Porter Drywall v. Olentangy Bld. Dev., Unpublished Decision (2-24-2000)

CourtOhio Court of Appeals
DecidedFebruary 24, 2000
DocketNo. 99AP-306.
StatusUnpublished

This text of Porter Drywall v. Olentangy Bld. Dev., Unpublished Decision (2-24-2000) (Porter Drywall v. Olentangy Bld. Dev., Unpublished Decision (2-24-2000)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Porter Drywall v. Olentangy Bld. Dev., Unpublished Decision (2-24-2000), (Ohio Ct. App. 2000).

Opinion

OPINION
Plaintiffs, Porter Drywall, Inc. ("Porter") and Access Drywall Supply Company, Inc. ("Access") appeal from an order of the Franklin County Court of Common Pleas which granted summary judgment in favor of defendants, Olentangy Building Development Company ("Olentangy") and general partners Richard C. Wing, Roger C. Wing and Jacqueline S. Dematteis-O'Brien.1 Porter and Access advance the following four assignments of error:

1. The trial court erred when it concluded that reasonable minds could come to one conclusion, and that conclusion was that the plans and specifications clearly provided for a double wall system in all apartments [sic] units.

2. The trial court erred when it found that the Porter contract had a duty to exclude and then failed to exclude the double wall system in the garden units.

3. The trial court erred when it found that the Defendants-Appellees were entitled to relief from a breach of contract by the Plaintiff.

4. The trial court erred when it found that materials ordered from Plaintiff-Appellant, Access Drywall Supply Co., Inc., could be found to be covered under the contract of Plaintiff-Appellant, Porter Drywall, Inc.

On September 12, 1995, Porter, a drywall subcontractor, submitted a proposal to provide materials and labor for the installation of drywall in a ten-building apartment project wherein Olentangy was the owner and general contractor. The apartment project included both one and two-bedroom garden units and two-bedroom, two-story townhouse units. Olentangy provided Porter a complete set of plans and specifications so that Porter could prepare its bid. The plans and specifications were prepared by architect Donald R. McCartney.

Porter analyzed the plans and specifications for the project in preparing its bid. Porter's written proposal incorporated the provisions of AIA Document 401, entitled "Standard Form of Agreement Between Contractor and Subcontractor," which in turn incorporated the plans and specifications. In addition, Porter's proposal contained the following pertinent language: "* * * subject to the clarifications and qualifications contained herein, Porter will furnish all labor, material, equipment and supervision necessary to complete the drywall and related work in accordance with specification sections and these specific drawings * * *." Under the "clarifications" section of the proposal, Porter set out the unit price breakdown for the project. Pricing for the garden units included the following notation: "One hour fire separation walls — one layer 5/8" F.C. hung and taped each side of truss at tenant separation wall[.]" Pricing for the townhouse units included the above-referenced notation, as well as the following additional notation: "Double wall system — one layer 5/8" F.C. hung and taped each side of tenant separation wall from 1st floor to roof deck[.]"

On February 1, 1996, Olentangy accepted Porter's bid, which totaled $134,745. On July 17, 1996, the parties agreed to a written change order in the amount of $604.80, thereby increasing the total amount of the contract between Porter and Olentangy to $135,349.80.

During the course of construction, it became apparent to Richard C. Wing, Olentangy's primary representative to Porter on the project, that Porter had not delivered enough drywall to complete the installation of a double drywall system in the garden units. Wing met with Robert E. Porter, vice-president of both Porter and Access, to discuss the problem. After reviewing the plans and specifications, Mr. Porter stated that he had missed the double drywall system in the garden units and would "take care of it — I'll eat it." Despite Mr. Porter's admission, Porter did not install it. As a result, Olentangy ordered additional drywall from Access and incurred additional labor costs in installing the double drywall system in the garden units.

Over the course of the project, Porter submitted draws on the $135,349.80 contract amount of which Olentangy paid a total of $125,620. Olentangy paid Access $10,309.71 of the $14,798.45 amount billed by Access.

On August 8, 1997, Porter and Access filed a complaint alleging breach of contract due to Olentangy's refusal to pay the balance owed on the written contract with Porter and the alleged oral contract with Access. The complaint demanded judgment under the Porter contract for $9,729.80, plus interest and attorney fees, and under the Access contract for $4,490.84 plus interest.

On September 2, 1997, Olentangy filed an answer and counterclaim, asserting that Porter breached its contract "by failing to provide the materials specified, failing to timely install the work and other shortcomings." The counterclaim demanded judgment in the amount of $6,150.2

Porter and Access filed a motion for summary judgment, arguing that Porter interpreted the plans and specifications to include a double drywall system in the townhouse units, but to exclude a double drywall system in the garden units. Porter further argued that based upon this interpretation, it specified in its proposal that the double drywall system would be installed in the townhouse units and included the cost of such a system in its proposal; in contrast, Porter excluded references to a double drywall system for the garden units and did not include the cost of such a system in its proposal. Accordingly, Porter argued that it was not obligated to supply labor and materials for the double drywall system in the garden units and that Olentangy owed Porter the amount set forth in the complaint. Regarding Access's claims against Olentangy, Access argued that Olentangy ordered the drywall it used to install the double drywall system in the garden units pursuant to an oral contract with Access, paid a portion of the debt incurred in that transaction directly to Access, but failed to pay the remaining balance.

The summary judgment motion was supported by the January 22, 1998 affidavit of Robert Porter, who averred that Access entered into an oral contract with Olentangy to provide drywall and related materials for the project, and that the balance due on the account was $4,490.84. The motion was further supported by the affidavit of Melinda Barnhard, Porter's Office Accounts Manager, who averred that the balance due under Porter's contract with Olentangy was $9,729.80.

Olentangy filed a memorandum in opposition to Porter's motion and a cross-motion for summary judgment, arguing that pursuant to both the plans and specifications and Porter's proposal, Porter was obligated to provide labor and materials for a double drywall system in all of the units, including the garden units. Olentangy's motion was supported by the February 9, 1998 affidavit of Richard C. Wing, who averred that the floor plans for both the townhouse and garden units depicted the double drywall system by using double wall lines and that the cross-section on page 13 of the plans and specifications also illustrated the double drywall system.3 Wing further averred that Olentangy understood Porter's proposal to include pricing for the supply and installation of drywall for a double drywall system in both types of units.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Viock v. Stowe-Woodward Co.
467 N.E.2d 1378 (Ohio Court of Appeals, 1983)
Brown v. Scioto Cty. Bd. of Commrs.
622 N.E.2d 1153 (Ohio Court of Appeals, 1993)
Stevens Skin Softener, Inc. v. Revco Drug Stores, Inc.
699 N.E.2d 549 (Ohio Court of Appeals, 1997)
Amf, Inc. v. Mravec
440 N.E.2d 600 (Ohio Court of Appeals, 1981)
Maust v. Bank One Columbus, N.A.
614 N.E.2d 765 (Ohio Court of Appeals, 1992)
Ohio Farmers Insurance v. Estate of Brace
688 N.E.2d 298 (Ohio Court of Appeals, 1997)
Duke v. Sanymetal Products Co.
286 N.E.2d 324 (Ohio Court of Appeals, 1972)
Murphy v. City of Reynoldsburg
604 N.E.2d 138 (Ohio Supreme Court, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
Porter Drywall v. Olentangy Bld. Dev., Unpublished Decision (2-24-2000), Counsel Stack Legal Research, https://law.counselstack.com/opinion/porter-drywall-v-olentangy-bld-dev-unpublished-decision-2-24-2000-ohioctapp-2000.