Potts v. Village of Haverstraw

79 F.2d 102, 1935 U.S. App. LEXIS 4028
Court of Appeals for the Second Circuit·Decided July 22, 1935·No. No. 442·Published·Cited by 6 cases

Opinion

L. HAND, Circuit Judge.

The plaintiff, a civil engineer, skilled in designing and building municipal waterworks, sued the village of llaverstraw, New York, upon a contract made by its board of trustees employing him to design and supervise the construction of a system of waterworks for the village. Under the New York law (sections 520-529, N. Y. Conservation Law [Consol. Laws, c. 65]), the village must get the approval of the Water Power and Conlrol Commission of the state, and this the trustees started a proceeding to procure; but a succeeding board failed to press it and finally discontinued it, and repudiated the contract. The plaintiff, who had prepared the plans in full and had delivered them to the village, sued on the theory that the abandonment of the project was a breach entitling him to loss of profits. The village answered and moved to dismiss the complaint which the court denied. At the trial which followed, the judge directed a verdict for the plaintiff except as to damages, which the jury found in the sum of about $17,000. The defendant appealed from the judgment so entered.

The plaintiff promised to perform four different kinds of services; first, “to submit * * * complete working plans * * * required to place the construction of said water system under contract.” This meant to carry them so far with all incidental “surveys, investigations * * * plates, plans, profiles arid details,” that the contractors could directly estimate upon them. Some of this work, or similar work, had to be done, or at least it was reasonable to do, before the trustees decided whether to build new waterworks, or to keep on with the private system. They had to inform themselves about the chances of bettering the supply, the cost of the proposed work and so on. But some would seem to have been unnecessary until the new waterworks were finally approved by all necessary authorities; for instance, we do not see why, in order to enable the trustees to make up their minds, working plans and specifications need be prepared adequate “to place the construction of said system under contract.” Second, the plaintiff was “to prepare all necessary engineering papers” in the proceeding which the trustees must prosecute before the state commission in order to get its approval. Section 521, N. Y. Conservation Law. Not only was the plaintiff to do this, but he was to attend the hearings and help the village attorney, so far as an engineer could. Those services were of course to be rendered before the enterprise had been finally authorized; were indeed part of the effort to get authorization. Third, he was to do the usual work of supervision as the waterworks were being built; that is, “to locate * * * for the contractor * * * the various lines * * * to furnish all grades and engineering information * * * to inspect * * * all materials * * * and to submit estimates of the work done.” That of course must, all take place after the work was under way. Last, when the whole thing was completed, in order to help its operation he was “to prepare * * * a set of record plans show[104] ing the construction that has been done * * * also * * * to furnish * * * suggested ordinance governing the operation of the water system * * * also * * * a suggested schedule of rates * * * and * * * system of accounting.” In return for all these services the trustees promised to pay him “seven per cent, of the cost of said work * * * as indicated by the amounts paid on each separate contract”; these payments not being allocated among the four classes of service. If the project did not go through, he was in any event to get $800 as the cost of preparing plans. It will thus appear, since the defendant’s promise was indivisible, that if the trustees had no power to employ the plaintiff to supervise the work, or to make “record plans,” ordinances and a rate schedule, or to prepare more plans and specifications than were necessary to advise them and to present their case to the commission, their promise did not create any contract at all. They had no power to pay for what they had no power to' demand. The plaintiff might be able to sue on a common count for labor and services, but he could not recover damages.

The contract was executed on July 2, 1928, and two weeks later the trustees appointed a village water board to take over construction, with which on August 8, 1928, the plaintiff filed a full set of complete plans and estimates, presumably ready to be submitted to the contractors. On September twentieth the electors of the village ratified a resolution of the trustees, passed on September fourth, authorizing the construction of such a water supply at an expense of $450,000 to be raised by a bond issue; and on January 5, 1929, the trustees filed with the state commission their petition for approval, to which they attached the plans. One hearing was held on February 14, 1929, but the old board was superseded at an election on April first, and the whole enterprise'was abandoned by a resolution of the new board on December 15, 1930, which the voters ratified in the following month.

Free access — add to your briefcase to read the full text and ask questions with AI

Potts v. Village of Haverstraw, 79 F.2d 102, 1935 U.S. App. LEXIS 4028 (2d Cir. 1935).

79 F.2d 102 (Potts v. Village of Haverstraw) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Potts v. Village of Haverstraw
93 F.2d 506 (Second Circuit, 1937)
Moss v. United States
72 F.2d 30 (Fourth Circuit, 1934)