Posh Construction, Inc. v. Simmons & Greer, Inc.

436 A.2d 1192, 292 Pa. Super. 142, 1981 Pa. Super. LEXIS 3636
CourtSuperior Court of Pennsylvania
DecidedOctober 30, 1981
Docket2903
StatusPublished
Cited by6 cases

This text of 436 A.2d 1192 (Posh Construction, Inc. v. Simmons & Greer, Inc.) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Posh Construction, Inc. v. Simmons & Greer, Inc., 436 A.2d 1192, 292 Pa. Super. 142, 1981 Pa. Super. LEXIS 3636 (Pa. Ct. App. 1981).

Opinion

MONTGOMERY, Judge:

The Appellant in the instant case 1 is one of the original defendants, Maryland Casualty Company (hereinafter referred to as “Maryland Casualty”). The case was tried in the lower court before a jury, which returned a verdict for the plaintiff against Maryland Casualty, and verdicts in favor of the other original defendant and the additional defendant. Maryland Casualty filed a motion for judgment n. o. v., or in. the alternative, for a new trial. The lower court granted a new trial, but Maryland Casualty has filed the instant appeal, claiming that it was entitled to judgment n. o. v.

It is well-established that when a motion for judgment n. o. v. or a new trial is filed, and the lower court grants the new trial but denies the judgment n. o. v., the appellate court is limited to a determination of whether there has been an abuse of discretion by the lower court. Ellerbe v. Steinman, 162 Pa.Super. 440, 58 A.2d 202 (1948); Standard Oil Company of New Jersey v. Graham Oil Transport Corp., 157 Pa.Super. 41, 41 A.2d 414 (1945). However, if the record clearly establishes that the moving party was *145 entitled to judgment n. o. v., the grant of a new trial in such circumstances may be found to have been an abuse of discretion on the part of the lower court. See Matevish v. School District of Borough of Ramey, 167 Pa.Super. 313, 74 A.2d 797 (1950), where there were no factual issues for determination by a jury. Further, we must be mindful that judgment n. o. v. will be entered only in a clear case, when the facts are such that no two reasonable persons could fail to agree that the verdict was improper, and any doubts should be resolved in favor of the verdict. See Atkins v. Urban Redevelopment Authority of Pittsburgh, 489 Pa. 344, 414 A.2d 100 (1980); Broxie v. Household Finance Co., 472 Pa. 373, 372 A.2d 741 (1977); Bottorf v. Waltz, 245 Pa.Super. 139, 369 A.2d 332 (1976). In the resolution of this appeal, we must consider the evidence available to the lower court in the light most favorable to the verdict winner, giving it the benefit of every reasonable inference of fact arising therefrom, and we must resolve any conflict in evidence in the favor of the verdict winner. See Broxie v. Household Finance Company, supra.

Viewing the evidence in that light, the record shows that the defendant Simmons & Greer, Inc. (hereinafter referred to as “Simmons”) was a general contractor for various building projects. In late January, 1969 Simmons entered into a contract with the General State Authority for the erection of a gymnasium at Kutztown State College in Berks County. Pursuant to the Public Works Contractors Bond Law 2 , Simmons obtained performance and payment bonds for the project, from Maryland Casualty. During the course of the project, Simmons entered into a contract with Simpson Steel Products Company, Inc. 3 (hereinafter referred to as “Simpson”), for certain work on the project. In turn, Simpson hired the plaintiff, Posh Construction, Inc. (herein *146 after referred to as “Posh”), to furnish labor, materials, and equipment to Simpson for the project. Thereafter, the Plaintiff commenced work on the gymnasium construction in September, 1969. Posh submitted an initial bill to Simpson for partial work completed on the project and Simpson paid the bill by check. However, the Plaintiff’s next billing to Simpson was not paid and Posh approached the general contractor, Simmons, about the problem. Posh did this by orally notifying the Simmons’ field superintendent at the construction site that it would not continue on the job unless it was paid, as Simpson had not made a payment for work completed to that date, in accordance with the second billing by Posh. Thereafter, a representative of the plaintiff was summoned to Simmons’ home office in Philadelphia. At that time, Posh’s representative received a check from Simmons in the amount of just over $11,000.00, which check was made payable to both Simpson and Posh as co-payees. The Posh representative obtained appropriate signatures on the check from Simpson and deposited the proceeds of the check in its own account. As the work progressed further, Simmons issued another check for almost $21,000.00, in identical circumstances, for the benefit of the plaintiff. In the instant action, Posh claimed a balance due of just over $14,-000.00, representing both the final payment on its work for Simpson on the project, and also including several hundred dollars for work performed directly at the request of Simpson, which work was not covered by plaintiff’s contract with Simpson.

The plaintiff filed the instant action claiming it supplied its labor, material and equipment in reliance upon Simmons’ promise to pay any debts of Simpson to the plaintiff in connection with the project. The plaintiff claimed that Maryland Casualty was liable to it under Simmons’ payment bond, and in that regard, the plaintiff’s claims were based upon its rights under the Public Works Contractors Bond Law of 1967. In describing the types of bonds required, that Act in § 3(a)(2) [8 P.S. § 193(a)(2)] states that a payment bond “. . . shall be solely for the protection of claimants *147 supplying labor or materials to the prime contractor to whom the contract was awarded, or to any of his subcontractors, in the prosecution of the work provided for in such contract, and shall be conditioned for the prompt payment of all such material furnished or labor supplied or performed in the prosecution of the work.” Further, § 4(b) [8 P.S. § 194(b)] is particularly relevant to the issues presented in this case, and provides:

Any claimant who has a direct contractual relationship with any subcontractor of the prime contractor who gave such payment bond but has no contractual relationship, express or implied, with such prime contractor may bring an action on the payment bond only if he has given written notice to such contractor within ninety days from the date on which the claimant performed the last of the labor or furnished the last of the materials for which he claims payment, stating with substantial accuracy the amount claimed and the name of the person for whom the work was performed or to whom the material was furnished.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

S.W. Bjorhus v. Aston Twp.
Commonwealth Court of Pennsylvania, 2021
J. Allen v. City of Philadelphia and Lt. D. McCann
Commonwealth Court of Pennsylvania, 2019
General Equipment Manufacturers v. Westfield Insurance
592 A.2d 1349 (Superior Court of Pennsylvania, 1991)
Martin v. Soblotney
442 A.2d 700 (Superior Court of Pennsylvania, 1982)
McKnight v. City of Philadelphia
445 A.2d 778 (Superior Court of Pennsylvania, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
436 A.2d 1192, 292 Pa. Super. 142, 1981 Pa. Super. LEXIS 3636, Counsel Stack Legal Research, https://law.counselstack.com/opinion/posh-construction-inc-v-simmons-greer-inc-pasuperct-1981.