Portland General Electric Co. v. U.S. Bank Trust National Ass'n

38 F. Supp. 2d 1195, 1999 U.S. Dist. LEXIS 2299, 1999 WL 112838
CourtDistrict Court, D. Oregon
DecidedJanuary 26, 1999
DocketCiv. 98-1332-HA
StatusPublished

This text of 38 F. Supp. 2d 1195 (Portland General Electric Co. v. U.S. Bank Trust National Ass'n) is published on Counsel Stack Legal Research, covering District Court, D. Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Portland General Electric Co. v. U.S. Bank Trust National Ass'n, 38 F. Supp. 2d 1195, 1999 U.S. Dist. LEXIS 2299, 1999 WL 112838 (D. Or. 1999).

Opinion

OPINION AND ORDER

HAGGERTY, District Judge.

I. Introduction

Pending before the court is Plaintiff Portland General Electric Co.’s (“PGE’s”) motion for a declaratory judgment against Trusts No. 2 and 3 of Defendant U.S. Bank Trust National Association (“U.S.Bank”). For the foregoing reasons, the motion shall be granted, and an order shall be entered finding the December 17, 1998 full report of the appraisal of the generator equipment contained in exhibit 4 of plaintiffs memorandum is binding on the parties.

II. Background

Twenty-five years ago Plaintiff PGE, an electrical company based in Portland, Oregon, leased four generator “units,” under two Lease Agreements, from the Bank of California National Association (“Bank of California”). Apparently, the Bank of California held title to the generators through three separate trusts (“Trusts No. 1, 2, and 3”), two through Trust No. 1 and one each through Trusts No. 2 and 3. Through a series of acquisitions and assignments, Defendant U.S. Bank eventually became trustee for the trusts.

Both Lease Agreements terminate on August 8,1999. Under § 24 of both Lease Agreements, PGE has the option to (1) renew them for an additional five-year term at fair market rental value, (2) purchase the units at fair market sales value, or (3) do nothing and let the Leases expire. PGE has until February 7, 1999 to make its decision. Under § 24 of the Lease Agreements, by giving written notice no earlier than one year prior to expiration of the lease, PGE could request those values be determined. If the parties failed to agree upon those values before ten months prior to expiration of the Lease Agreements (October 8, 1998), the Agreements allowed PGE to request an independent appraisal of the value of the equipment. If within 15 business days of the request for appraisal the parties failed to agree on who would be the independent appraiser, either party could request the American Arbitration Association (“AAA”) to appoint an independent appraiser.

PGE filed this action on October 27, 1998 asking the Court to appoint an appraiser and instruct that appraiser how to determine the fair market rental value and fair market sales value. On November 13, 1998, the AAA appointed Carl Bloomquist of Marshall & Stevens, Inc. as the inde *1197 pendent appraiser of the units owned by Trusts No. 2 and 3. 1 At a hearing on November 24, 1998, this court ruled that under Ninth Circuit case law, Raytheon Co. v. Rheem Manuf. Co., 322 F.2d 173 (9th Cir.1963), as well as the Federal Arbitration Act (“FAA”), this court had no authority to instruct the appraiser how to determine those values.

On December 14, 1998, Bloomquist, the appraiser, issued a letter by facsimile summarizing his assessment of the equipment owned by Trusts No. 2 and 3. He found that the fair market sales value of the units was $24,000,000 and the fair market rental value of the units was $24,869,407. He stated in the letter that the actual report would be forthcoming on Friday, December 18, 1998. Before issuing the body of the report, however, on December 17, 1998, Bloomquist sent the parties a two-paragraph facsimile stating that he had discovered an error in his calculations. He revised his appraisal so that the sales value was $27,500,000 and the rental value was $24,455,154. He then issued the full report. On January 6, 1998 he sent another facsimile to the parties explaining the valuation change, at the request of a PGE representative.

The value change was a result of adjustments made to a risk factor costs [sic] and because of a miscalculation (where the future market value was calculated as of December 31, 1999-as opposed to the actual valuation date of August 8, 1999). As current and immediate future markets for used gas turbine equipment appear strong, volatile, and time sensitive, the adjustments resulted in change to the market value in continued use as presented in the final report.

(Plaintiffs Memorandum, ex. 5.)

PGE requests a declaratory judgment from this court establishing whether the revision was valid even though it occurred outside the thirty-day time period established by the contract. PGE claims it is unable to determine which option to exercise, if either, because it now has “two appraisals” with different valuations of the sales value and rental value in each. It also argues that the December 17th revisal was invalid because it occurred outside the time frame set forth in the contract. If faced with the possibility of having no binding appraisal, however, PGE is willing, as an alternative, to accept the December 17th revision rather than be left with no valid appraisal whatsoever. (See docs. 50 and 51.)

II. DISCUSSION

A. Functus Officio

PGE argues that upon rendering the initial December 14, 1998 facsimile, the appraiser’s power to issue a decision terminated and under the doctrine of “functus officio” 2 he had no authority to correct his erroneous decision. This common-law doctrine has been described by commentators as follows:

When an award has been made, the authority of the arbitrator comes to an end. He become functus officio. Under general principles of arbitration law he cannot in any way change or explain his award unless his authority is reinstated in writing by all parties, or the matter is returned to him by the appropriate court.

In re Arbitration of the Board of Directors of the Association of Apartment Owners of Tropicana Manor, 73 Haw. 201, 830 P.2d 503, 507 (1992) (quoting Domke on Commercial Arbitration § 32:01, at 458-59 (rev. ed.1991)). The policy underlying the doctrine is based on “an unwillingness to permit one who is not a judicial officer and who acts informally and sporadically, to reexamine a final decision which he has already rendered, because of the potential *1198 evil of outside communication and unilateral influence which might affect a new conclusion.” 3 McClatchy Newspapers v. Central Valley Typographical Union No. 16, 686 F.2d 731, 734, cert. denied 459 U.S. 1071, 103 S.Ct. 491, 74 L.Ed.2d 633 (1982) (quoting La Vale Plaza, Inc. v. R.S. Noonan, Inc., 378 F.2d 569, 572 (3d Cir.1967)).

In arguing that the doctrine of functus officio applies, PGE ignores an essential precondition to its use: finality. The doctrine applies “once an arbitrator has made and published a final award[.]” International Brotherhood of Teamsters v. Silver State Disposal Serv., Inc., 109 F.3d 1409

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
38 F. Supp. 2d 1195, 1999 U.S. Dist. LEXIS 2299, 1999 WL 112838, Counsel Stack Legal Research, https://law.counselstack.com/opinion/portland-general-electric-co-v-us-bank-trust-national-assn-ord-1999.