Porter v. Western Tube Co.

144 Ill. App. 237, 1908 Ill. App. LEXIS 462
CourtAppellate Court of Illinois
DecidedOctober 14, 1908
DocketGen. No. 4,998
StatusPublished

This text of 144 Ill. App. 237 (Porter v. Western Tube Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Porter v. Western Tube Co., 144 Ill. App. 237, 1908 Ill. App. LEXIS 462 (Ill. Ct. App. 1908).

Opinion

Mr. Justice' Willis

delivered the opinion of the court.

This is an appeal from the Circuit Court of Henry county to review a decree of that court allowing appellees, James Porter and Harry W. Trask, subcontractors, a mechanic’s lien on property owned by appellant, the Western Tube Company.

On June 20, 1906, appellees filed in said court a bill against the Western Tube Company and Frederick H. Mathews and Charles F. McMullen, co-partners, doing business as the Mathews Construction Company, to establish and foreclose a subcontractors’ mechanic’s lien for lumber and building materials furnished on a building erected on lots one and two, of block thirteen, of the original town, now city of Kewanee. The bill alleged that on or about June 28, 1905, appellant entered into a written contract with the Mathews Construction Company to erect an office building on its premises according to certain plans and specifications, a copy of which contract was attached to the bill. The contract provided that the building was to be constructed according to said plans and specifications and finished by Decernber 1, 1905, and in the event of failure to complete the building by that date, unless delayed by certain causes therein enumerated, a forfeiture of $5 per day was stipulated for. The contract price for the construction of said building was $16,400. The bill further alleged that on June 29, 1905, appellee entered into a verbal subcontract with the Mathews Construction Company to furnish the lumber and mill work necessary for the execution of said contract for the sum of $3350 and to furnish such extra material as was needed, the price therefor not to exceed the fair market value of ‘the same, to be delivered and payment made therefor, within three years from the furnishing of the first of such material, and that in accordance with the terms of said subcontract they delivered upon appellant’s premises between July 3,1905, and March 9,1906, the material so contracted for, and also delivered between June 29, 1905, and February 21, 1906, extra material to the amount of $621.17; and that said office building in the construction of which such material was used, was constructed on lot one and a part of lot two in block thirteen, in the original town, now city of Kewanee, of which appellant was the owner, and that there was due and unpaid on said contract, $1717.73, and that on April 16, 1906; the Mathews Construction Company rendered to appellant a verified statement in writing of the names of all parties furnishing labor or materials and of the amounts due or to become due each, which was delivered to appellant within sixty days after the final delivery of the materials by appellees. Appellant answered the bill and admitted the contract between it and the Mathews Construction Company, substantially as set up in the bill, but denied that the Construction Company ever completed said building and alleged that it was not completed according to the contract, and that said contract had not been performed by the Construction Company, and admitted that it owned the premises, and disclaimed knowledge as to the contract between appellees and the Construction Company and its indebtedness to appellees, and denied that legal notice was served on it, stating the amounts due and owing to the said Construction Company, and the names of the persons furnishing labor or material for the construction of said building, and stated that it had no knowledge that appellees furnished material, and that it was not advised and could not state whether appellees furnished material and labor in the construction of the buildings, and denied that it was indebted to appellees or that they were entitled to a lien. Appellees filed a general replication to appellant’s answer, and the bill was taken as confessed as to Mathews and McMullen. The cause was referred to the master to take proof and report the evidence and his conclusions of law and fact. The master heard the proof and reported that appellees were entitled to a lien on lots one and two of block thirteen of the original town, now city of Kewanee, on account of materials furnished in the erection of the building thereon.

To this report, appellant filed a number of objections, one of which was that it appeared from the evidence that no part of the building was on lot one, but that it was on lots two and three. This objection was held to be,good and the master amended his report and found that the lien should be allowed on lot two and overruled appellant’s other objections. There was a hearing before the court upon the master’s report and the exceptions thereto. The court approved his finding, and entered a decree granting appellees a lien for $1717.73 on lot two and $171.77 to appellees’ counsel as attorney’s fees. From this decree the Western Tube Company appealed.

Appellant first contends that the decree is erroneous, because it found that a lien should be allowed on lot two whereas the bill alleged that the building was erected on lots one and two, on the ground that appellees w.ere bound by the allegation in the bill, that to entitle them to recover they must prove the whole allegation, and that appellees failed in this because the evidence did not show that the building was erected on lots one and two but did show that it was erected on lot two, on the alley between lots two and three, and on a part of lot three.

Counsel for appellant contends that a subcontractor can have a lien the same as the original contractor under section one of the Mechanic’s Lien Act of 1903, which provides that a lien may be had upon the whole of such lot or tract of land and upon the adjoining or adjacent lots or tracts of land- of such owner, constituting the same premises, and occupied or used in connection with such lot or tract of land as a place of residence or business; and in case the contract relates to two or more buildings, or two or more lots or tracts of land, upon all of such lots and tracts of land and improvements thereon, for the amount due with the interest thereon, and that that means a lien must be taken upon all the premises occupied by the building or none.

We cannot agree with counsel on this proposition. In. Sorg v. Pfalzgraf, 113 Ill. App. 569, a suit to enforce a mechanic’s lien, the bill located the house on lots nine and ten. On the trial it developed that it stood on lots eight and nine and not on lot ten. It was then too late to enforce a lien against lot eight. The court ordered a decree against lot nine only. We there said, the owner cannot be permitted to defeat the lien upon his land which the law has given the builder simply because the builder might have obtained a lien upon more of the owner’s land.

It does not appear that Granquist’s rights were prejudiced by the decree in this case, unless, as urged by appellant, Granquist should share pro rata with the other subcontractors in the amount shown to be due by the statement made by the Construction Company on April 16, 1906. Section five of the Mechanic’s Lien Law of 1903, makes it the duty of the owner to require of the contractor, before he, or anyone for him, shall pay or cause to be paid to said contractor, or for him, any moneys or other consideration due, or to become due such contractor, or make or cause to he made any advancement of any moneys or other consideration, a statement in writing, under oath, or verified by affidavit, of the names of all parties furnishing material and labor and the amounts due or to become due each.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Manowsky v. Stephan
84 N.E. 365 (Illinois Supreme Court, 1908)
Pease v. Chicago Crayon Co.
85 N.E. 619 (Illinois Supreme Court, 1908)
Nutriment Co. v. George Green Lumber Co.
94 Ill. App. 342 (Appellate Court of Illinois, 1901)
Sorg v. Pfalzgraf
113 Ill. App. 569 (Appellate Court of Illinois, 1904)

Cite This Page — Counsel Stack

Bluebook (online)
144 Ill. App. 237, 1908 Ill. App. LEXIS 462, Counsel Stack Legal Research, https://law.counselstack.com/opinion/porter-v-western-tube-co-illappct-1908.