Portzen Construction, Inc. v. Cal-Co Insulation, Inc., Cal-Co Insulation, Inc. v. Portzen Construction, Inc., and United Fire & Casualty Company

CourtCourt of Appeals of Iowa
DecidedMay 29, 2014
Docket13-0758
StatusPublished

This text of Portzen Construction, Inc. v. Cal-Co Insulation, Inc., Cal-Co Insulation, Inc. v. Portzen Construction, Inc., and United Fire & Casualty Company (Portzen Construction, Inc. v. Cal-Co Insulation, Inc., Cal-Co Insulation, Inc. v. Portzen Construction, Inc., and United Fire & Casualty Company) is published on Counsel Stack Legal Research, covering Court of Appeals of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Portzen Construction, Inc. v. Cal-Co Insulation, Inc., Cal-Co Insulation, Inc. v. Portzen Construction, Inc., and United Fire & Casualty Company, (iowactapp 2014).

Opinion

IN THE COURT OF APPEALS OF IOWA

No. 13-0758 Filed May 29, 2014

PORTZEN CONSTRUCTION, INC., Plaintiff-Appellee,

vs.

CAL-CO INSULATION, INC., Defendant-Appellant.

CAL-CO INSULATION, INC., Plaintiff-Appellant,

PORTZEN CONSTRUCTION, INC., and UNITED FIRE & CASUALTY COMPANY, Defendant-Appellees. ________________________________________________________________ Appeal from the Iowa District Court for Dubuque County, Thomas A.

Bitter, Judge.

A subcontractor appeals from the judgment entered by the district court in

favor of a general contractor. AFFIRMED.

Todd J. Locher of Locher & Locher, PLC, Farley, for appellant.

Douglas M. Henry of Fuerste, Carew, Juergens & Sudemeier, P.C.,

Dubuque, for appellee Portzen.

Drew J. Gentsch of Whitfield & Eddy, P.L.C., Des Moines, for appellee

United Fire.

Heard by Doyle, P.J., Tabor, J., and Zimmer, S.J.*

*Senior judge assigned by order pursuant to Iowa Code section 602.9206 (2013). 2

DOYLE, J.

Cal-Co Insulation, Inc., a subcontractor on a commercial building

renovation project, appeals from the judgment entered by the district court in

favor of general contractor Portzen Construction, Inc. on the parties’ respective

breach-of-contract claims and the discharge of the bond posted by United Fire

& Casualty Company. We affirm.

I. Background Facts and Proceedings

In early 2011, Gronen Restoration, Inc. began accepting bids for a number

of construction contracts associated with a renovation project of the Caradco

building in Dubuque. Portzen Construction, Inc. prepared a bid for the contract

entitled “Concrete Flooring Systems”—a flooring portion of the project that

included installation of insulation in places, a layer of noise-retardant material,

and new concrete poured over the top. As part of its bid, Portzen wanted to offer

Gronen the option of either “rigid board” insulation or “spray foam” insulation.

To provide the spray foam insulation option, Portzen contacted Cal-Co

Insulation, Inc. to request a subcontractor bid. Portzen told Cal-Co the second

floor would require 633 cubic yards of insulation and the third floor would require

720 cubic yards of insulation.1 Cal-Co stated it would need to calculate its

numbers. Cal-Co called back later that day and told Portzen its cost would be

$14,185 to spray the second floor and $16,135 to spray the third floor, for a total

of $30,320.

1 To prepare the estimate of the amount of product that would be needed, Portzen owner Michael Portzen calculated the volume of the area to be insulated by using more than 400 different elevation points on each floor. 3

The next day, June 2, 2011, Cal-Co met with Portzen at Portzen’s office.

Portzen showed Cal-Co the project plans, and emphasized that the floors of the

Caradco building were uneven and the layer of insulation would vary between

one inch and ten inches. Portzen also told Cal-Co the job would need to be done

in stages, meaning Cal-Co would have to do sections of the insulation rather than

complete the insulation at one time. After some discussion, Cal-Co stated the

extra “mobilizations” would add an additional $1000 to its bid. Portzen therefore

considered Cal-Co’s bid to be an even $32,000.

Portzen submitted its bid to Gronen later that day. Relying on Cal-Co’s

subcontractor bid, Portzen’s bid included the option to “use spray foam in lieu of

board insulation” for a $265,000 deduction in cost. Gronen accepted Portzen’s

bid with the spray foam insulation option and a contract between Gronen and

Portzen was signed. An agreement between Portzen and Cal-Co was drafted

but was not signed.

On June 13, Cal-Co sprayed a test section (approximately ten feet by ten

feet) with spray foam insulation. Cal-Co billed Portzen $840 for the test section.

On September 1, Cal-Co sprayed an entire apartment of the building

(apartment 222) as another test section. Cal-Co billed Portzen $5268 for the

spraying on apartment 222.

Around that time, Cal-Co became concerned the job was going to require

far more spray foam insulation than it had originally determined. Cal-Co

contacted its spray foam insulation supplier in an attempt to get a better price on

the insulation. Cal-Co and the supplier discussed the job site measurements.

The supplier calculated the total quantity of insulation Cal-Co needed for the job 4

to be between 106 and 125 “sets” of insulation,2 priced at approximately $1950

per set—for a total product cost of $206,700 to $243,750.

Cal-Co contacted Portzen regarding the fact that the job was going to

require more than $200,000 in product alone. To prevent the project from

coming to a standstill, Portzen asked Cal-Co to spray a section of the building

(approximately 5000 square feet) to buy some time to find a solution to the

problem. Between September 23 and September 28, Cal-Co sprayed 5160

square feet, for which it billed Portzen $10,986.

Meanwhile, Portzen met with Gronen to discuss miscalculation of cost for

the spray foam insulation portion of the project. Ultimately, Gronen hired Noonan

Insulation to finish the insulation job. Bel-Aire Home Improvements also

completed a small portion of the insulation. Portzen lost a total of $303,000 as a

result of Cal-Co not completing the insulation as originally planned.

Portzen filed a petition at law claiming Cal-Co breached its contract with

Portzen and seeking damages in the amount the actual cost of completion of the

insulation “exceeded the agreed price of $32,000,” plus interest and costs.

Meanwhile, Cal-Co filed an action in equity against Portzen and its bonding

company, United Fire & Casualty Company, seeking recovery on its mechanic’s

lien in the amount of $18,837 that Portzen discharged, for work completed by

Cal-Co that had not been paid by Portzen. The district court stayed Cal-Co’s

equity action pending the outcome of Portzen’s law action.

2 Each set of spray foam insulation is approximately 1000 pounds and covers about 4500 board feet. Witnesses at trial testified a “board foot” is a unit of measurement twelve inches by twelve inches by one inch. 5

Following a bench trial, the district court determined a contract existed

between the parties and entered judgment in favor of Portzen on its breach-of-

contract claim. The court found, “Cal-Co had enough information to properly bid

the job. Cal-Co simply made a mistake.” The court further determined, “Portzen

acted to its detriment in reliance on [Cal-Co’s] promise. Substantial injustice

would result if the promise is not enforced.” The district court awarded Portzen

$303,000 in damages. The court also ordered Portzen to pay Cal-Co $1743 for

work it performed but was not paid for on a different part of the Caradco building.

Cal-Co filed a motion to enlarge, and Portzen filed a motion to provide for

payment and a motion to discharge bond. Following a hearing, the court entered

an order (1) denying Cal-Co’s motion, (2) specifying the terms of payment to

satisfy the parties’ respective judgments, and (3) discharging the bond posted by

United. Cal-Co now appeals.3,4

3 United, as appellee, joins the arguments made by Portzen on appeal. Insofar as United alternatively claims Cal-Co waived any claims against United by not specifically discussing “United,” we believe Cal-Co’s claims appropriately incorporate United and address them as such.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Service Unlimited, Inc. v. Elder
542 N.W.2d 855 (Court of Appeals of Iowa, 1995)
RET Corp. v. Frank Paxton Co., Inc.
329 N.W.2d 416 (Supreme Court of Iowa, 1983)
Dallenbach v. MAPCO Gas Products, Inc.
459 N.W.2d 483 (Supreme Court of Iowa, 1990)
Land O'Lakes, Inc. v. Hanig
610 N.W.2d 518 (Supreme Court of Iowa, 2000)
Flom v. Stahly
569 N.W.2d 135 (Supreme Court of Iowa, 1997)
Audus v. Sabre Communications Corp.
554 N.W.2d 868 (Supreme Court of Iowa, 1996)
Gallagher, Langlas & Gallagher v. Burco
587 N.W.2d 615 (Court of Appeals of Iowa, 1998)
Speckel Ex Rel. Speckel v. Perkins
364 N.W.2d 890 (Court of Appeals of Minnesota, 1985)
Iowa Mortgage Center, L.L.C. v. Lana Baccam and Phouthone Sylavong
841 N.W.2d 107 (Supreme Court of Iowa, 2013)
John R. Baur v. Baur Farms, Inc. and Robert F. Baur
832 N.W.2d 663 (Supreme Court of Iowa, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Portzen Construction, Inc. v. Cal-Co Insulation, Inc., Cal-Co Insulation, Inc. v. Portzen Construction, Inc., and United Fire & Casualty Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/portzen-construction-inc-v-cal-co-insulation-inc-c-iowactapp-2014.