Potts v. Village of Haverstraw

79 F.2d 102, 1935 U.S. App. LEXIS 4028
CourtCourt of Appeals for the Second Circuit
DecidedJuly 22, 1935
DocketNo. 442
StatusPublished
Cited by6 cases

This text of 79 F.2d 102 (Potts v. Village of Haverstraw) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Potts v. Village of Haverstraw, 79 F.2d 102, 1935 U.S. App. LEXIS 4028 (2d Cir. 1935).

Opinion

L. HAND, Circuit Judge.

The plaintiff, a civil engineer, skilled in designing and building municipal waterworks, sued the village of llaverstraw, New York, upon a contract made by its board of trustees employing him to design and supervise the construction of a system of waterworks for the village. Under the New York law (sections 520-529, N. Y. Conservation Law [Consol. Laws, c. 65]), the village must get the approval of the Water Power and Conlrol Commission of the state, and this the trustees started a proceeding to procure; but a succeeding board failed to press it and finally discontinued it, and repudiated the contract. The plaintiff, who had prepared the plans in full and had delivered them to the village, sued on the theory that the abandonment of the project was a breach entitling him to loss of profits. The village answered and moved to dismiss the complaint which the court denied. At the trial which followed, the judge directed a verdict for the plaintiff except as to damages, which the jury found in the sum of about $17,000. The defendant appealed from the judgment so entered.

The plaintiff promised to perform four different kinds of services; first, “to submit * * * complete working plans * * * required to place the construction of said water system under contract.” This meant to carry them so far with all incidental “surveys, investigations * * * plates, plans, profiles arid details,” that the contractors could directly estimate upon them. Some of this work, or similar work, had to be done, or at least it was reasonable to do, before the trustees decided whether to build new waterworks, or to keep on with the private system. They had to inform themselves about the chances of bettering the supply, the cost of the proposed work and so on. But some would seem to have been unnecessary until the new waterworks were finally approved by all necessary authorities; for instance, we do not see why, in order to enable the trustees to make up their minds, working plans and specifications need be prepared adequate “to place the construction of said system under contract.” Second, the plaintiff was “to prepare all necessary engineering papers” in the proceeding which the trustees must prosecute before the state commission in order to get its approval. Section 521, N. Y. Conservation Law. Not only was the plaintiff to do this, but he was to attend the hearings and help the village attorney, so far as an engineer could. Those services were of course to be rendered before the enterprise had been finally authorized; were indeed part of the effort to get authorization. Third, he was to do the usual work of supervision as the waterworks were being built; that is, “to locate * * * for the contractor * * * the various lines * * * to furnish all grades and engineering information * * * to inspect * * * all materials * * * and to submit estimates of the work done.” That of course must, all take place after the work was under way. Last, when the whole thing was completed, in order to help its operation he was “to prepare * * * a set of record plans show[104]*104ing the construction that has been done * * * also * * * to furnish * * * suggested ordinance governing the operation of the water system * * * also * * * a suggested schedule of rates * * * and * * * system of accounting.” In return for all these services the trustees promised to pay him “seven per cent, of the cost of said work * * * as indicated by the amounts paid on each separate contract”; these payments not being allocated among the four classes of service. If the project did not go through, he was in any event to get $800 as the cost of preparing plans. It will thus appear, since the defendant’s promise was indivisible, that if the trustees had no power to employ the plaintiff to supervise the work, or to make “record plans,” ordinances and a rate schedule, or to prepare more plans and specifications than were necessary to advise them and to present their case to the commission, their promise did not create any contract at all. They had no power to pay for what they had no power to' demand. The plaintiff might be able to sue on a common count for labor and services, but he could not recover damages.

The contract was executed on July 2, 1928, and two weeks later the trustees appointed a village water board to take over construction, with which on August 8, 1928, the plaintiff filed a full set of complete plans and estimates, presumably ready to be submitted to the contractors. On September twentieth the electors of the village ratified a resolution of the trustees, passed on September fourth, authorizing the construction of such a water supply at an expense of $450,000 to be raised by a bond issue; and on January 5, 1929, the trustees filed with the state commission their petition for approval, to which they attached the plans. One hearing was held on February 14, 1929, but the old board was superseded at an election on April first, and the whole enterprise'was abandoned by a resolution of the new board on December 15, 1930, which the voters ratified in the following month.

By section 128-a of the N. Y. Village Law (Consol. Laws, „c. 64) “no contract shall be made involving an expenditure by the village unless the money therefor has previously-been estimated by the board of trustees as necessary to be raised during the then fiscal year, or unless a resolution to borrow money on bonds or other obligations of the village has been adopted by the board of trustees as provided in this chapter or if required by this chapter that the a.ction or resolution of the board of trustees be approved by the electors, then by such approval.” This was intended to forbid villages to contract obligations without providing the means of payment; the Court of Appeals in Kelly v. Merry, 262 N. Y. 151, 186 N. E. 425, supported the contract then before them only on the theory that it did not pledge the village’s credit. When the section applies two courses are open; the money may be “previously estimated by the board of trustees as necessary to be raised during the fiscal year.” Nothing of the sort was done in the case at bar, except that the budget for 1928 contained an item- of $8,000 appropriated to “miscellaneous expenses.” The trustees adopted the second course and indeed had to do so for the authorized cost, $450,000, could not have been raised in “the then fiscal year.” The defendant questions the regularity of the submission to the electors of- the trustees’ resolution, but the criticism is trivial. On the motion to dismiss, the judge concluded that the contract did not “involve an expenditure,” and was not within section 128-a. We think otherwise; it is enough that the village would have to pay seven per cent, of the estimated cost, if the work' went through. That payment would be an “expenditure”; the contract “involved it,” and was therefore invalid at least until September 20, 1928, except in so far as it could depend upon the appropriation of $8,000. Such an appropriation would not support it; the system of village finance set up by sections 110-112 of the N. Y. Village Law precluded such loose methods. By section 110 the mayor must prepare “an itemized statement in writing of the estimated revenues and expenditures,” which must contain “an estimate of the several amounts * * * necessary to provide for j;he expenses of conducting the business of the village in each board, department and office thereof and for the various purposes contemplated by this chapter and otherwise by law for the fiscal year.” The board of trustees then considers this “estimate and tentative budget” and must “prepare a budget” which becomes such by its vote, section 111.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Potts v. Village of Haverstraw
93 F.2d 506 (Second Circuit, 1937)
Moss v. United States
72 F.2d 30 (Fourth Circuit, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
79 F.2d 102, 1935 U.S. App. LEXIS 4028, Counsel Stack Legal Research, https://law.counselstack.com/opinion/potts-v-village-of-haverstraw-ca2-1935.