Porter Drywall, Inc. v. Nations Construction, 07ap-726 (3-31-2008)

2008 Ohio 1512
CourtOhio Court of Appeals
DecidedMarch 31, 2008
DocketNo. 07AP-726.
StatusUnpublished
Cited by3 cases

This text of 2008 Ohio 1512 (Porter Drywall, Inc. v. Nations Construction, 07ap-726 (3-31-2008)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Porter Drywall, Inc. v. Nations Construction, 07ap-726 (3-31-2008), 2008 Ohio 1512 (Ohio Ct. App. 2008).

Opinion

DECISION
{¶ 1} Defendants-appellants, Nations Construction, LLC ("Nations") and William W. Bridge, III, its manager (collectively "defendants"), appeal from a judgment of the Franklin County Court of Common Pleas denying Bridge's summary judgment motion and granting the cross-motion for summary judgment of plaintiff-appellee, Porter Drywall, Inc. Because defendants waived the arguments raised on appeal when they failed to *Page 2 assert them in the trial court, and because the trial court properly granted summary judgment to plaintiff, we affirm.

{¶ 2} On April 25, 2007, plaintiff filed a four-count complaint against defendants, seeking damages in the amount of $5,065, plus interest and costs, for (1) an unpaid account, (2) services and materials provided, and (3) violation of R.C. 4113.61. The fourth count of the complaint sought to hold Bridge personally liable for Nations' failure to pay plaintiff.

{¶ 3} Nations filed an answer and a counterclaim on June 29, 2007. In its answer, Nations denied the pertinent allegations of plaintiff's complaint and set forth affirmative defenses contending (1) plaintiff failed to complete the work specified under the contract, and (2) the work plaintiff performed was substandard. Nations' counterclaim sought to recover money Nations expended to correct plaintiff's substandard performance and to complete the work plaintiff failed to perform. Bridge's individual answer denied the allegations of plaintiff's complaint.

{¶ 4} On the same date Bridge filed his answer to plaintiff's complaint, he filed a motion for summary judgment noting Nations had a written contract with plaintiff; the parties agree Bridge attached a single page document to his motion. According to Bridge's motion, Nations paid plaintiff $745 under the contract but subsequent disagreement with plaintiff about timely completion and quality of contracted work led to plaintiff's suit against defendants, including Bridge personally. Bridge's motion asserted that "there is simply no evidence, and therefore no genuine issue of material fact, that *Page 3 Defendant Bridge, personally or individually entered into any contracts with Plaintiff and is therefore entitled to Summary Judgment as a matter of law." (Emphasis sic.)

{¶ 5} On July 6, 2007, plaintiff filed an answer to Nations counterclaim, denying the allegations and asserting affirmative defenses. At the same time, plaintiff filed both a memorandum contra Bridge's summary judgment motion and a cross-motion for summary judgment with the attached affidavit of Shannon Boston, plaintiff's vice-president. Affixed to Boston's affidavit are two complete contracts between the parties, each consisting of both a front and back side. The front side of the contract is the same as the document attached, without affidavit, to Bridge's summary judgment motion. Neither Nations nor Bridge responded to plaintiff's cross-motion for summary judgment.

{¶ 6} By decision filed August 16, 2007, the trial court denied Bridge's summary judgment motion and granted plaintiff's cross-motion for summary judgment. In determining Bridge's personal liability, the trial court observed that paragraph 19(f) of Nations' contract with plaintiff specifically states an individual who signs the contract to bind the company assumes personal responsibility for amounts due and owing.

{¶ 7} As to defendants' contention that plaintiff's work was substandard and incomplete, the trial court noted the contract provides that if defendants were unsatisfied with plaintiff's work, plaintiff was to be notified in writing and given an opportunity to cure. Because Boston's affidavit states plaintiff received no notice Nations was dissatisfied with its work and because defendants responded with no evidence to suggest they forwarded the necessary notice, the trial court found defendants' contentions lacked merit. By judgment entry filed September 5, 2007, the trial court entered judgment for plaintiff, *Page 4 awarding $5,065 plus interest at the rate of 1.5 percent per month from January 27, 2006, plus costs, including attorney fees in the amount of $1,130.

{¶ 8} Defendants appeal, assigning the following errors:

FIRST ASSIGNMENT OF ERROR: THE TRIAL COURT ERRED IN HOLDING AN AGENT LIABLE FOR THE DEBTS OF A DISCLOSED PRINCIPAL WHERE THE AGENT SIGNED ONLY IN HIS CAPACITY AS AGENT.

SECOND ASSIGNMENT OF ERROR: THE TRIAL COURT ERRED IN GRANTING JUDGMENT AGAINST DEFENDANT BRIDGE PERSONALLY WHERE PLAINTIFF NEVER SOUGHT JUDGMENT ON THAT THEORY OF LIABILITY.

THIRD ASSIGNMENT OF ERROR: THE TRIAL COURT ERRED IN GRANTING SUMMARY JUDGMENT AGAINST DEFENDANT BRIDGE PERSONALLY AND DISREGARDING THE CORPORATE FORMAT WHERE THE EVIDENCE WAS AMBIGUOUS AND A MATTER OF FACT WAS PRESENTED.

{¶ 9} An appellate court's review of summary judgment is conducted under a de novo standard. Coventry Twp. v. Ecker (1995),101 Ohio App.3d 38, 41; Koos v. Cent. Ohio Cellular, Inc. (1994), 94 Ohio App.3d 579,588. Summary judgment is proper only when the parties moving for summary judgment demonstrate: (1) no genuine issue of material fact exists, (2) the moving parties are entitled to judgment as a matter of law, and (3) reasonable minds could come to but one conclusion and that conclusion is adverse to the party against whom the motion for summary judgment is made, that party being entitled to have the evidence most strongly construed in its favor. Civ.R. 56; State ex rel. Grady v. State Emp.Relations Bd. (1997), 78 Ohio St.3d 181.

{¶ 10} Pursuant to Civ.R. 56(C), the moving party bears the initial burden of informing the trial court of the basis for the motion and identifying those portions of the *Page 5 record demonstrating the absence of a material fact. Dresher v.Burt (1996), 75 Ohio St.3d 280, 293. The moving party, however, cannot discharge its initial burden under this rule with a conclusory assertion that the non-moving party has no evidence to prove its case; the moving party must specifically point to evidence of a type listed in Civ.R. 56(C), affirmatively demonstrating that the non-moving party has no evidence to support the non-moving party's claims. Id.; Vahila v.Hall (1997), 77 Ohio St.3d 421. Once the moving party discharges its initial burden, summary judgment is appropriate if the non-moving party does not respond, by affidavit or as otherwise provided in Civ.R. 56, with specific facts showing that a genuine issue exists for trial.Dresher at 293; Vahila at 430; Civ.R. 56(E). See, also, Castrataro v.Urban (Mar. 7, 2000), Franklin App. No. 99AP-219.

I. First Assignment of Error

{¶ 11} Defendants' first assignment of error contends the trial court erred in holding Bridge liable for Nations' debts because the facts of this case involve a disclosed principal whose agent signed only in his capacity as agent.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kreuzer v. Kreuzer
2015 Ohio 3253 (Ohio Court of Appeals, 2015)
Parmater v. Internet Brands, Inc.
2015 Ohio 253 (Ohio Court of Appeals, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
2008 Ohio 1512, Counsel Stack Legal Research, https://law.counselstack.com/opinion/porter-drywall-inc-v-nations-construction-07ap-726-3-31-2008-ohioctapp-2008.