Poudre River Oil, Corp. v. Carey

266 P. 201, 83 Colo. 419, 1928 Colo. LEXIS 256
CourtSupreme Court of Colorado
DecidedMarch 19, 1928
DocketNo. 11,869.
StatusPublished
Cited by5 cases

This text of 266 P. 201 (Poudre River Oil, Corp. v. Carey) is published on Counsel Stack Legal Research, covering Supreme Court of Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Poudre River Oil, Corp. v. Carey, 266 P. 201, 83 Colo. 419, 1928 Colo. LEXIS 256 (Colo. 1928).

Opinion

Mr. Justice Walker

delivered the opinion of the court.

Dependant in error was plaintiff, plaintiff in error defendant below, and we shall so designate them in this opinion. Present counsel for defendant did not represent it in the court below.

The action was to recover $3,350 claimed for services in drilling an oil well, and to foreclose a lien for that amount which the plaintiff had filed upon certain personal property belonging to the defendant. The trial was to the court without a jury. Judgment was rendered for the plaintiff in the sum of $2,920, and foreclosure of the lien was ordered. Errors are assigned both to the money judgment and the decree for the foreclosure of the lien.

Defendant had a lease upon certain lands in Larimer county, upon which it desired to sink a well for oil. It was however without funds except such as were accruing from the sale of its capital stock. On April 14, 1926, plaintiff, who was an experienced driller, entered into a *421 written contract with defendant, by the terms of which plaintiff was to drill a well upon defendant’s leased land, to a depth of 3,000 feet unless oil or gas should be sooner encountered. The plaintiff agreed to furnish all drilling equipment and machinery, except derrick, rig irons and cordage, which defendant was to' provide. The defendant also agreed to furnish all fuel and casing on location. Plaintiff was to do the work “in good and workmanlike manner” and “to prosecute the same to final completion at the earliest possible time compatible with good workmanship and safety to drilling operations.” Defendant agreed to pay $2.50 per foot for the drilling, payments for work done to be made upon completion of each 500 feet of well, but 25 per cent of the payment so earned was to be by the defendant deposited in escrow in the Pondré Yalley National Bank, and turned over to plaintiff upon completion of the work.

Operations were begun under the contract, and the well had been sunk to a depth of 2,165 feet without oil or gas having been struck, when on August 25th plaintiff removed his machinery from the location. On Au- • gust 28th he filed the lien in question, and on September 6th instituted this action.

The complaint as amended set forth the written contract, and oral contracts for extra work. The oral contracts were $120 for repairing and $500 for daylight drilling and $430 for swedging casing. Upon the written contract $5,350 was claimed to have been earned, being 2,140 feet at' the contract rate. However, the total demand was $7,100, less $3,750 admitted to have been paid. Of this demand $700 represented a claim for straight reaming under oral agreement not specifically mentioned in the complaint but shown in the evidence. The complaint alleged that the plaintiff performed all the conditions of the written contract on his part except that he was unable to proceed further with the contract because of the defaults of the defendant in the following particulars: (1) Failure to furnish fuel; (2) failure to *422 furnish casing; (3) failure to furnish cordage; and (4) failure to deposit the escrow money as agreed. Defendant by its answer denied the making of the oral contracts, averred that the escrow provision had been waived by agreement, denied the other defaults charged .against it, averred that plaintiff had without justification abandoned the contract, and in addition, by way of counterclaim, averred that plaintiff had drilled a “crooked hole” and ruined casing belonging to defendant. Issue was also joined upon the existence of the lien claimed by plaintiff. The court found for the plaintiff except upon the $430 claimed for swedging.

The findings having been for plaintiff, we must assume that all conflicts in the testimony were resolved in his favor. The questions presented must therefore be treated in the light of the evidence most favorable to the plaintiff.

1. The errors assigned to the recovery upon the oral items do not present any difficulty. There was evidence to support each of these items, but it is not necessary to detail it here. The principal objection to the allowance of the $700 claim for straight reaming is that the plaintiff did not set it forth in his complaint. However, it was embraced in the general allegation of the original complaint, and within the amount of the demand in the complaint as amended, and so was at least defectively pleaded. Evidence pertaining to it was introduced by the plaintiff without objection by defendant, which in its turn offered testimony to support its version of the item. It was thus treated as an issue, and the omission of the specific allegation from the complaint cannot be raised for the first time in this court under such circumstances. 31 Cyc. 723; Lampman v. Lamping, 70 Colo. 167, 199 Pac. 418.

2. The. recovery upon the written contract is vigorously assailed upon several grounds. It is contended that there is no sufficient evidence to support the finding *423 that the defendant had breached the contract; that the defendant’s defaults, if any, had been waived by the act of the plaintiff in proceeding thereafter with the execution of the contract; that the evidence was such as to compel a finding that the plaintiff’s abandonment of the work before the well reached the required depth was unjustified; and that the evidence conclusively established the breaches charged to the plaintiff by the counterclaim.

It is manifest that the complaint is drama on the theory that the defendant had committed such a breach or breaches of the contract as excused the plaintiff from further performance, and entitled him to recover the contract price for the work which had been completed when he terminated the agreement. No question is raised as to the propriety of the measure of damages selected by the plaintiff.

According to the plaintiff’s testimony, the drilling line and cordage furnished by the defendant were defective, and on that account the drilling was stopped more than once; that May 29th to June 25th, July 10th to 20th, drilling was stopped because of the failure of defendant to furnish casing; that July 29th to 30th, August 8th to 13th, August 17th to the time when plaintiff quit work, drilling was stopped on account of the failure of the defendant to furnish fuel; that plaintiff on August 1st and 2nd had to purchase fuel, as the defendant had failed to supply it; that each shutdown was at plaintiff’s expense. Plaintiff also testified that an agent of the defendant company was continuously upon the location with full opportunity to know of conditions there, and that the plaintiff on August 18th told the president of the defendant company that operations were suspended on account of lack of fuel. Plaintiff further testified that the escrow money was never deposited, that there was never any agreement to waive it, but that on the contrary the plaintiff repeatedly demanded that this provision of the contract be complied with.

*424 The parties contemplated that the work would be prosecuted as speedily as “compatible with good workmanship and safety.” Every cessation of operations diminished the plaintiff’s profits.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Blood v. Qwest Services Corp.
224 P.3d 301 (Colorado Court of Appeals, 2009)
Gearhart-Owen Industries, Inc. v. Panhandle Production Co.
624 P.2d 355 (Colorado Court of Appeals, 1980)
Terminal Drilling Co. v. Jones
269 P. 894 (Supreme Court of Colorado, 1928)

Cite This Page — Counsel Stack

Bluebook (online)
266 P. 201, 83 Colo. 419, 1928 Colo. LEXIS 256, Counsel Stack Legal Research, https://law.counselstack.com/opinion/poudre-river-oil-corp-v-carey-colo-1928.