Portco, Inc. v. Eye Specialists, Inc.

894 N.E.2d 84, 177 Ohio App. 3d 139, 2008 Ohio 3154
CourtOhio Court of Appeals
DecidedJune 20, 2008
DocketNo. 08CA3213.
StatusPublished
Cited by5 cases

This text of 894 N.E.2d 84 (Portco, Inc. v. Eye Specialists, Inc.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Portco, Inc. v. Eye Specialists, Inc., 894 N.E.2d 84, 177 Ohio App. 3d 139, 2008 Ohio 3154 (Ohio Ct. App. 2008).

Opinions

Abele, Presiding Judge.

{¶ 1} This is an appeal from a Scioto County Common Pleas Court judgment, entered after a trial to the court, for Porteo, Inc., plaintiff below and appellee herein, on its claim against Eye Specialists, Inc., defendant below and appellant herein.

{¶ 2} Appellant assigns the following errors for review:

FIRST ASSIGNMENT OF ERROR:
The trial court erred by failing to credit defendant for the entire amount of the West Virginia electric lien.
SECOND ASSIGNMENT OF ERROR:
The trial court erred in failing to award defendant damages pursuant to the contract based upon plaintiffs failure to complete the work prior to the completion date.
THIRD ASSIGNMENT OF ERROR:
The trial court’s decision that plaintiff failed to provide credible evidence to support defendant’s claim for unworkmanlike performance of a contract is against the manifest weight of the evidence.

*142 {¶ 3} In July 2003, the parties entered into a contract whereby Porteo agreed to renovate a former NAPA auto body parts store into a medical facility for use by Eye Specialists. In return, Eye Specialists promised to pay Porteo $320,178. Because Eye Specialists wanted to open its Portsmouth office as soon as possible, the contract called for “substantial completion” of the building no later than November 27, 2003. The contract defined “substantial completion” to mean possession of an “occupancy permit.” If the renovation was not substantially completed by that time, Porteo agreed to pay a $200 per day penalty. In the end, Porteo did not obtain the required “occupancy permit” until several months after the targeted completion date.

{¶ 4} Porteo commenced the instant action on September 28, 2004 and alleged that the contract was completed, but Eye Specialists owed an additional $31,061.13 for extra construction (change orders) that it had requested. Eye Specialists denied liability, counterclaimed for various alleged breaches of the contract, and requested compensatory damages in excess of $25,000. 1 Porteo denied any liability on the counterclaim.

{¶ 5} At the November bench trial, the parties focused on the change orders and their impact on the overall contract. Gary Cunningham, owner of Porteo, testified at length about numerous change orders Eye Specialists requested during construction. John Kendall, a carpenter and inspector, testified that roof leaks in the budding were caused by faulty installation of a generator. The witness explained it would take $8,000 to $10,000 to repair the roof. Likewise, Terry Lee Shultz, the clinic director for Eye Specialists, testified that he was quoted $10,000 to repair the roof. 2

{¶ 6} The trial court entered judgment for Porteo on December 1, 2006. The court concluded that due to the various change orders, Porteo was not at fault for the delay in completing the construction project. Further, the court ruled' that Porteo was due and owing $17,885.13 for additional work that it had performed.

{¶ 7} An appeal was taken from that judgment, but we dismissed it for lack of a final order due to an unresolved counterclaim. See Portco, Inc. v. Eye Specialists, Inc., 173 Ohio App.3d 108, 2007-Ohio-4403, 877 N.E.2d 709. On January 16, 2008, the trial court found that Eye Specialists failed to present any credible evidence in support of its counterclaim and, thus, entered judgment against them. This appeal followed.

*143 I

{¶ 8} Appellant’s first assignment of error involves the issue of monies owed to a materialman. West Virginia Electric, Inc. (“WVE”) was to supply an “emergency generator” to be used in operating rooms. A dispute arose between WVE and Porteo prompting WVE to file a mechanic’s lien against the property. That lien was released in this action when WVE defaulted on answer to Eye Specialists’ third-party complaint against them. Eye Specialists argues that because the hen was vacated, Porteo had no legal obligation to pay WVE for the generator and, thus, has been unjustly enriched by that amount. Eye Specialists therefore concludes that the amount of damages it was ordered to pay Porteo should be credited by the amount of the generator. We disagree. 3

{¶ 9} We believe that appellant fails to distinguish the mechanic’s lien and the contractual obligation (or debt) that underlies it. See Schlueter v. Shaheen (Nov. 8, 1989), Hancock App. No. 5-88-27, 1989 WL 138133 (courts consistently recognize separate enforcement of the lien and the underlying contract); Thrush v. Thrush (Apr. 26, 1988), Union App. No. 14-86-17, 1988 WL 40427 (distinction between mechanic’s lien and underlying debt). A mechanic’s lien (1) gives a materialman an interest in the property to secure payment for materials and (2) fixes the order of priority for that payment. The debt underlying the lien is completely separate.

{¶ 10} Here, the trial court’s order voiding the mechanic’s lien on Eye Specialists’ property removed WVE’s security in that property for payment of the generator. It did not affect the underlying debt Porteo owed WVE for that material.

{¶ 11} Accordingly, we find no merit in appellant’s first assignment of error, and it is hereby overruled.

II

{¶ 12} Appellant asserts in its second assignment of error that the trial court erred by failing to award damages under the contract due to Portco’s failure to complete all construction by the specified date.

{¶ 13} In its December 1, 2006 judgment, the trial court found that “it would be inappropriate to assess” a penalty for the failure to timely complete the *144 construction because the delay resulted from Eye Specialists’ change orders. Generally, an appellate court should not reverse a trial court’s factual finding if that finding is supported by some competent, credible evidence. Shemo v. Mayfield Hts. (2000), 88 Ohio St.3d 7, 10, 722 N.E.2d 1018; C.E. Morris Co. v. Foley Constr. Co. (1978), 54 Ohio St.2d 279, 8 O.O.3d 261, 376 N.E.2d 578, at the syllabus. This standard of review is highly deferential and even “some” evidence is enough to support a court’s judgment and prevent a reversal. See Barkley v. Barkley (1997), 119 Ohio App.3d 155, 159, 694 N.E.2d 989; Willman v. Cole, Adams App. No. 01CA725, 2002-Ohio-3596, 2002 WL 1560888, ¶ 24.

{¶ 14} Gary Cunningham, the owner of Porteo, testified about the numerous change orders that Eye Specialists requested.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

M.R. Durant Elec., L.L.C. v. Awesome87, L.L.C.
2017 Ohio 4331 (Ohio Court of Appeals, 2017)
Holiday Haven Members Assn. v. Paulson
2014 Ohio 3902 (Ohio Court of Appeals, 2014)
Solomon v. Harwood
2011 Ohio 5268 (Ohio Court of Appeals, 2011)
Williams v. Williams
2011 Ohio 1200 (Ohio Court of Appeals, 2011)
Bray v. Bray
2011 Ohio 861 (Ohio Court of Appeals, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
894 N.E.2d 84, 177 Ohio App. 3d 139, 2008 Ohio 3154, Counsel Stack Legal Research, https://law.counselstack.com/opinion/portco-inc-v-eye-specialists-inc-ohioctapp-2008.