Potelco, Inc. & Jeff Lampman v. L&i

CourtCourt of Appeals of Washington
DecidedJanuary 9, 2018
Docket49716-6
StatusUnpublished

This text of Potelco, Inc. & Jeff Lampman v. L&i (Potelco, Inc. & Jeff Lampman v. L&i) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Potelco, Inc. & Jeff Lampman v. L&i, (Wash. Ct. App. 2018).

Opinion

Filed Washington State Court of Appeals Division Two

January 9, 2018 IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

DIVISION II POTELCO, INC.; JEFF LAMPMAN, No. 49716-6-II

Appellants,

v.

WASHINGTON STATE DEPARTMENT OF LABOR AND INDUSTRIES, UNPUBLISHED OPINION

Respondent.

WORSWICK, P.J. — The Department of Labor and Industries issued Potelco Inc. a citation

for violating an electricians and electrical installations regulation. Specifically, the citation

alleged that Potelco failed to comply with WAC 296-46B-901(9)(a), which requires that an

electrical contractor request an inspection after the contractor completes or energizes an

electrical project. The Department also issued a citation to Potelco’s site administrator, Jeff

Lampman, for failing to comply with RCW 19.28.061(5)(b), which requires that a site

administrator ensure all electrical work complies with the electrical laws and rules of the State.

Potelco and Lampman now appeal the superior court’s order affirming the Washington State

Electrical Board’s decision affirming the Department’s citation and penalty assessment.

Potelco and Lampman argue that (1) the Board’s order is not supported by substantial

evidence, (2) Lampman did ensure compliance as required under RCW 19.28.061(5)(b), and (3)

the Board’s affirmation of Lampman’s citation improperly transformed RCW 19.28.061(5)(b)

into a strict liability statute. We affirm the Board’s order. No. 49716-6-II

FACTS

I. BACKGROUND

The White River School District hired Potelco to replace underground power cables at a

school in Buckley. The project required Potelco to install high-voltage wires between a utility

pole and the school’s transformer. This type of project required a permit from the Department of

Labor and Industries and also required a final inspection by a Department inspector to ensure

compliance with the National Electrical Code and related Washington statutes and Department

regulations.

On July 17, 2013, while Potelco’s crew worked to complete the installation project,

Department inspector John Boespflug was in the area on other business. After seeing a Potelco

truck parked behind the school, Boespflug decided that it would “be a good time to go over [to

the work site].” Clerk’s Papers (CP) at 45. The installation was not complete because the

Potelco crew had not installed connectors to the high-voltage wires to connect them to the

transformer. Boespflug spoke to the linemen at the work site and told them that “everything

looked good.” CP at 583. Potelco’s crew did not energize or complete the project while

Boespflug was at the site, but the crew energized the project the next day.

In October 2013, Boespflug reviewed the Department records to see if Potelco had

requested a final inspection for the project and discovered that Potelco had not. Boespflug then

called Lampman and informed him that Potelco needed to request an inspection for the project.

Potelco then requested a final inspection, and Boespflug later gave final approval on the project.

The Department subsequently issued Potelco a citation for failing to request an inspection

within three business days after completion of the installation or within one day after energizing

2 No. 49716-6-II

the project pursuant to WAC 296-46B-901(9)(a).1 The citation included a penalty in the amount

of $250. The Department also issued Lampman, as the administrator, a citation for failing to

ensure that Potelco complied with the electrical laws of Washington State pursuant to

RCW19.28.061(5)(b).2 Lampman’s citation included a penalty in the amount of $100.

II. PROCEDURAL AND ADMINISTRATIVE HISTORY

Potelco and Lampman appealed the citations to the Office of Administrative Hearings

(OAH). The issues before the OAH were whether Potelco failed to request an inspection within

three business days after completion of the installation or one business day after energizing,

whichever occurred first, as required by WAC 296-46B-901(9)(a), and whether Lampman failed

to ensure all electrical work complied with the electrical laws and rules of the State, as required

by RCW19.28.064(5)(b).

An OAH administrative law judge (ALJ) held a hearing on the matter. Boespflug,

Lampman, Potelco manager John Gower, foreman Mark Langberg, and lineman Kevin Hudson,

among others, testified at the hearing. Glen Thomas, an employee of Potelco who had obtained

the initial permit for the project, did not testify.

1 WAC 296-46B-901(9)(a) provides: (9) Requests for inspections. (a) Requests for inspections must be made no later than three business days after completion of the electrical/telecommunications installation or one business day after any part of the installation has been energized, whichever occurs first. 2 RCW 19.28.061(5)(b) provides: (5) The designated master electrician or administrator shall: (b) Ensure that all electrical work complies with the electrical installation laws and rules of the state.

3 No. 49716-6-II

Boespflug testified that he “expected” that the Potelco crew would complete the project

on the day he was at the work site. CP at 583. Boespflug also testified that he told the crew that

they needed to make sure the project was “called in and requested for inspection.” CP at 583.

Boespflug testified that if he had completed an inspection the day he went to the work site, the

permit would have been signed off and the electronic system would reflect that he had conducted

an inspection. Boespflug stated that he did not complete any documentation at the work site the

day he was there because the project was not complete and because he had not received

information as to whether the connectors Potelco was using were appropriate. Boespflug further

testified that he did not know of any statute or regulation that allows a final inspection to be

conducted when a project is “almost completed” and that the law is very specific and required

that a request for inspection be made when the project is complete. CP at 665.

Langberg testified that the project was completed within an hour of Boespflug being at

the work site. Langberg also stated that it was his understanding that Boespflug conducted an

inspection while he was at the site. Langberg testified that he personally did not call in any

inspection but that it was his assumption that Thomas was the person who would have called.

Langberg added that he did not recall if Boespflug informed the crew that they needed to request

an inspection.

Hudson testified that Boespflug told the crew that they could “heat up the wire” which

Hudson interpreted to mean that the crew could energize the wires. CP at 635. Hudson also

testified that he assumed Boespflug was there for an inspection and that he personally did not

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Snohomish County v. Hinds
810 P.2d 84 (Court of Appeals of Washington, 1991)
Clausing v. State
955 P.2d 394 (Court of Appeals of Washington, 1998)
West v. Thurston County
275 P.3d 1200 (Court of Appeals of Washington, 2012)
HomeStreet, Inc. v. STATE, DEPT. OF REVENUE
210 P.3d 297 (Washington Supreme Court, 2009)
State v. Torres
212 P.3d 573 (Court of Appeals of Washington, 2009)
Harrison Memorial Hosp. v. Gagnon
40 P.3d 1221 (Court of Appeals of Washington, 2002)
Harold Bircumshaw v. State Of Washington, Health Care Authority
380 P.3d 524 (Court of Appeals of Washington, 2016)
State v. K.L.B.
328 P.3d 886 (Washington Supreme Court, 2014)
National Electrical Contractors Ass'n v. Riveland
978 P.2d 481 (Washington Supreme Court, 1999)
HomeStreet, Inc. v. Department of Revenue
166 Wash. 2d 444 (Washington Supreme Court, 2009)
State v. Budik
272 P.3d 816 (Washington Supreme Court, 2012)
Harrison Memorial Hospital v. Gagnon
110 Wash. App. 475 (Court of Appeals of Washington, 2002)
Mid Mountain Contractors, Inc. v. Department of Labor & Industries
146 P.3d 1212 (Court of Appeals of Washington, 2006)
J&S Services, Inc. v. Department of Labor & Industries
174 P.3d 1190 (Court of Appeals of Washington, 2007)
State v. Torres
151 Wash. App. 378 (Court of Appeals of Washington, 2009)
Pilchuck Contractors, Inc. v. Department of Labor & Industries
286 P.3d 383 (Court of Appeals of Washington, 2012)
Estate of Nelson v. Department of Labor & Industries
308 P.3d 686 (Court of Appeals of Washington, 2013)
Ainsworth v. Progressive Casualty Insurance
322 P.3d 6 (Court of Appeals of Washington, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Potelco, Inc. & Jeff Lampman v. L&i, Counsel Stack Legal Research, https://law.counselstack.com/opinion/potelco-inc-jeff-lampman-v-li-washctapp-2018.