Port Clinton v. Scagnetti Construction Co.

1 Ohio App. Unrep. 205
CourtOhio Court of Appeals
DecidedJanuary 12, 1990
DocketCase No. OT-88-47
StatusPublished

This text of 1 Ohio App. Unrep. 205 (Port Clinton v. Scagnetti Construction Co.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Port Clinton v. Scagnetti Construction Co., 1 Ohio App. Unrep. 205 (Ohio Ct. App. 1990).

Opinion

This is an appeal from a decision of the Ottawa County Court of Common Pleas in which the court vacated an arbitration award, granted summary judgment in favor of appellee, Scagnetti Construction Company, denied the city's motion for summary judgment and assessed costs against appellant, city of Port Clinton, Ohio.

Appellant, city of Port Clinton, Ohio, ("city"), sets forth the following assignments of error:

"I. THE COURT OF COMMON PLEAS ERRED IN VACATING THE ARBITRATION AWARD IN THIS PROCEEDING ON THE BASIS THAT THERE WAS A LACK OF JURISDICTION FOR THE ARBITRATION PANEL.
"II. THE COURT OF COMMON PLEAS ERRED IN NOT APPLYING SECTION 2305.06 O.R.C., THE FIFTEEN YEAR STATUTE OF LIMITATIONS FOR WRITTEN CONTRACTS IN THIS ACTION.
"III. IF APPELLANT'S CLAIMS IN THIS ACTION AGAINST APPELLEE, SCAGNETTI, SOUND IN TORT, THEN THOSE CLAIMS ARE GOVERNED BY THE TEN YEAR STATUTE OF LIMITATIONS FOUND IN SECTION 2305.131 O.R.C.
"IV. THE COURT OF COMMON PLEAS EXCEEDED ITS STATUTORY AUTHORITY AND COMMON LAW AUTHORITY IN REVIEWING THE ARBITRATION PROCEEDINGS HEREIN AND IN DETERMINING WHETHER TO CONFIRM, VACATE OR MODIFY THE AWARD."

The pertinent facts of this case are as follows. On July 15,1976, the city entered into a contract with Scagnetti to make improvements on certain already existing but sub-standard city streets. The written contract was prepared for the city by Don C. Waggoner, P.E.., Inc., who also prepared the plans and specifications and the remainder of the contract documents for the project and who supervised the work which was undertaken and completed. The work was completed by the fall of 1976. It is significant to note that upon the consulting engineer's recommendation and authorization, the city accepted the work and paid appellee Scagnetti. Final payment was made on January [206]*20624, 1977.

We first note the pertinent paragraphs of the contract drafted by the city and entered into by Scagnetti.

"29. GUARANTY
"29.1 The Contractor shall guarantee all materials and equipment furnished and Work performed for a period of one (1) year from the date of Substantial Completion. The Contractor warrants and guarantees for a period of (1) year from the date of Substantial Completion of the system that the completed system is free from all defects due to faulty materials or workmanship and the Contractor shall promptly make such corrections as may be necessary by reason of such corrections as may he necessary by reason of such defects including the repairs of any damage to other parts of the system resulting from such defects. The Owner will give notice of observed defects with reasonable promptness. In the event that the Contractor should fail to make such repairs, adjustments, or other Work that may be made necessary by such defects, the Owner may do so and charge the Contractor the cost thereby incurred.
The Performance Bond shall remain in full force and effect through the guarantee period.
"30. ARBITRATION
"30.1 All claims, disputes, and other matters in question arising out of, or relating to, the Contract Documents or the breach thereof, except for Documents or the breach thereof, except for claims which have been waived by the making and acceptance of final payment as provided by Section 20, shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association. This agreement to arbitrate shall be specifically enforceable under the prevailing arbitration law. The award rendered by the arbitrators shall be final, and judgment may be entered upon it in any court having jurisdiction thereof.
"30.2 Notice of the demand for arbitration shall be filled in writing with the other party to the Contract Documents and with the American Arbitration Association, and a copy shall be filed with the Engineer. Demand for arbitration shall in no event be made after institution of legal proceedings based on any claim, dispute or other matter in question which would be barred by the applicable statute of limitations."

Sometime in 1977, after the expiration of the one year maintenance period in the contract, the city noticed some deterioration in the form of some longitudinal cracks in the paving work done by Scagnetti. Apparently at the same time, similar problems were noted regarding roadways involved in other projects performed in 1973 by other contractors. Tests run by the city concluded that the cracks were the result of the design of the roadways that did not conform to generally accepted engineering practices. The city took no action against Scagnetti or the other contractors for these defects, other than to write to them about those conditions.

In June 1979, approximately two years and two winters after Scagnetti had paved the streets, the city noticed that certain portions of the surface of the roadways were deteriorating with a condition described as "spaulling." Thereupon, and in 1979, the city retained the services of several consulting engineering firms. At that point in time, the city took no action against Scagnetti or the other contractors nor did the city take any action to correct the problem or to do any maintenance work on the roads.

It was not until May 23,1984, that the city filed this action against Scagnetti and the Pot Clinton Lumber Company1, the concrete supplier to Scagnetti on the 176 project. In its complaint, the city alleged negligence based upon workmanship, although the city also alleged breach of contract and various warranties.

In June 1984, Scagnetti filed a motion to dismiss on the basis that the claim of the city was barred by the Statute of limitations and by the terms and conditions of the contract itself. The trial court denied this motion on August 21, 1984 and ordered Scagnetti to commence a separate action to enforce any arbitration rights if it was going to assert any arbitration rights as set forth in the contract. The lower court made this order interlocutory only, the entry not including any language suggestive of Civ. R. 54(B) to make the order final and appealable.

On or about September 7, 1984, Scagnetti filed a motion for reconsideration regarding the denial of its motion to dismiss on the [207]*207contractual and statute of limitations issues; a motion to stay proceedings; and a petition for order directing arbitration. On November 26, 1984, the trial court denied Scagnetti’s motion for reconsideration, again denied its motion to dismiss and again made its order interlocutory.

On March 8, 1985, the city filed a general demand for arbitration, "detailing" the nature of the dispute in three words - "breach of contract." In response, Scagnetti filed numerous motions to require the city to amplify and enumerate its claims. The arbitration panel, after two days of hearing on October 14 and 15, 1985, made an award of $25,000 in favor of the city. We would note at this juncture that this award bears no relationship whatsoever to the contract or damage evidence in the case, but rather approximates the city's expenditure for road tests. As far as we are aware, there was no evidence adduced at the arbitration hearing regarding the lack of good workmanship by Scagnetti. Throughout the proceedings, Scagnetti raised the defense of the statute of limitations, thus preserving it for the record.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vulcan-Cincinnati, Inc. v. United Steelworkers of America
173 N.E.2d 709 (Ohio Court of Appeals, 1960)
Colegrove v. Handler
517 N.E.2d 979 (Ohio Court of Appeals, 1986)
Pitts v. Ohio Department of Transportation
423 N.E.2d 1105 (Ohio Supreme Court, 1981)
Velotta v. Leo Petronzio Landscaping, Inc.
433 N.E.2d 147 (Ohio Supreme Court, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
1 Ohio App. Unrep. 205, Counsel Stack Legal Research, https://law.counselstack.com/opinion/port-clinton-v-scagnetti-construction-co-ohioctapp-1990.