Potter v. Dundee Hydraulic Power Co.

165 N.W. 689, 198 Mich. 585, 1917 Mich. LEXIS 916
CourtMichigan Supreme Court
DecidedDecember 27, 1917
DocketDocket No. 90
StatusPublished

This text of 165 N.W. 689 (Potter v. Dundee Hydraulic Power Co.) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Potter v. Dundee Hydraulic Power Co., 165 N.W. 689, 198 Mich. 585, 1917 Mich. LEXIS 916 (Mich. 1917).

Opinion

Steere, J.

Plaintiffs, who are husband and wife, have owned and occupied for more than 20 years an 80-acre farm located upon the north side of the river Raisin about one-half mile up stream and westerly from defendant’s, dam across said river at the village of Dundee, Monroe county. Approximately one-half of this farm is upland and the remainder flats, or bottom land, along the north bank of the river which plaintiff claims was especially fertile and productive farming land, subject to overflow only in the time of spring freshets, and which he tilled successfully until defendant erected a new and higher dam of concrete in the summer of 1911, raising the level of its millpond and flooding his lowland. This bill was filed in February, 1912, to restrain defendant from maintaining this dam at a higher level than the one it replaced, [587]*587and to perpetually enjoin defendant from flooding plaintiff’s land to any greater extent than had been done by preceding dams erected upon the same site.

It was shown that as early as 1827 a tract of 120 acres of land upon which the dam in question is located was conveyed by the then owner to defendant’s predecessors in title, requiring the grantees “to construct a good, substantial, and firm dam across the river Raisin at the best point on the said river on said premises, where they can get the neatest head and fall, and also to construct, excavate, and build a good and sufficient race,” etc.

Tradition, supplemented by the testimony of living witnesses, shows that a dam of some kind and height has been maintained since that time at the point where the grantees then decided they could '“get the neatest head and fall.” No flowage privileges were ever acquired by defendant or its grantors from upstream owners, and beyond the limits of the land first acquired what rights defendant has are by prescription.

During the intervening years age, freshets, and ice floes from time to time made imperative frequent re-, pairs and occasional reconstruction of the dam maintained at this site. According to the memory of the oldest inhabitant, running back some 70 years, the first dam was known as a brush dam, later repaired and reconstructed with logs and known as “a log dam,” as early as 1846, which was washed out in whole or in part and rebuilt or repaired occasionally, but retaining that character and name until some time between 1897 and 1900, after being wrecked by a flood, it was restored or rebuilt by its then owner, Mr. Davis, in a more substantial manner, and thereafter known as a “timber” or “rafter.dam.” This work was done by or under the supervision of a witness named Edwards, who was running the mill, and in charge of the property for Davis. He testified that he was there in [588]*588Davis’ employ 20 or 21 years, “had everything to do with it while there,” and built the “new” or rafter dam about 2 years before he went to Detroit, where he had lived 14 or 15 years. He described the old dam as a “wooden crib dam, made of wood, logs, plank, and dirt.” He testified that he measured and intended to build the new dam the same height as the one it replaced. It experienced similar vicissitudes as had its predecessors, requiring frequent repairs, or reconstruction, but was maintained and in use until defendant acquired the property, and the cement dam was constructed according to the plans and under supervision of an engineer who testified to surveys, measurements, photographs, etc., of the old and new dams tending to show that the height had not been increased, and the elevation at the spillway formerly enjoyed by Davis and his predecessors was not exceeded.

After this bill was filed the north end of the new cement dam, built during the summer, washed out, and in October, 1912, plaintiffs obtained a temporary injunction restraining construction of the portion carried away at the height proposed, but upon defendant filing a bond to meet any damages which plaintiffs might recover the dam was permitted to be restored to its former height.

The case was heard in the fall of 1914, and findings were made by the trial court in which the evidence is reviewed and the conclusion reached that the present dam is in fact and effect much higher than former dams, that plaintiffs had suffered damages therefrom amounting to $840 up to the time of the finding, which was adjudicated against defendant, and a mandatory injunction granted requiring the present dam to—

“be cut down 2 feet from the top of the wing, measuring from the top of the wing at the south end of the timber on the north stone wall, and that this dam [589]*589be so cut down from the north end to within 50 feet of the flume. This remaining 50 feet may be continued as it is. The headgates in the flume shall not be maintained at any greater "height than that portion of the dam shall be after cutting it back 2 feet.”

The principles of law applicable to this controversy are well settled and not in dispute. It is conceded by plaintiffs that defendant has a prescriptive right to maintain adjacent to their land as high a level of backwater as resulted from the old dam, or dams, and to overflow their flats to the same extent. If the new dam does no more, they cannot complain of the burden. It is conceded by defendant that it cannot place an additional servitude upon the upstream shore lands by raising the level of the backwater either through constructing a higher dam or an absolutely tight dam if the former one maintained during the period of limitation was so imperfect or leaky as to regularly allow water to go through it instead of over its crest, thus failing to fully impound the water and maintain a level of which it would be capable if more perfectly constructed and kept tight against leakage. The settled law in this case is abundantly discussed and defined in White v. Forbes, Walk. Ch. 112; Turner v. Hart, 71 Mich. 128 (38 N. W. 890, 15 Am. St. Rep. 243); Miller v. Bank of Belleville, 148 Mich. 339 (111 N. W. 1062); Sheffield Car Co. v. Hydraulic Co., 171 Mich. 423 (137 N. W. 305, Am. & Eng. Ann. Cas. 1914B, 984); Brockway v. Power & Light Co., 175 Mich. 339 (141 N. W. 693).

It is apparently undisputed that this dam, as were its predecessors, is about 400 feet long, extending nearly north and south across the Raisin river and its adjacent flats to the higher land, or “banks,” on either side. The mill and flume are at its south end, on the south side of the river, connected with the pond by a raceway extending from the flume northwesterly [590]*590into the impounded water above the dam. The only suggestion of the power developed by any of the dams is found in the testimony of a witness named Pulver, who had lived his life of 67 years in the vicinity of the dam, and was called as a witness by defendant. He testified:

That more horse' power was used in the “old times than now”; that “the paper mill used 60, the turning mill 15, and the sawmill 25, making about 100 horse power. The sawmill at times ran from 25 to 30 horse power. It did not have a good wheel. * * * There was power enough to run all these six months in the year, perhaps not so much sometimes; some years it was quite a bit less. * * * In dry weather all these mills could not run continuously.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Turner v. Hart
38 N.W. 890 (Michigan Supreme Court, 1888)
Miller v. Bank of Belleville
111 N.W. 1062 (Michigan Supreme Court, 1907)
Sheffield Car Co. v. Constantine Hydraulic Co.
137 N.W. 305 (Michigan Supreme Court, 1912)
Brockway v. Hydraulic Power & Light Co.
141 N.W. 693 (Michigan Supreme Court, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
165 N.W. 689, 198 Mich. 585, 1917 Mich. LEXIS 916, Counsel Stack Legal Research, https://law.counselstack.com/opinion/potter-v-dundee-hydraulic-power-co-mich-1917.