (D.C. Cir. 2006). The court “look[s] only to what the agency said at the time of
the rulemaking—not to its lawyers’ post-hoc rationalizations.” Am. Fed’n of Lab. & Cong. of
Indus. Orgs. v. NLRB, 57 F.4th 1023, 1049 (D.C. Cir. 2023) (quoting Good Fortune Shipping SA
v. Comm’r, 897 F.3d 256, 263 (D.C. Cir. 2018)).
Finally, BLM reasoned that it need not further investigate a paced development
alternative because Alternative C “already considered reduced effects by limiting the number of
well pads.” AR 16758; see Defs.’ Reply Supp. Cross Mot. Summ. J. at 15 n.11, ECF No. 125.
But the record suggests otherwise. BLM’s own “analysis does not suggest that the impacts
would be identical”—or even comparable to—commenters’ proposed phased-development
alternatives. Union Neighbors United, Inc. v. Jewell, 831 F.3d 564, 577 (D.C. Cir. 2016). While
Alternative C contemplated fewer well pads than Alternative B, AR 12374, “development under
Alternative C would occur at the same rate as Alternative B, and the overall level of production
would remain the same,” AR 12961. BLM estimated that Alternative C would therefore “vary
only slightly from Alternative B” in terms of air quality impacts. AR 12377; see AR 4180
(noting that Alternative C is “basically indistinguishable from the preferred action when it comes
to air emissions and resulting air quality impacts because it assumes the same degree of oil and
gas development in the same area” and that Alternative C might even “result in greater emissions
compared to Alternative B”); AR 6331 (“Alternative C does not reduce the impacts from the
Project, especially for air, land, and wildlife resources.”).
Page 12 of 21 b. Greenhouse Gas Mitigation Alternative
BLM noted that commenters had proposed three distinct layers of greenhouse gas
control: an outcome-based carbon-neutral operations requirement, a categorical prohibition on
venting and flaring, and source-level direct mitigation measures designed to reduce methane
emissions across drilling, completion, and production activities. AR 12491. In eliminating an
alternative involving greater greenhouse gas mitigation, BLM stated that “it is not technically
feasible to conduct full carbon-neutral processes” and that “venting and flaring are conducted for
safety reasons and cannot be fully avoided.” AR 12492.
In focusing only on the feasibility of carbon-neutral operations and total elimination of
venting and flaring, BLM omitted any consideration of the feasibility of reducing greenhouse gas
emissions. Commenters had suggested adopting measures such as more efficient flaring
practices, high-efficiency compressor technologies and practices, and more advanced leak
detection and repair protocols to reduce greenhouse gas emissions. See, e.g., AR 4181, 4207,
4208, 4438, 4449. BLM’s EIS Scoping Report acknowledged comments requesting alternatives
“designed to reduce or eliminate greenhouse gas emissions.” AR 400 (emphasis added). The
EIS’s all-or-nothing approach conflicts with the agency’s obligation under NEPA to “provide
legitimate consideration to alternatives that fall between the obvious extremes.” High Country
Conservation Advocs. v. U.S. Forest Serv., 951 F.3d 1217, 1224 (10th Cir. 2020) (quoting Colo.
Env’t Coal. v. Dombeck, 185 F.3d 1162, 1175 (10th Cir. 1999)); see Nat. Res. Def. Council, Inc.
v. Morton, 458 F.2d 827, 836 (D.C. Cir. 1972) (holding that an agency should not “disregard
alternatives merely because they do not offer a complete solution to the problem”).
BLM responds that certain measures to reduce greenhouse gas emissions were included
in Alternative B, and that further measures were not feasible. See Defs.’ Cross Mot. Summ. J. at
Page 13 of 21 39. But while Alternative B includes a set of air-quality mitigation measures, those measures are
primarily aimed at criteria pollutants—particularly nitrogen oxides—rather than greenhouse
gases such as methane and carbon dioxide. See AR 13366, 13370–71. The EIS makes clear that
measures to reduce criteria pollutants and improve compliance with ozone-related air quality
standards have only secondary or incidental benefits with respect to greenhouse gas reduction.
See, e.g., AR 12248, 13295–96 (outlining measures primarily aimed at volatile organic
compounds, particulate matter, and nitrogen oxides). Although BLM correctly observed that
“[m]any control strategies and mitigation measures that reduce criteria pollutants and hazardous
pollutants also reduce greenhouse gas emissions,” AR 12248, incidental climate benefits from
criteria-pollutant controls are analytically distinct from direct mitigation of greenhouse gas
emissions, particularly methane, the dominant climate pollutant from oil and gas development.
By contrast, Plaintiffs’ proposed greenhouse gas reduction alternative would have
imposed mandatory, performance-based measures specifically designed to reduce methane and
carbon dioxide emissions, including limits on venting and flaring as well as direct methane-
control technologies. See AR 400–01, 4181, 4864–65. Allowing incidental mitigation measures
embedded in the preferred alternative to serve as a substitute for consideration of direct
greenhouse-gas control measures would undermine NEPA’s core function of ensuring “the
agency’s presentation of ‘the environmental impacts of the proposal and the alternatives in
comparative form, thus sharply defining the issues and providing a clear basis for choice among
options by the decisionmaker and the public.’” City of Grapevine v. Dep’t of Transp., 17 F.3d
1502, 1506 (D.C. Cir. 1994) (citation omitted). The agency’s determination that there may be
incidental spillover effects from controls aimed at other pollutants cannot satisfy its duty to
Page 14 of 21 “[r]igorously explore and objectively evaluate” targeted greenhouse gas reduction measures as a
standalone alternative. Oceana, 384 F. Supp. 2d at 240 (citation omitted).
Applying the rule of reason, the court concludes that in eliminating reduced rate of
development and greenhouse gas reduction alternatives without further analysis, BLM violated
its obligation to rigorously evaluate a reasonable range of alternatives to its proposed action. See
42 U.S.C. § 4332(2)(C).
B. Remedy
Having determined that the Converse County Project approval violated NEPA, the court
must decide whether to vacate the EIS and ROD or remand without vacatur. The APA requires a
reviewing court to “hold unlawful and set aside” agency action it determines to be “arbitrary,
capricious, an abuse of discretion, or otherwise not in accordance with law.” 5 U.S.C. §
706(2)(A). Accordingly, the “ordinary practice . . . is to vacate unlawful agency action, and
district courts in this circuit routinely vacate agency actions taken in violation
of NEPA.” Standing Rock Sioux Tribe v. U.S. Army Corps of Eng’rs, 985 F.3d 1032, 1050 (D.C.
Cir. 2021) (citation omitted).
“Although vacatur is the typical remedy for an APA violation, it is not inevitable.” Gulf
Restoration Network v. Haaland, 47 F.4th 795, 804 (D.C. Cir. 2022). In limited circumstances,
courts may decline to vacate an agency’s action if equity so requires. Id. at 804–05. The choice
depends on two factors: the “seriousness of the order’s deficiencies (and thus the extent of doubt
whether the agency chose correctly) and the disruptive consequences of an interim change.”
Allied-Signal, Inc. v. U.S. Nuclear Regul. Comm’n, 988 F.2d 146, 150–51 (D.C. Cir. 1993). “Put
otherwise, this Court must determine whether there is ‘at least a serious possibility that the
[agency] will be able to substantiate its decision on remand,’ and whether vacatur will lead to
Page 15 of 21 impermissibly disruptive consequences in the interim.” Zinke, 368 F. Supp. 3d at 84 (quoting
Standing Rock Sioux Tribe v. U.S. Army Corps of Eng’rs, 282 F. Supp. 3d 91, 97 (D.D.C. 2017)).
Both factors militate in favor of vacating the Project approval before remanding it to the
agency. The errors here were the type that prompts “substantial doubt” that the agency chose
correctly. Standing Rock Sioux Tribe, 985 F.3d at 1052. With an informed look at the
alternatives involving a slower pace of development and greenhouse gas reduction measures,
BLM could reasonably change course. “[T]he Court cannot be sure that the agency will arrive at
the same conclusion after further consideration—let alone whether, on further judicial review,
this or a similar [agency action] will withstand challenge under the APA.” Humane Soc’y of
U.S. v. Kempthorne, 579 F. Supp. 2d 7, 21 (D.D.C. 2008).
Defendants and Intervenors also fail to carry their burden of showing “that vacatur would
be so disruptive as to justify a departure from [the] normal course.” Cboe Futures Exch., LLC v.
SEC, 77 F.4th 971, 982 (D.C. Cir. 2023). Plaintiffs ask the court to vacate only the EIS and
ROD, not existing permitting decisions made in reliance on them. See Pls.’ Reply Supp. Mot.
Summ. J. at 72–73, ECF No. 124. That modest relief would not enjoin development of existing
drilling permits or require BLM to unwind completed wells or infrastructure. And as the
Government and Intervenors concede, “vacatur of the EIS and ROD will not prevent BLM from
approving new APDs or other authorizations” in the Converse County area that are independent
of the deficient EIS. Intervenors’ Remedy Br. at 13, ECF No. 138. The only relevant disruption
is the cost to the Government of supplementing its NEPA analysis and any delays in issuing new
permits during that reconsideration. While the Government and Intervenors project significant
economic consequences from such delay, these are ordinary consequences of NEPA compliance,
and not ones that establish sufficient prejudice to merit withholding vacatur. See Standing Rock
Page 16 of 21 Sioux Tribe, 985 F.3d at 1051 (explaining that economic harm “is not commonly a basis,
standing alone, for declining to vacate agency action”). The court must also consider the
environmental harm of keeping the deficient EIS in place. The Project is already emitting and
will continue to emit significant levels of greenhouse gases that will contribute to climate change
and impart other significant environmental harm, impacting human health, sensitive natural
resources, landscapes, and wildlife. Vacatur is necessary to ensure that the Project proceeds with
the benefit of a fully fleshed out consideration of the issues under NEPA.
C. Second Amended Complaint
Plaintiffs now seek to file a Second Amended Complaint realleging their pending claims
against the 2020 Converse County EIS, ROD, and RMP Amendment, and introducing new
claims against several more recent NEPA documents and associated permit approvals.
Specifically, in Counts 1 to 3, Plaintiffs reallege their pending NEPA, APA, FLPMA, and MLA
claims against the 2020 EIS. 1 Proposed 2d Am. Compl. ¶¶ 380–99, ECF No. 155-1. In Counts
11 to 13, Plaintiffs allege new claims against the 2025 Supplemental EA, FONNSI, and DR. Id.
¶¶ 458–81. In Counts 4 to 10, Plaintiffs seek to challenge the 22 new BLM decisions approving
the 255 APDs for oil and gas wells in Converse County between August and October 2025, as
well as the NEPA documents used to approve those APDs, including two new EAs and 20
Categorical Exclusions that rely on the 2025 White Paper’s groundwater analysis. Id. ¶¶ 400–57.
Under Federal Rule of Civil Procedure 15, an addition to a pleading may take one of two
forms: it may be an “amendment” under Rule 15(a), or a “supplement” under Rule 15(d). Clean
Water Action v. Pruitt, 315 F. Supp. 3d 72, 79 (D.D.C. 2018). An amendment “typically rest[s]
on matters in place prior to the filing of the original pleading,” while a supplement “sets forth
1 Vacating the Converse County EIS and ROD moots Plaintiffs’ unaddressed claims challenging those decisions. Therefore, leave to amend would be futile as to Counts 1 to 3. Page 17 of 21 transactions or occurrences or events which have happened since the date of the pleading sought
to be supplemented.” United States v. Hicks, 283 F.3d 380, 385 (D.C. Cir. 2002) (quoting Fed.
R. Civ. P. 15(d)). Rule 15(a) provides that unless permitted as a matter of course, “a party may
amend its pleading only with the opposing party’s written consent or the court’s leave.” Fed. R.
Civ. P. 15(a)(2). “The court should freely give leave when justice so requires.” Id. Rule 15(d)
provides that “[o]n motion and reasonable notice, the court may, on just terms, permit a party to
serve a supplemental pleading” and “may order that the opposing party plead to the supplemental
pleading.” Id. 15(d).
Leave to amend or supplement “should be denied” when “the complaint, as amended,
would radically alter the scope and nature of the case and bears no more than a tangential
relationship to the original action.” Miss. Ass’n of Cooperatives v. Farmers Home Admin., 139
F.R.D. 542, 544 (D.D.C. 1991); see also Nat’l Treasury Emps. Union v. Helfer, 53 F.3d 1289,
1295 (D.C. Cir. 1995) (“[T]he district court did not abuse its discretion in denying the
amendment, which bore ‘only tangential relationship’ to the original claim.”). “Delay and
prejudice are precisely the matters to be addressed in considering whether to grant motions for
supplemental pleadings; such motions are to be ‘freely granted when doing so will promote the
economic and speedy disposition of the entire controversy between the parties, will not cause
undue delay or trial inconvenience, and will not prejudice the rights of any of the other parties to
the action.’” Hall v. CIA, 437 F.3d 94, 101 (D.C. Cir. 2006) (quoting 6A Wright & Miller,
Federal Practice & Procedure § 1504, at 186–87 (2d ed. 1990)).
While both the decision whether to allow amendment and supplementation are within the
discretion of the district court, see WildEarth Guardians v. Kempthorne, 592 F. Supp. 2d 18, 23
(D.D.C. 2008), the plain text of Rule 15(d) suggests the district court has wider discretion to
Page 18 of 21 deny supplementation than leave to amend, compare Fed. R. Civ. P. 15(a)(2) (“The court should
freely give leave when justice so requires”) with id. 15(d) (“[T]he court may, on just terms,
permit a party to serve a supplemental pleading . . .”); see Pruitt, 315 F. Supp. 3d at 80 (“The
plain text of Rule 15(d) . . . permits a court to grant leave to supplement, but imposes no standard
requiring a court to do so.”). Plaintiffs acknowledge that whether they should be permitted to
add BLM decisions post-dating the existing Complaint—(1) the June 2025 EA, FONNSI, and
DR, and (2) the approval of 255 new APDs from August through October 2025 and their
supporting NEPA documents—is appropriately analyzed under Rule 15(d) governing motions to
supplement. See Pls.’ Mot. for 2d Am. Compl. at 12.
Plaintiffs’ proposed new claims are “factually and legally distinct from the current
claims.” Pruitt, 315 F. Supp. 3d at 85. Count 13, for example, alleges that BLM personnel
lacked the requisite authority to issue the June 2025 DR, a claim wholly unrelated to Plaintiffs’
original NEPA, MLA, and FLPMA claims against the 2020 ROD. See Proposed 2d Am. Compl.
¶¶ 477–81. While the 2025 EAs, Categorical Exclusions, and APDs are “superficially similar”
to the 2020 EIS and ROD in that they all concern proposed drilling in Converse County and
allegedly rely on the same flawed groundwater analysis, they are otherwise separate agency
actions concerning a new set of projects. Pruitt, 315 F. Supp. 3d at 85. None of the post-August
2025 documents ties to the 2020 EIS or purport to implement or carry out the land-use planning
decisions embodied in the ROD. Each EA is accompanied by its own FONSI and DR, marking
the consummation of BLM’s decision-making process for those projects and conferring direct
legal consequences. The Categorical Exclusions were likewise issued through a distinct, more
streamlined NEPA process that authorizes drilling without preparation of an EA or EIS.
Page 19 of 21 Because the 2025 approvals rest on separate procedures, administrative records, and
decision documents independently authorizing development, they constitute new, final agency
actions subject to separate NEPA and APA review, rather than extensions of the 2020 EIS or
ROD. See Pruitt, 315 F. Supp. 3d at 85 (rejecting supplementation seeking to challenge
“different type[s] of agency action” that were “promulgated based on a different administrative
record, pursuant to different authority”). Adding these claims after years of dispositive motions
that have narrowed the case would “radically alter the scope and nature of the case,” Wolf v. CIA,
569 F. Supp. 2d 1, 11 (D.D.C. 2008), and force Defendants and Intervenors “to respond to ever-
changing targets,” Howard v. Blank, 891 F. Supp. 2d 95, 102 (D.D.C. 2012).
“Additionally, one of the ‘most important factor[s]’ to consider is ‘the possibility of
prejudice to the opposing party.’” Lawrence v. Lew, 156 F. Supp. 3d 149, 174 (D.D.C. 2016)
(quoting Djourabchi v. Self, 240 F.R.D. 5, 13 (D.D.C. 2006)). Plaintiffs will suffer
comparatively minimal prejudice because they can readily file their claims in a separate action.
Any inconvenience from not being able to assert new causes of action in this litigation is not “the
type of inconvenience that implicates the principles of fairness and judicial economy that justify
application of the standard that leave to file a supplemental pleading should ‘be liberally
granted.’” Cause of Action Inst. v. U.S. Dep’t of Just., 282 F. Supp. 3d 66, 76 (D.D.C. 2017).
By contrast, to allow amendment now would protract this litigation and thus prejudice
Defendants and Intervenors. See id. The parties have already completed multiple rounds of
briefing on various dispositive motions, including the pending motion for summary judgment
that predates Plaintiffs’ request to supplement the complaint. Allowing supplementation would
necessitate yet another round of briefing based on a different administrative record before a final
Page 20 of 21 ruling on Plaintiffs’ fully briefed Converse County ROD claims could be obtained. See Pruitt,
315 F. Supp. 3d at 84.
In sum, because Plaintiffs’ proposed claims “would unduly delay and alter the scope of
this litigation,” denial of leave to supplement is appropriate. Id. at 85.
IV. CONCLUSION
For the foregoing reasons, the court will GRANT Plaintiffs’ Motion for Summary
Judgment. ECF No. 116. Accordingly, the 2020 Converse County EIS and ROD will be
vacated and remanded to the agency for further consideration consistent with this Memorandum
Opinion. The court will DENY as moot Defendants’ Motion to Dissolve the Injunction, ECF
No. 145, Intervenors’ Motion to Dissolve the Injunction, ECF No. 148, and Wyoming’s Motion
for Joinder, ECF No. 147. The court will also DENY Plaintiffs’ Motion for Leave to File a
Second Amended Complaint. ECF No. 155. A separate order will accompany this
Memorandum Opinion.
Date: February 27, 2026
Tanya S. Chutkan TANYA S. CHUTKAN United States District Judge
Page 21 of 21