Portland General Electric Co. v. Montana Department of Revenue

773 P.2d 1189, 237 Mont. 324, 1989 Mont. LEXIS 126
CourtMontana Supreme Court
DecidedMay 10, 1989
Docket88-160
StatusPublished
Cited by1 cases

This text of 773 P.2d 1189 (Portland General Electric Co. v. Montana Department of Revenue) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Portland General Electric Co. v. Montana Department of Revenue, 773 P.2d 1189, 237 Mont. 324, 1989 Mont. LEXIS 126 (Mo. 1989).

Opinion

MR. JUSTICE HARRISON

delivered the Opinion of the Court.

Appellant, Portland General Electric (hereinafter PGE), appeals an order entered by the Honorable Henry Loble, First Judicial District Court, Lewis and Clark County, Montana, denying injunctive and declaratory relief. We affirm.

This case concerns the imposition of beneficial use taxes, pursuant to § 15-24-1203, MCA (1983), for appellant’s use of the Hot Springs to Idaho Border portion of the BPA 500 kilovolts (KV) transmission line system within the State of Montana.

“[Tjhere is imposed and shall be collected a tax upon the possession or other beneficial use enjoyed by any private individual, association, or corporation of any property, real or personal, which for any reason is exempt from taxation . . . The tax shall be imposed upon the possession or other beneficial use of an electric transmission line and associated facilities, except that lines and facilities of a design capacity of less than 500 kilovolts shall not be subject to the tax.”

Section 15-24-1203, MCA.

Much of the factual background surrounding this case has previously been discussed in our decision, Pacific Power & Light Co. v. Department of Revenue, (1989) [237 Mont. 77,] 773 P.2d 1176, [46 St.Rep. 636]. Therefore, we will limit the extensive background discussion and instead focus on the additional facts relevant to this case.

PGE is an investor-owned utility which provides retail electric utility service to customers located in the State of Oregon. PGE owns an undivided 20% interest in Colstrip Units III and IV, which began *326 operation in October of 1983 and 1985, respectively. The other four Colstrip owners are Pacific Power & Light Company, Washington Water Power Company, Puget Sound Power & Light Company, and Montana Power Company. Collectively, these companies are referred to as the “Colstrip Owners.”

With the development of Colstrip Units III and IV, additional transmission capacity was needed from the Colstrip facilities to the west. To accommodate the increased generation, Colstrip Owners initially converted one 230 KV line extending from the generating facilities to a substation near Broadview, Montana, to 500 KV and constructed a second 500 KV line. From the Broadview substation, the Colstrip Owners’ 500 KV lines extend westward to a point near Townsend, Montana. At Townsend, the Colstrip Owners’ 500 KV lines interconnect with the Bonneville Power Administration’s (BPA) 500 KV lines. The portion extending from Townsend to the BPA’s Garrison substation is referred to as the Montana Intertie, and is extensively discussed in our previous opinion, Pacific Power & Light Co. In 1986, anticipating the completion of Colstrip Unit IV, the BPA, at the request of the Colstrip Owners, completed the Garrison-West lines connecting the Garrison substation to the Taft, Montana, substation and points to the west. Prior to the completion of the Garrison-Taft 500 KV transmission lines, the Hot SpringsDworshak lines were the only existing 500 KV lines providing access to the west.

From the BPA substation at Garrison, Montana, the transmission of Colstrip power is governed by separate contracts, commonly referred to as the Garrison-West Agreement. These contracts continue for a period of 22 years, with a right to renew at comparable terms. Under each Owners’ separate contract with the BPA, power would be introduced at the Garrison substation and transmitted across the entire BPA “main grid” which included both 230 and 500 KV lines. Notably, appellant entered into no other agreement for the transmission of its Colstrip power to points west.

Under the terms of PGE’s agreement with the BPA, PGE requested BPA provide adequate transmission facilities west of Garrison, Montana, to transmit power on a firm basis over the Federal Transmission System to PGE’s system load at the Pearl substation in Oregon. PGE made available and BPA was required to accept scheduled power not to exceed the reserved transmission demand set forth on Exhibit D of the Garrison-West Agreement. Exhibit D provided that from the date of commercial operation of Colstrip *327 Unit III until the date when the 500 KV transmission lines connecting Garrison to the Federal 500 KV transmission system first became available for scheduling power (the Garrison-Taft lines), the transmission demand for PGE was zero. However, a footnote to Exhibit D provided for the five Colstrip owners to allocate BPA’s available 330 megawatts transmission capacity.

At this point, a brief explanation describing the 330 megawatt limitation is in order. From the Garrison substation to points west, the BPA lacked transmission line capacity to accommodate full transmission of Colstrip power to the Owners’ individual system loads. This lack of transmission capacity is due to a gap in the 500 KV lines between the Garrison substation and the Hot Springs substation, referred to in this litigation as the “bottleneck.” Between the two substations, the BPA had only 230 KV lines, which proved insufficient to accommodate the total scheduled Colstrip power. Recognizing its inability to fulfill obligations under the Garrison-West Agreements, the BPA imposed a 330 megawatt limitation upon the amount of power which could be scheduled west of the Garrison substation, until the Garrison-Taft 500 KV lines were completed.

On December 20, 1983, a Montana Power Company representative contacted BPA officials indicating Colstrip Owners had reached an agreement on the allocation of BPA’s 330 megawatts. Respectively, PGE was allocated 65 megawatts transmission demand. The reserved amount is reflected in a revised Exhibit D to the PGE’s Garrison-West Agreement. In turn, the BPA responded on February 4, 1984, stating:

“This is to confirm that each of your companies [Colstrip Owners] has sent BPA a letter agreeing with the allocation, contained in The Montana Power Company’s letter dated December 20, 1983, of the 330 MW of transmission capacity available to the Colstrip owners on BPA’s Garrison-Hot Springs transmission line during the period starting with commercial operation of Colstrip Unit No. 3 and ending at 2400 hours on the date when the Garrison-Taft 500 KV transmission line is available for scheduling power, pursuant to existing contracts for wheeling Colstrip power.

Transmission Company Bonneville Contract No. Demand
Portland DE-MS79-81BP00167 65 MW

*328 Once scheduling of Colstrip power over the Hot Springs to border line began, PGE was required to pay BPA a monthly charge calculated pursuant to the terms of the Garrison-West Agreement. The transfer of energy was “deemed” to have occurred whether or not there was actual physical transmission.' Therefore, the monthly charge was due BPA regardless of PGE’s actual transmission flow across the lines.

Beginning in the tax year 1985, the Department of Revenue (DOR) imposed taxes upon appellant for its “beneficial use” of the BPA 500 KV transmission lines from Hot Springs to the Idaho border.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pacific Power & Light Co. v. Montana Department of Revenue
804 P.2d 397 (Montana Supreme Court, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
773 P.2d 1189, 237 Mont. 324, 1989 Mont. LEXIS 126, Counsel Stack Legal Research, https://law.counselstack.com/opinion/portland-general-electric-co-v-montana-department-of-revenue-mont-1989.