Potelco, Inc. & Jeff Lampman v. L&i

Court of Appeals of Washington·Decided January 9, 2018·No. 49716-6·Unpublished

Opinion

Filed

Washington State

Court of Appeals

Division Two

January 9, 2018

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

DIVISION II

POTELCO, INC.; JEFF LAMPMAN, No. 49716-6-II

Appellants,

v.

WASHINGTON STATE DEPARTMENT OF LABOR AND INDUSTRIES, UNPUBLISHED OPINION

Respondent.

WORSWICK, P.J. — The Department of Labor and Industries issued Potelco Inc. a citation for violating an electricians and electrical installations regulation. Specifically, the citation alleged that Potelco failed to comply with WAC 296-46B-901(9)(a), which requires that an electrical contractor request an inspection after the contractor completes or energizes an electrical project. The Department also issued a citation to Potelco’s site administrator, Jeff Lampman, for failing to comply with RCW 19.28.061(5)(b), which requires that a site administrator ensure all electrical work complies with the electrical laws and rules of the State. Potelco and Lampman now appeal the superior court’s order affirming the Washington State Electrical Board’s decision affirming the Department’s citation and penalty assessment.

Potelco and Lampman argue that (1) the Board’s order is not supported by substantial evidence, (2) Lampman did ensure compliance as required under RCW 19.28.061(5)(b), and (3) the Board’s affirmation of Lampman’s citation improperly transformed RCW 19.28.061(5)(b) into a strict liability statute. We affirm the Board’s order.

FACTS

I. BACKGROUND

The White River School District hired Potelco to replace underground power cables at a school in Buckley. The project required Potelco to install high-voltage wires between a utility pole and the school’s transformer. This type of project required a permit from the Department of Labor and Industries and also required a final inspection by a Department inspector to ensure compliance with the National Electrical Code and related Washington statutes and Department regulations.

On July 17, 2013, while Potelco’s crew worked to complete the installation project, Department inspector John Boespflug was in the area on other business. After seeing a Potelco truck parked behind the school, Boespflug decided that it would “be a good time to go over [to the work site].” Clerk’s Papers (CP) at 45. The installation was not complete because the Potelco crew had not installed connectors to the high-voltage wires to connect them to the transformer. Boespflug spoke to the linemen at the work site and told them that “everything looked good.” CP at 583. Potelco’s crew did not energize or complete the project while Boespflug was at the site, but the crew energized the project the next day.

In October 2013, Boespflug reviewed the Department records to see if Potelco had requested a final inspection for the project and discovered that Potelco had not. Boespflug then called Lampman and informed him that Potelco needed to request an inspection for the project. Potelco then requested a final inspection, and Boespflug later gave final approval on the project.

The Department subsequently issued Potelco a citation for failing to request an inspection within three business days after completion of the installation or within one day after energizing

the project pursuant to WAC 296-46B-901(9)(a).1 The citation included a penalty in the amount of $250. The Department also issued Lampman, as the administrator, a citation for failing to ensure that Potelco complied with the electrical laws of Washington State pursuant to RCW19.28.061(5)(b).2 Lampman’s citation included a penalty in the amount of $100.

II. PROCEDURAL AND ADMINISTRATIVE HISTORY Potelco and Lampman appealed the citations to the Office of Administrative Hearings (OAH). The issues before the OAH were whether Potelco failed to request an inspection within three business days after completion of the installation or one business day after energizing, whichever occurred first, as required by WAC 296-46B-901(9)(a), and whether Lampman failed to ensure all electrical work complied with the electrical laws and rules of the State, as required by RCW19.28.064(5)(b).

An OAH administrative law judge (ALJ) held a hearing on the matter. Boespflug, Lampman, Potelco manager John Gower, foreman Mark Langberg, and lineman Kevin Hudson, among others, testified at the hearing. Glen Thomas, an employee of Potelco who had obtained the initial permit for the project, did not testify.

1 WAC 296-46B-901(9)(a) provides:

(9) Requests for inspections.

(a) Requests for inspections must be made no later than three business days after completion of the electrical/telecommunications installation or one business day after any part of the installation has been energized, whichever occurs first.

2 RCW 19.28.061(5)(b) provides:

(5) The designated master electrician or administrator shall:

(b) Ensure that all electrical work complies with the electrical installation laws and rules of the state.

Boespflug testified that he “expected” that the Potelco crew would complete the project on the day he was at the work site. CP at 583. Boespflug also testified that he told the crew that they needed to make sure the project was “called in and requested for inspection.” CP at 583. Boespflug testified that if he had completed an inspection the day he went to the work site, the permit would have been signed off and the electronic system would reflect that he had conducted an inspection. Boespflug stated that he did not complete any documentation at the work site the day he was there because the project was not complete and because he had not received information as to whether the connectors Potelco was using were appropriate. Boespflug further testified that he did not know of any statute or regulation that allows a final inspection to be conducted when a project is “almost completed” and that the law is very specific and required that a request for inspection be made when the project is complete. CP at 665.

Langberg testified that the project was completed within an hour of Boespflug being at the work site. Langberg also stated that it was his understanding that Boespflug conducted an inspection while he was at the site. Langberg testified that he personally did not call in any inspection but that it was his assumption that Thomas was the person who would have called. Langberg added that he did not recall if Boespflug informed the crew that they needed to request an inspection.

Hudson testified that Boespflug told the crew that they could “heat up the wire” which Hudson interpreted to mean that the crew could energize the wires. CP at 635. Hudson also testified that he assumed Boespflug was there for an inspection and that he personally did not call in for the inspection and did not know if anyone else called in for an inspection.

Lampman testified as to his role as site administrator, and explained that he was responsible for ensuring that the company complies with all the rules and regulations of electrical laws. Lampman stated that he ensures that Potelco complies with electrical laws by offering training sessions for employees and by forwarding electrical newsletters by e-mail to managers about rule and regulation changes. Lampman also testified that he reviewed contracts for Potelco’s projects as part of his duties. Lampman agreed that it was a requirement that an entity that obtains a permit for electrical work must also request an inspection upon completion of the work.

Lampman then explained that after a project’s completion, he sometimes requests an inspection and at other times it is the person who obtained the permit for the project who requests an inspection. Lampman testified that sometimes he contacts the person who obtained the permit to get a verbal confirmation that the request for inspection had been made, but at other times he simply “trust[s]” that the person who obtained the permit also requested final inspection. CP at 654.

Free access — add to your briefcase to read the full text and ask questions with AI

Potelco, Inc. & Jeff Lampman v. L&i, (Wash. Ct. App. 2018).

Potelco, Inc. & Jeff Lampman v. L&i (Potelco, Inc. & Jeff Lampman v. L&i) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Snohomish County v. Hinds
810 P.2d 84 (Court of Appeals of Washington, 1991)
Clausing v. State
955 P.2d 394 (Court of Appeals of Washington, 1998)
West v. Thurston County
275 P.3d 1200 (Court of Appeals of Washington, 2012)
HomeStreet, Inc. v. STATE, DEPT. OF REVENUE
210 P.3d 297 (Washington Supreme Court, 2009)
State v. Torres
212 P.3d 573 (Court of Appeals of Washington, 2009)
Harrison Memorial Hosp. v. Gagnon
40 P.3d 1221 (Court of Appeals of Washington, 2002)
Harold Bircumshaw v. State Of Washington, Health Care Authority
380 P.3d 524 (Court of Appeals of Washington, 2016)
State v. K.L.B.
328 P.3d 886 (Washington Supreme Court, 2014)
National Electrical Contractors Ass'n v. Riveland
978 P.2d 481 (Washington Supreme Court, 1999)
HomeStreet, Inc. v. Department of Revenue
166 Wash. 2d 444 (Washington Supreme Court, 2009)
State v. Budik
272 P.3d 816 (Washington Supreme Court, 2012)
Harrison Memorial Hospital v. Gagnon
110 Wash. App. 475 (Court of Appeals of Washington, 2002)
Mid Mountain Contractors, Inc. v. Department of Labor & Industries
146 P.3d 1212 (Court of Appeals of Washington, 2006)
J&S Services, Inc. v. Department of Labor & Industries
174 P.3d 1190 (Court of Appeals of Washington, 2007)
State v. Torres
151 Wash. App. 378 (Court of Appeals of Washington, 2009)
Pilchuck Contractors, Inc. v. Department of Labor & Industries
286 P.3d 383 (Court of Appeals of Washington, 2012)
Estate of Nelson v. Department of Labor & Industries
308 P.3d 686 (Court of Appeals of Washington, 2013)
Ainsworth v. Progressive Casualty Insurance
322 P.3d 6 (Court of Appeals of Washington, 2014)