Portland Development Commission v. CH2M Hill Northwest, Inc.

758 P.2d 353, 92 Or. App. 43
CourtCourt of Appeals of Oregon
DecidedJuly 6, 1988
DocketA8508-04965; CA A42840
StatusPublished
Cited by3 cases

This text of 758 P.2d 353 (Portland Development Commission v. CH2M Hill Northwest, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Portland Development Commission v. CH2M Hill Northwest, Inc., 758 P.2d 353, 92 Or. App. 43 (Or. Ct. App. 1988).

Opinion

*45 WARREN, J.

Plaintiff Portland Development Commission appeals a judgment in favor of Riedel International, Inc. (Riedel), for attorney fees of $167,830.25, purportedly awarded pursuant to ORS 20.105(1).

In 1979, plaintiff contracted with defendant CH2M Hill Northwest (CH2M) to provide design services, plans and specifications for construction of a breakwater for plaintiffs South Downtown Development Project. In June, 1984, Riedel was awarded the construction contract. 1 In the summer or early fall, Riedel notified plaintiff that the plans and specifications provided by CH2M were not final and were not sufficient for construction of the breakwater. CH2M took the position that it had performed its contract with plaintiff and that the plans required Riedel to design and build the breakwater. Riedel proceeded to build the breakwater. In the spring of 1985, blowouts and cracks became evident in the bréakwater units. Plaintiff engaged an engineering firm to determine the cause of the failures. Riedel claimed additional costs and had ongoing negotiations with plaintiff regarding the claims.

On August 9, 1985, plaintiff filed this declaratory judgment action against CH2M and Riedel. Plaintiff alleged that it construed its contract with CH2M to provide that CH2M was to prepare final plans, that Riedel contended that the plans were not final and that, because of that, Riedel had asserted a claim for damages of $400,000 against plaintiff. Plaintiff prayed for a declaration that its contract with CH2M required CH2M to provide final plans, that the plans provided by CH2M were not final and that the plans did not require the contractor to design the breakwater.

On September 24, after the action had been filed, Hayford, of the engineering firm retained by plaintiff, sent a letter to plaintiff which detailed the problems and possible solutions for the failures in the concrete units. He concluded that there were design difficulties and that the units did not have adequate concrete cover on the “rebar”; plaintiff blamed the latter deficiency on inadequate workmanship by Riedel. On January 28,1986, Hayford confirmed by letter to plaintiff *46 that it would take $55,320 to maintain the units because of the inadequate concrete cover, and plaintiff withheld that amount from its contract payment to Riedel.

The declaratory judgment action proceeded in three phases. The first concluded on June 23, 1986, when all the parties stipulated that, under the contract with plaintiff, CH2M was to provide final design plans and specifications for the breakwater. Judgment was entered on the stipulation, reserving for trial the issue of whether CH2M had fulfilled its responsibility. Also unresolved was plaintiffs claim for damages from Riedel for inadequate workmanship. 2 Riedel filed an amended answer and counterclaim, alleging that plaintiff had no basis for asserting inadequate workmanship and that plaintiff had involved Riedel in litigation to avoid paying the contract balance. Riedel alleged that plaintiffs conduct justified an award of attorney fees. The second phase of the proceeding concluded after a trial in August. The court found that CH2M had not provided final design plans or specifications. The third phase of the proceeding determined damages. The court dismissed plaintiffs claim against Riedel for $55,320 for failure of proof and ordered CH2M to indemnify plaintiff for Riedel’s claims against plaintiff. The court also allowed Riedel’s claim for attorney fees.

The bifurcated nature of the proceeding apparently led the trial court to conclude that attorney fees were warranted under ORS 20.105(1). The court held that, although plaintiff had an “understandable position” at the time it filed the proceeding, its refusal to pay the $55,320 after receiving Hayford’s September letter was “inexplicable.” The court apparently concluded that plaintiff should have proved its case against CH2M, using Riedel personnel as witnesses instead of joining it as a party. Apparently because plaintiff pursued its damages claim against Riedel, the trial court concluded that attorney fees should be awarded to Riedel. 3

*47 ORS 20.105(1) provides:

“In any civil action, suit or other proceeding in a district court, a circuit court or the Oregon Tax Court, or in any civil appeal to or review by the Court of Appeals or Supreme Court, the court may, in its discretion, award reasonable attorney fees appropriate in the circumstances to a party against whom a claim, defense or ground for appeal or review is asserted, if that party is a prevailing party in the proceeding and to be paid by the party asserting the claim, defense or ground, upon a finding by the court that the party wilfully disobeyed a court order or acted in bad faith, wantonly or solely for oppressive reasons.”

We have not previously examined the standards under ORS 20.105, 4 apart from suggesting its applicability to “frivolous” and “malicious” claims. See Kling v. Exxon Corp., 74 Or App 399, 404, 703 P2d 1021 (1985). The terminology “bad faith, wantonly or solely for oppressive reasons” was adopted from Alyeska Pipeline Co. v. Wilderness Soc., 421 US 420, 95 S Ct 1612, 44 L Ed 2d 141 (1975), and reflects the standards used in federal cases. 5 However, Alyeska 6 did not *48 define “bad faith,” 7 nor did the cases on which it relied. Later federal cases have made it clear that a finding of “bad faith” requires clear evidence that a claim has been made entirely without any basis in fact or law. See Browning Debenture Holders’ Committee v. DAS A Corp., 560 F2d 1078, 1088 (2nd Cir 1977). Nemeroff v. Abelson, 620 F2d 339, 348 (2nd Cir 1980), defined a colorable claim, for the purpose of the bad faith exception, as one which

“has some legal and factual support, considered in light of the reasonable beliefs of the individual making the claim. The question is whether a reasonable attorney could have concluded that facts supporting the claim might be established, not whether such facts actually had been established.” (Footnote omitted; emphasis deleted.)

Riedel argues that plaintiffs actions were taken in bad faith, because there was never any reason to involve Riedel in a judicial determination of any of the issues. 8

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mattiza v. Foster
803 P.2d 723 (Oregon Supreme Court, 1990)
Adams v. State
798 P.2d 244 (Court of Appeals of Oregon, 1990)
Tyler v. Hartford Insurance
780 P.2d 755 (Court of Appeals of Oregon, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
758 P.2d 353, 92 Or. App. 43, Counsel Stack Legal Research, https://law.counselstack.com/opinion/portland-development-commission-v-ch2m-hill-northwest-inc-orctapp-1988.